Wallbridge Mining Company Limited (TSX: WM) (OTCQB:WLBMF) is pleased to announce assay results from the final four holes completed during the Phase 1 portion of its 2026 drilling campaign at its 100% owned Martiniere gold project. Phase 1 drilling was comprised of six holes focused on the Bug Lake deformation corridor, which hosts the majority of the Martiniere mineral resource.

 

HIGHLIGHTS*

 

  MR-26-143 18.30 g/t Auover 1.4 m  
    6.10 g/t Auover 1.5 m  
  MR-26-144 8.67 g/t Auover 1.8 m Including 18.70 g/t Au over 0.8 m
    10.49 g/t Auover 2.5 m Including 8.94 g/t Au over 0.5 m
      36.10 g/t Au over 0.5 m
    3.69 g/t Auover 2.8 m Including 7.09 g/t Au over 1.4 m
    4.34 g/t Auover 10.0 m Including 4.86 g/t Au over 1.3 m
      4.27 g/t Au over 3.8 m
      16.43 g/t Au over 1.1 m
    2.25 g/t Auover 8.4 m Including 11.90 g/t Au over 0.6 m
  MR-26-145 8.21 g/t Auover 1.4 m  
    5.50 g/t Auover 1.4 m  
    4.66 g/t Auover 1.6 m  
    10.10 g/t Auover 1.5 m Including 30.20 g/t Au over 0.5 m
  MR-26-146 9.95 g/t Auover 3.0 m Including 31.70 g/t Au over 0.9 m
    3.46 g/t Auover 6.3 m Including 16.20 g/t Au over 0.9 m
    2.63 g/t Auover 9.8 m Including 5.14 g/t Au over 2.8 m
      3.30 g//t Au over 2.0 m
       
* True widths are estimated to be 70-90% of the reported core interval lengths.
 
 

“The results from Phase 1 of our 2026 drilling campaign build on the success of our 2025 drilling program and further strengthen our confidence in the scale and continuity of the Martiniere gold system,” commented Brian Penny, Chief Executive Officer of Wallbridge. “All six Phase 1 holes intersected multiple gold-bearing structures, including several high-grade intervals within broader zones of shear-hosted mineralization along the Bug Lake corridor. Since drilling began in early 2025, we have continued to expand the mineralized footprint beyond the limits of the current mineral resource while demonstrating that the system continues to remain open for further expansion laterally and at depth. These results provide a strong foundation as we continue evaluating Martiniere’s potential to support meaningful future resource growth.”

 

On March 16, 2026, the Company announced the commencement of a two-phase 17,000 metre exploration drilling program at Martiniere. Phase 1 was completed as scheduled on May 14, 2026, and comprised six holes totaling 4,108 metres. The Phase 2 drilling campaign, originally scheduled to commence in early July, has been temporarily postponed due to nearby forest fires. The planned exploration program at Martiniere will be reassessed once the evacuation order (as detailed below) is lifted.

 

On July 2, 2026, the Company announced that it had temporarily suspended all drilling and related exploration activities on its Detour-Fenelon Gold Trend Property following an evacuation order issued by SOPFEU (Société de protection des forêts contre le feu) and Quebec’s Ministère des Ressources naturelles et des Forêts due to increasing wildland fire danger in the area. The project site remains subject to the evacuation order, and exploration activities will resume only when the relevant authorities determine that conditions to return to the area are safe. The Company will provide an update on its exploration plans for the remainder of the 2026 field season once permission to re-enter the site and resume exploration activities has been granted.

 

Martiniere 2026 Drilling Program

 

The objective of the 2026 program is to further evaluate Martiniere’s growth potential through systematic widely spaced step-out drilling targeting the projected extensions of principal structures controlling gold mineralization beyond the limits of the currently defined mineral resource.

 

Five of the six Phase 1 holes were drilled across an approximate 350 metre long by 300 metre wide section of the Dragonfly shear zone as it extends along strike to the southeast of the Bug Lake North and Bug Lake South zones. The sixth hole, MR-26-146, was drilled to test the down-dip continuation of gold mineralization in the Horsefly zone and along the southern margin of the Lac du Doigt fault.

 

Results from the first two holes of the Phase 1 campaign, MR-26-141A and MR-26-142, were reported in the Company’s May 11, 2026 news release, available on Wallbridge’s website and at www.sedarplus.ca. Summaries of the four holes reported in this release are provided below.

  • MR-26-143 (Section C-C’): Collared approximately 75 metres east of previously reported hole MR-26-142 and 135 metres up-dip of previously reported hole MR-25-121 (see Wallbridge news release dated June 2, 2025). MR-26-143 intersected multiple mineralized intervals developed primarily along sheared contacts between felsic porphyry dikes and the surrounding basaltic host rocks. Significant intercepts include 18.30 g/t Au over 1.4 metres, 1.19 g/t Au over 7.4 metres, and 6.10 g/t Au over 1.5 metres.
  • MR-26-144 (Section C-C’): Collared approximately 40 metres east of MR-26-143, hole MR-26-144 intersected several well mineralized structures. Significant results include 8.67 g/t Au over 1.8 metres, 10.49 g/t Au over 2.5 metres, 3.69 g/t Au over 2.8 metres, and 4.34 g/t Au over 10.0 metres, and 2.25 g/t Au over 8.4 metres.
  • MR-26-145 (Section D-D’): Collared approximately 50 metres to the east of MR-26-144 and 80 metres up-dip of previously reported hole MR-25-130A (see Wallbridge news release dated September 29, 2025). MR-26-145 intersected a series of well-mineralized shear structures developed along the margins of felsic porphyry dikes and surrounding basalts. Significant results include 8.21 g/t Au over 1.4 metres, 5.50 g/t Au over 1.4 metres, 4.66 g/t Au over 1.6 metres, and 10.10 g/t Au over 1.5 metres.
  • MR-26-146 (Section B-B’): Collared near the eastern limit of the Bug Lake South mineral resource and drilled northward to test the down-dip projection of the Horsefly zone and Lac du Doigt fault farther north. This hole intersected a well-mineralized shear structure along a porphyry dike contact, followed by additional mineralized shears hosted in pillowed basalt and along the margin of the Lac du Doigt fault. Significant results include 9.95 g/t Au over 3.0 metres, 3.46 g/t Au over 6.3 metres, and 2.63 g/t Au over 9.8 metres.

 

Martiniere Geological Setting and Exploration Potential

 

The majority of the current Martiniere mineral resource occurs along the Bug Lake deformation corridor, a broad zone comprising a series of northwest-striking, southwest-dipping shear structures spatially associated with felsic intrusive dikes. These structures represent part of a larger drag-fold system related to the regional-scale Lac du Doigt fault.

 

The Lac du Doigt fault is interpreted to represent an important structural control on the emplacement and distribution of gold mineralization at Martiniere and currently marks the northern limit of systematic exploration drilling completed to date.

 

The Lac du Doigt fault is interpreted to form part of the broader Sunday Lake Deformation Zone fault system, a major regional structural corridor that extends across the Company’s approximately 600 km² Detour–Fenelon property and hosts the Detour Lake Mine approximately 45 kilometres west of Martiniere. Like other major deformation corridors in the Abitibi greenstone belt, the SLDZ is interpreted to have acted as a deep-seated conduit for hydrothermal fluids associated with gold mineralization.

 

Since early 2025, exploration drilling targeting the continuity and broader extent of the mineralized system has intersected significant gold mineralization across an area measuring approximately 2,000 metres along strike, 800 metres in width and extending to a vertical depth of at least 800 metres below surface. The system remains open for further expansion to the southeast, to the north and at depth.

 

Gold mineralization at Martiniere is primarily hosted within mafic volcanic rocks and younger felsic porphyry dikes. Mineralization occurs within discrete shear and breccia zones characterized by pyritic silica flooding, quartz-carbonate veining, and silica-sericite alteration. Higher gold grades are commonly concentrated along sheared dike contacts and within areas of increased deformation throughout the broader Bug Lake deformation corridor.

 

The current Martiniere mineral resource, published March 27, 2025, contains an estimated 346,000 ounces of gold averaging 2.29 g/t Au in the Indicated category and 387,000 ounces of gold averaging 3.11 g/t Au in the Inferred category. The estimate includes all drilling completed up to December 31, 2024, and therefore excludes all results from the Company’s 2025 and 2026 drilling programs.

 

Additional information is in the Company’s current NI43-101 Technical Report dated March 27, 2025, available on the Wallbridge website at www.wallbridgemining.com and under the Company’s profile at SEDAR+ at www.sedarplus.ca.

 

Significant gold assay intercepts for the four holes reported in this release are provided in the table below:

 

Martiniere Project 2026 Phase 1 – Drill Assay Highlights1
      From3 To3 Length3, 4 Au
Drill Hole VG*2   (m) (m) (m) (g/t)
DRAGONFLY ZONE            
  MR-26-143     207.6 209.0 1.4 18.30
        367.9 371.0 3.1 1.95
        416.0 423.4 7.4 1.19
        517.5 519.0 1.5 6.10
        555.0 556.9 1.9 2.81
  MR-26-144     232.9 234.7 1.8 8.67
    Including   232.9 233.7 0.8 18.70
        233.7 234.7 1.0 0.15
        392.5 395.0 2.5 10.49
    Including   392.5 393.0 0.5 8.94
    *   393.0 393.5 0.5 36.10
        393.5 395.0 1.5 2.46
        542.5 545.3 2.8 3.69
    Including   543.2 543.9 1.4 7.09
        543.9 545.3 1.4 0.40
        592.0 602.0 10.0 4.34
    Including   592.0 593.3 1.3 4.86
        593.3 597.1 3.8 0.63
        597.1 600.9 3.8 4.27
    *   600.9 602.0 1.1 16.43
        611.6 620.0 8.4 2.25
    Including   611.6 612.2 0.6 11.90
        612.2 613.0 0.8 0.50
        613.0 614.2 1.2 3.81
        614.2 619.0 4.8 0.60
        619.0 620.0 1.0 3.97
  MR-26-145     469.0 470.4 1.4 8.21
        489.4 490.8 1.4 5.50
        494.5 496.1 1.6 4.66
        531.5 533.0 1.5 3.53
        635.6 637.1 1.5 10.10
    Including   635.6 636.1 0.5 30.20
HORSEFLY ZONE            
  MR-26-146     336.2 339.2 3.0 9.95
    Including   336.2 337.1 0.9 31.70
        337.1 339.2 2.1 0.62
        453.4 459.7 6.3 3.46
    Including   453.4 454.9 1.5 0.28
        454.9 456.1 1.2 1.27
        456.1 457.0 0.9 16.20
        457.0 458.7 1.7 0.84
        458.7 459.7 1.0 3.86
        582.2 592.0 9.8 2.63
        582.2 584.2 2.0 1.66
        584.2 587.0 2.8 5.14
        587.0 590.0 3.0 0.49
        590.0 592.0 2.0 3.30
Notes            
1 Assay composites have been selected based on a combination of the following criteria: presence of observable mineralization; a Metal Factor>5 gm*m (MF = Au g/t * Interval length); a minimum interval length of ~1.4 metres.
2 Asterisk * denotes visible gold (VG) observed in drill core.
3 Reported drill hole depths and interval lengths have been rounded to the nearest 0.1 metres. As a result, interval lengths may vary slightly from differences calculated directly from drill hole depths reported here.
4 True widths are estimated to be within 70-90% of the reported core length intervals.
   
   

For more information, please refer to the links below for a drill hole location map, representative cross sections, and assay summaries of complete drill holes.

 

Martiniere Gold Project: 2026 Phase 1 Drill Hole Location Map Plan View
Martiniere Gold Project: 2026 Phase 1 Longitudinal Section A-A’
Martiniere Gold Project: 2026 Phase 1 Cross Section B-B’ MR-26-146
Martiniere Gold Project: 2026 Phase 1 Cross Section C-C’ MR-26-143 & 144
Martiniere Gold Project: 2026 Phase 1 Cross Section D-D’ MR-26-145
Martiniere Gold Project: 2026 Phase 1 Drill Assay Summary and Drill Hole Location Information

 

The Martiniere project is a key component of the Company’s ~600 km2 Detour-Fenelon Gold Trend property, Northern Abitibi, Quebec. Martiniere is located 30 kilometres west of the Company’s flagship Fenelon gold project and 45 kilometres east of Agnico Eagle’s Detour Lake gold mine, currently Canada’s largest producing gold mine.

 

Wallbridge Mining Detour – Fenelon Gold Trend Properties

 

Quality Assurance / Quality Control

 

Wallbridge maintains a Quality Assurance/Quality Control program for all its exploration projects using industry best practices. Key elements of the QA/QC program include verifiable chain of custody for samples, regular insertion of blanks and certified reference materials, and completion of secondary check analyses performed at a separate independent accredited laboratory. Drill core is halved, sampled, and shipped in sealed bags to Activation Laboratories Ltd. (ActLabs) in Val d’Or, Quebec, where samples are routinely analysed via fire assay with atomic absorption spectroscopy (‘AAS’) finish methods. For greater precision and accuracy, samples assaying 10 g/t Au or greater are re-distributed to other ActLabs facilities where they are re-assayed via metallic screen fire assay or fire assay/gravimetric finish, depending on the amount of sample material remaining available. Samples containing visible gold are routinely submitted directly for analysis by metallic screen fire assay method. Activation Laboratories Ltd. operates under a Quality Management System that conforms to the requirements of ISO/IEC 17025.

 

Qualified Person

 

The Qualified Person responsible for the technical content of this news release is Mr. Mark A. Petersen M.Sc., P.Geo. (OGQ AS-10796; PGO 3069), Senior Exploration Consultant for Wallbridge.

 

About Wallbridge Mining

 

Wallbridge is focused on creating value through the exploration and sustainable development of gold projects in Quebec’s Abitibi region while respecting the environment and communities where it operates. The Company holds a contiguous mineral property position totaling 598 square kilometres that extends approximately 82 kilometres along the Detour-Fenelon gold trend. The land position is host to the Company’s flagship PEA stage Fenelon Gold Project, and its earlier exploration stage Martiniere Gold Project, as well as numerous greenfield gold projects.

 

Posted July 14, 2026

Share this news article

MORE or "UNCATEGORIZED"


EraNova Produces 50 oz Silver Bar from Silver Surprise Mini-Bulk Sample at Local Atlin Facility

Confirms strong metallurgical potential and local processing capa... READ MORE

July 14, 2026

Standard Uranium Confirms Uranium Enrichment in All Winter 2026 Drill Holes at the Corvo Uranium Project

Standard Uranium Ltd. (TSX-V: STND) (OTCQB: STTDF) (FSE: 9SU0) ... READ MORE

July 14, 2026

CanAlaska Announces Results from Nebula Winter Drill Program

Drilling Program Confirms Significant Graphitic Fault Zones and Associat... READ MORE

July 14, 2026

Metals Creek Returns High-Grade Mineralization with 115.51 g/t Gold over 9.85 meters including 2050 g/t Gold over 0.50 meters at Ogden Gold Project in Timmins, Ontario

Second Highest Grade Intercept to Date on Ogden Project 115.51 g/... READ MORE

July 14, 2026

Copyright 2026 The Prospector News