The Prospector News

Defense Metals Corp. Initial Drilling Results Yield 1.78% Over 192 Metres Total Rare Earth Oxide at Wicheeda; Including 3.13% Over 73 Metres

You have opened a direct link to the current edition PDF

Open PDF Close
Uncategorized

Share this news article

Defense Metals Corp. Initial Drilling Results Yield 1.78% Over 192 Metres Total Rare Earth Oxide at Wicheeda; Including 3.13% Over 73 Metres

 

 

 

 

 

Defense Metals Corp. (TSX-V: DEFN)  (OTCQB: DFMTF) (FSE: 35D) is pleased to announce results for the first two drill holes totalling 720 metres from the Company’s 2022 diamond drill program that is still underway. To date, a total of 15 drill holes totalling 4,800 metres have been completed of a planned 18 holes totalling 5,000 metres (96% complete) designed to upgrade existing resource categories. Drill holes WI22-64 and WI22-62, the first and third holes drilled, were collared from the two sites within the northern area of the Wicheeda Rare Earth Element (REE) deposit.

 

Infill drill hole WI22-64 (-65o dip / 204o azimuth) drilled southwest to depth within central area of the deposit yield a broad mineralized intercept of high-grade dolomite carbonate higher in the hole, and mixed mineralized xenolithic dolomite carbonate and syenite at depth averaging 1.78% total rare earth oxide (TREO) over 192 metres; including 3.13% TREO over 73 metres1 (Figure 1). The assays reported for WI22-64, one of the deepest holes drilled to date on the Wicheeda Project are partial from surface to a downhole depth of 284 metres. Assay results for the remaining 101 metres to end of hole at 384.5 metres are expected in the coming days.

 

Drill hole WI21-64 (-50o dip / 204o azimuth) collared 120 metres to the north of WI21-64, intersected a 109 metre drilled interval of mineralized dolomite carbonatite above a mixed xenolithic dolomite carbonatite and syenite at depth returning 1.39% TREO over 167 metres; including 2.29% TREO over 48 metres1 (Figure 2).

 

Kristopher Raffle, P.Geo. and Director and QP of Defense Metals stated: “We are pleased to have started receiving assays for our ongoing 2022 Wicheeda REE Deposit infill drilling campaign. These initial results compare very favourably to our PEA mineral resource cut-off of 0.5% TREO and continue to demonstrate continuity of mineralization over significant widths. We expect additional results in the coming days, weeks, and months ahead. With the 2022 drill campaign now 96% complete, we look forward to finishing a small number of remaining pit slope geotechnical and hydrogeological holes designed to inform any Preliminary Feasibility Studies.”

 

Table 1. Wicheeda REE Deposit 2022 Diamond Drill Intercepts

 

Hole ID From
(m)
To
(m)
Interval
(m)
TREO2 
(%)
Ce2O3
(%)
La2O3
(%)
Nd2O3
(%)
Pr2O3
(%)
Sm2O3
(ppm)
Gd2O3
(ppm)
Eu2O3
(ppm)
Dy2O3
(ppm)
Tb4O7
(ppm)
Ho2O3
(ppm)
WI22-64
(204/-65)
77 269.3 192.3 1.78 0.86 0.58 0.22 0.08 230 116 51 34 10 4
including 77 150 73 3.13 1.51 1.06 0.37 0.13 353 156 71 30 12 3
WI22-62
(204/-50)
93 260 167 1.39 0.68 0.43 0.18 0.06 222 101 43 29 9 4
including 121 169 48 2.29 1.13 0.72 0.29 0.10 316 123 54 22 9 2
__________________________
1The true width of REE mineralization is estimated to be 70-100% of the drilled interval.
2TREO % sum of CeO2, La2O3, Nd2O3, Pr6O11, Sm2O3, Eu2O3, Gd2O3, Tb4O7, Dy2O3 and Ho2O3.

 

About the Wicheeda REE Property

 

The 100% owned 4,244-hectare Wicheeda REE Property, located approximately 80 km northeast of the city of Prince George, British Columbia, is readily accessible by all-weather gravel roads and is near infrastructure, including power transmission lines, the CN railway, and major highways.

 

The Wicheeda REE Project yielded a robust 2021 preliminary economic assessment technical report (PEA) that demonstrated an after-tax net present value (NPV@8%) of $517 million, and 18% IRR3. A unique advantage of the Wicheeda REE Project is the production of a saleable high-grade flotation-concentrate. The PEA contemplates a 1.8 Mtpa (million tonnes per year) mill throughput open pit mining operation with 1.75:1 (waste:mill feed) strip ratio over a 19 year mine (project) life producing and average of 25,423 tonnes REO annually. A Phase 1 initial pit strip ratio of 0.63:1 (waste:mill feed) would yield rapid access to higher grade surface mineralization in year 1 and payback of $440 million initial capital within 5 years.

____________________________
3 Independent Preliminary Economic Assessment for the Wicheeda Rare Earth Element Project, British Columbia, Canada, dated January 6, 2022, with an effective date of November 7, 2021, and prepared by SRK Consulting (Canada) Inc. is filed under Defense Metals Corp.’s Issuer Profile on SEDAR (www.sedar.com).

 

Methodology and QA/QC

 

The analytical work reported on herein was performed by ALS Canada Ltd. at Langley (sample preparation) and Vancouver (ICP-MS fusion), B.C. ALS is an ISO-IEC 17025:2017 and ISO 9001:2015 accredited geoanalytical laboratory and is independent of the Defense Metals and the QP. Drill core samples were subject to crushing at a minimum of 70% passing 2 mm, followed by pulverizing of a 250-gram split to 85% passing 75 microns. A 0.1-gram sample pulp was then subject to multi-element ICP-MS analysis via lithium-borate fusion to determine individual REE content (ME-MS81h). Defense Metals follows industry standard procedures for the work carried out on the Wicheeda Project, with a quality assurance/quality control program. Blank, duplicate, and standard samples were inserted into the sample sequence sent to the laboratory for analysis. Defense Metals detected no significant QA/QC issues during review of the data.

 

Qualified Person

 

The scientific and technical information contained in this news release as it relates to the Wicheeda REE Project has been reviewed and approved by Kristopher J. Raffle, P.Geo. (BC) Principal and Consultant of APEX Geoscience Ltd. of Edmonton, AB, a director of Defense Metals and a “Qualified Person” as defined in NI 43-101. Mr. Raffle verified the data disclosed which includes a review of the sampling, analytical and test data underlying the information and opinions contained therein.

 

About Defense Metals Corp.

 

Defense Metals Corp. is a mineral exploration and development company focused on the acquisition, exploration and development of mineral deposits containing metals and elements commonly used in the electric power market, defense industry, national security sector and in the production of green energy technologies, such as, rare earths magnets used in wind turbines and in permanent magnet motors for electric vehicles. Defense Metals owns 100% of the Wicheeda Rare Earth Element Property located near Prince George, British Columbia, Canada.

 

 


Figure 1. Drill Section Holes WI22-64 (CNW Group/Defense Metals Corp.)

 

 


Figure 2. Drill Section Holes WI22-62 (CNW Group/Defense Metals Corp.)

 

Posted September 22, 2022

Share this news article

MORE or "UNCATEGORIZED"


PPX Mining Announces Closing Of $1.35 Million Private Placement

PPX Mining Corp. is pleased to announce that it has closed its fu... READ MORE

April 19, 2024

Elevation Gold Reports Financial Results for Year Ended December 31, 2023, including $66.4M in Total Revenue

Elevation Gold Mining Corporation (TSX-V: ELVT) (OTCQB: EVGDF) i... READ MORE

April 18, 2024

Reunion Gold Announces the Signing of a Mineral Agreement With the Government of Guyana for Its Oko West Project

Reunion Gold Corporation (TSX-V: RGD; OTCQX: RGDFF) is pleased to announ... READ MORE

April 18, 2024

Drilling Confirms 4 km of Favourable Corridor at Lynx Gold Trend

Puma Exploration Inc. (TSX-V: PUMA) (OTCQB: PUMXF) is thrilled to... READ MORE

April 18, 2024

Grid Metals Intersects 7 m at 1.28% Li2O at over 125 m Below the Previously Deepest Drill Holes at Donner Lake; Provides Project Update

Grid Metals Corp. (TSX-V:GRDM) (OTCQB:MSMGF) is pleased to announ... READ MORE

April 18, 2024

Copyright 2024 The Prospector News