Goldsource Provides Eagle Mountain Construction Update

 

 

 

 

 

Goldsource Mines Inc. is pleased to announce that construction at its Phase I Eagle Mountain Gold Project located in Guyana, South America is nearing completion and testing of selected plant components is underway. Plans for Phase I are based on the Preliminary Economic Assessment of the Eagle Mountain Saprolite Gold Project, Guyana Technical Report which called for a 1,000 tonnes per day open pit ‑ gravity plant and post-commissioning cash operating costs of US$500 to US$600 per ounce of gold.

 

 

Yannis Tsitos, President, stated, “We are generally pleased with Eagle Mountain’s construction progress with most of our mine construction tasks either completed or nearing completion. During shipment to site, an automation control panel was damaged which required replacement and has delayed our previously targeted year-end production by about 4 to 6 weeks. The replacement panel is currently being delivered by air-freight to Guyana. Testing of sections of the process circuit is in progress. We expect to be under budget with final commissioning and initial production to occur in early 2016.”

 

 

The PEA was prepared for the Company by ACA Howe International Limited, dated effective June 15, 2014, and filed September 16, 2014 on SEDAR at www.sedar.com. Further details on the PEA are also provided in the Company’s news release, dated July 31, 2014, available on the Company’s website together with the PEA at www.goldsourcemines.com.

 

 

ABOUT GOLDSOURCE MINES INC.

 

Goldsource Mines Inc is a Canadian resource company that is progressing its advanced-stage, 100%-owned Eagle Mountain Gold Project, located in Guyana, towards initial staged production in Q1 2016. Goldsource is led by an experienced management team, proven in making exploration discoveries and achieving project construction on time and on-budget.

 

Posted December 17, 2015

Share this news article

MORE or "UNCATEGORIZED"


Treasury Announces Closing of C$2.8 Million Bought Deal Private Placement

Treasury Metals Inc. (TSX: TML)is pleased to announce that ... READ MORE

November 21, 2019

AMEX Announces Partial Exercise of Underwriter’s Option for Additional Gross Proceeds of $981,900 and Aggregate Gross Proceeds of $8,982,000

Further to its press release dated November 7, 2019, Amex Explora... READ MORE

November 21, 2019

Barksdale Defines Shallow Copper Porphyry Drill Target at San Antonio

Barksdale Capital Corp. (TSX-V:BRO) (OTCQB:BRKCF) is pleased to a... READ MORE

November 21, 2019

Group Ten Closes Oversubscribed Private Placement Financings, Including Investments by Sprott Asset Management and GoldSpot Discoveries

Group Ten Metals Inc. (TSX-V: PGE) (OTC: PGEZF) (FSE: 5D32) is pl... READ MORE

November 21, 2019

Tectonic Metals Drills 6.03 g/t Au Over 28.95 Metres Discovering New Mineralized Structure at Tibbs Property

Tectonic Metals Inc. (TSX-V:TECT) announced assay results of its ... READ MORE

November 21, 2019

Copyright 2019 The Prospector News - Site design by Spyderbaby Productions