IAMGOLD Corporation (NYSE: IAG) (TSX: IMG) reported its financial and operating results for the third quarter ended September 30, 2026.

 

“IAMGOLD delivered another quarter of strong performance, operating safely across our sites and producing 186,900 attributable ounces. We remain on track to achieve our full-year guidance of 720,000 to 820,000 ounces,” said Renaud Adams, President and Chief Executive Officer of IAMGOLD. “The Company generated $404 million in mine-site free cash flow, our net cash position increased resulting in available liquidity of $1.6 billion. We returned a further $135 million to shareholders through our share buyback, bringing total repurchases to nearly $600 million since the program began last December. Westwood is tracking toward the upper end of its production guidance, with higher-grade underground ore driving robust mine-site free cash flow year to date. Essakane remained a significant cash flow contributor, supporting our shareholder returns. At Côté, the operation completed its first full quarter without contractor crushing and operated above nameplate capacity in September, positioning the mine to deliver its strongest quarter of the year in the fourth quarter.”

 

“Looking ahead, we expect to deliver several key milestones over the coming quarters. The updated Côté mine plan, expected later this year, will be the first in a series of studies across our portfolio through 2027. These include an extended mine life at Essakane, a preliminary economic assessment for the Nelligan Mining Complex and Westwood’s underground expansion potential. The upcoming repurchase of half of Franco-Nevada’s royalty on Côté will further increase our exposure to one of Canada’s largest gold mines. With a strong balance sheet, a clear growth pipeline and long-life Canadian assets, we are building IAMGOLD into a leading, modern, Canadian-focused gold producer.”

 

HIGHLIGHTS:

 

Operating and Financial

  • Attributable gold production was 186,900 ounces in the third quarter and 558,600 ounces year-to-date, with the Company on track to achieve its 2026 production guidance of 720,000 to 820,000 ounces.
    • Côté produced 64,400 attributable ounces (92,000 ounces | 100%) in the third quarter and 184,000 attributable ounces YTD (262,900 ounces | 100%). Production at Côté is expected to be higher in the fourth quarter of the year due to higher grades from mine sequencing and increased processing rates;
    • Westwood produced 28,500 ounces in the third quarter and 97,100 ounces YTD. During the quarter, the mill team identified gold-bearing sludge type material that had accumulated at the bottom of the pregnant solution tank in the electrowinning circuit. For further details, refer to the “Westwood” section below;
    • Essakane produced 94,000 attributable ounces (110,500 ounces | 100%) in the third quarter and 277,500 attributable ounces (326,400 ounces | 100%) YTD.
  • Revenues in the third quarter totaled $856.5 million from sales of 199,900 ounces at an average realized gold price1 of $4,277 per ounce and $2,743.5 million YTD from sales of 606,500 ounces at an average realized gold price of $4,514 per ounce.
  • Cost of sales per ounce sold was $1,622 ($1,630 YTD), cash cost1 per ounce sold, excluding royalties was $1,266 ($1,251 YTD), cash cost1 per ounce sold, including royalties was $1,614 ($1,621 YTD).
  • All-in sustaining cost1  per ounce sold, excluding royalties, was $1,836 ($1,821 YTD) and AISC1 per ounce sold, including royalties was $2,184 ($2,191 YTD).
  • Net earnings and adjusted net earnings attributable to equity holders1 for the third quarter was $297.0 million ($907.2 million YTD) and $237.0 million ($869.7 million YTD), respectively.
  • Net earnings and adjusted net earnings per share attributable to equity holders1 for the third quarter of $0.52 ($1.57 YTD) and $0.42 ($1.50 YTD), respectively.
  • Net cash from operating activities was $461.1 million for the third quarter ($1,476.1 million YTD). Net cash from operating activities, before movements in working capital and non-current ore stockpiles1, was $422.9 million for the third quarter ($1,495.3 million YTD).
  • Earnings before interest, income taxes, depreciation and amortization1 was $584.4 million for the third quarter ($1,736.7 million YTD), and adjusted EBITDA1 was $503.9 million ($1,677.5 million YTD).
  • Mine-site free cash flow1 was $404.3 million during the third quarter ($1,297.8 million YTD).
  • The Company has available liquidity1 of $1,613.4 million as at September 30, 2026. Cash and cash equivalents was $766.6 million and the available balance of the revolving credit facility  was $845.8 million. Net cash, excluding leases and letters of credit1, was $317.6 million.
  • In health and safety, for the quarter ended September 30, 2026, the Company reported a total recordable injuries frequency rate of 0.58 and is tracking at 0.57 for the year. IAMGOLD is continuing to advance its critical risk management program and visible leadership to improve safety and reduce high-potential incidents.

 

Corporate

  • The Company purchased $134.7 million IAMGOLD shares (7.6 million shares) as part of the share buyback program during the quarter. The Company has purchased 32.1 million shares for $592.6 million since the inception of the program in December 2025. Subject to applicable TSX approval, the Company intends to continue to use cash flow from Essakane to repurchase shares under a share buyback program as cash is generated and repatriated from Essakane.
  • Total cash repatriated from Essakane in the third quarter was $87.8 million, and $497.6 million YTD. An additional $135.8 million was repatriated subsequent to quarter end. The cash was repatriated from the dividend declared in 2026 of approximately $500 million from Essakane’s 2025 profits. The Company’s portion, net of the Government of Burkina Faso portion and withholding taxes, is approximately $400 million, of which $223.6 million has been received to date. The remaining balance is expected to be distributed at regular intervals based on the cash generated in excess of working capital requirements by Essakane.
  • On August 10, 2026, the Company announced it has completed the divestiture of its 35% interest in the Bambadji Joint Venture in Senegal, generating $69.7 million in cash proceeds, before taxes and transaction costs of $21.7 million, for net proceeds of $48.0 million, monetizing a non-core exploration asset and further strengthening focus on IAMGOLD’s operating and development portfolio.
  • On November 5, 2026, the Company delivered to Franco Nevada (“FNV”) an irrevocable notice exercising its contractual right to repurchase 50% of FNV’s existing 7.5% Gross Margin Royalty (“GMR”) over the Côté Gold Mine. Upon completion of the repurchase, the GMR payable by the UJV to FNV will be reduced from 7.5% to 3.75%. Sumitomo Metals Mining Co., Ltd (“SMM”), through SMM Gold Cote Inc. (“SMMGC”) elected not to participate in the repurchase. Accordingly, IAMGOLD will fund the full repurchase price, estimated to be approximately $525 million and will retain the full economic benefit of the 50% GMR repurchase, pursuant to the arrangements between the Company, SMM and SMMGC. After giving effect to the 50% repurchase of the FNV GMR and the related arrangements between IAMGOLD, SMM and SMMGC, IAMGOLD’s GMR burden in respect of its 70% interest in the Coté Gold Mine is expected to reduce from 7.5% to 3.75% following the exercise of its option and reduce further to an effective GMR of 2.14% due to IAMGOLD exercising SMM’s 30% portion as well. The transaction is expected to close in December 2026, with economic effect from January 1, 2027.
  • On August 6, 2026, the Company announced that Ms. Catherine McLeod-Seltzer has been appointed to the Company’s Board of Directors effective September 1, 2026. Ms. McLeod-Seltzer, who was inducted into the Canadian Mining Hall of Fame in 2026, brings more than four decades of mining industry experience as both a senior executive and public-company director.

 

QUARTERLY REVIEW

 

For more details and the Company’s overall outlook for 2026, see “Outlook”, and for individual mines performance, see “Operations”. The following table summarizes certain operating and financial results for the three months ended September 30, 2026 (Q3 2026), September 30, 2025 (Q3 2025) and the nine months ended September 30 (YTD) 2026 and 2025, and certain measures of the Company’s financial position as at December 31, 2025.

 

 

Q3 2026 Q3 2025 YTD 2026 YTD 2025
Key Operating Statistics ($ millions)
Gold production – attributable (000s oz) 186.9 189.5 558.6 523.5
– Côté Gold1 64.4 74.6 184.0 192.7
– Westwood 28.5 22.7 97.1 76.0
– Essakane2 94.0 92.2 277.5 254.8
Gold sales – attributable (000s oz) 183.1 186.7 557.0 524.8
– Côté Gold1 59.2 75.9 181.2 195.9
– Westwood 28.3 20.7 95.0 76.5
– Essakane2 95.6 90.1 280.8 252.4
Cost of sales3 ($/oz sold) $ 1,622 $ 1,593 $ 1,630 $ 1,542
– Côté Gold1 $ 1,551 $ 1,323 $ 1,604 $ 1,272
– Westwood $ 1,817 $ 1,937 $ 1,552 $ 1,664
– Essakane2 $ 1,608 $ 1,740 $ 1,674 $ 1,714
Cash costs4 – excluding royalties ($/oz sold) $ 1,266 $ 1,338 $ 1,251 $ 1,321
– Côté Gold1 $ 1,243 $ 1,084 $ 1,283 $ 1,051
– Westwood $ 1,794 $ 1,924 $ 1,529 $ 1,648
– Essakane2 $ 1,122 $ 1,419 $ 1,136 $ 1,430
Cash costs4 ($/oz sold) $ 1,614 $ 1,588 $ 1,621 $ 1,537
– Côté Gold1 $ 1,544 $ 1,320 $ 1,597 $ 1,269
– Westwood $ 1,794 $ 1,924 $ 1,529 $ 1,648
– Essakane2 $ 1,603 $ 1,737 $ 1,667 $ 1,711
AISC4 – excluding royalties ($/oz sold) $ 1,836 $ 1,706 $ 1,821 $ 1,753
– Côté Gold1 $ 1,755 $ 1,358 $ 1,768 $ 1,395
– Westwood $ 2,118 $ 2,793 $ 1,980 $ 2,310
– Essakane2 $ 1,582 $ 1,596 $ 1,595 $ 1,704
AISC4 ($/oz sold) $ 2,184 $ 1,956 $ 2,191 $ 1,969
– Côté Gold1 $ 2,056 $ 1,594 $ 2,082 $ 1,613
– Westwood $ 2,118 $ 2,793 $ 1,980 $ 2,310
– Essakane2 $ 2,063 $ 1,914 $ 2,126 $ 1,985
Average realized gold price ($/oz) $ 4,277 $ 3,492 $ 4,514 $ 3,153

 

  1. Attributable portion for Côté Gold is based on IAMGOLD’s ownership of 70%. See “Operations – Côté Gold, Canada” for more details.
  2. IAMGOLD’s Essakane ownership interest decreased from 90% to 85% effective June 20, 2025. See “Operations – Essakane, Burkina Faso” for more details. The attributable portion for Essakane is presented as 90% for the first half of 2025 and 85% thereafter throughout this news release.
  3. Excludes depreciation – as disclosed in the segment note in the consolidated interim financial statements.
  4. Refer to the “Non-GAAP Financial Measures” disclosure at the end of this news release for a description and calculation of these measures.

 

 

Q3 2026 Q3 2025 YTD 2026 YTD 2025
Financial Results ($ millions)
Revenues $ 856.5 $ 706.7 $ 2,743.5 $ 1,764.7
Gross profit $ 406.0 $ 272.6 $ 1,391.8 $ 612.6
EBITDA1 $ 584.4 $ 338.4 $ 1,736.7 $ 817.4
Adjusted EBITDA1 $ 503.9 $ 359.5 $ 1,677.5 $ 840.4
Net earnings attributable to equity holders $ 297.0 $ 139.4 $ 907.2 $ 257.8
Adjusted net earnings attributable to equity holders1 $ 237.0 $ 170.9 $ 869.7 $ 303.4
Net earnings per share attributable to equity holders $ 0.52 $ 0.24 $ 1.57 $ 0.45
Adjusted net earnings per share attributable to equity holders1 $ 0.42 $ 0.30 $ 1.50 $ 0.53
Net cash from operating activities before changes in working capital1 $ 422.9 $ 280.6 $ 1,495.3 $ 512.8
Net cash from operating activities $ 461.1 $ 280.8 $ 1,476.1 $ 440.9
Basic weighted average number of common shares outstanding (in millions) $ 570.4 $ 575.2 $ 578.6 $ 574.3
Mine-site free cash flow1 $ 404.3 $ 292.3 $ 1,297.8 $ 572.4
Capital expenditures1 – sustaining $ 86.3 $ 59.9 $ 271.2 $ 200.0
Capital expenditures1 – expansion $ 23.4 $ 10.4 $ 58.2 $ 24.6

 

September 30 December 31
2026 2025
Financial Position ($ millions)
Cash and cash equivalents $ 766.6 $ 421.9
Long-term debt $ 449.2 $ 649.8
Net cash (debt) excluding lease liabilities and letters of credit $ 317.6 $ (228.1 )
Net cash (debt)1 $ 213.9 $ (344.4 )
Available Credit Facility $ 845.8 $ 445.7

 

  1. Refer to the “Non-GAAP Financial Measures” disclosure at the end of this news release for a description and calculation of these measures.

 

OUTLOOK

 

Production (000 oz)

 

YTD 2026 Full Year
Guidance 2026
Côté Gold – (70%) 184.0 270 – 310
Westwood – (100%) 97.1 110 – 130
Essakane – (85%) 277.5 340 – 380
Total attributable production (000s oz) 558.6 720 – 820

 

 

Total attributable production for IAMGOLD in 2026 is expected to be in the range of 720,000 to 820,000 ounces. Production at Côté is expected to be highest in the fourth quarter, driven by increased processing rates and grades as recent operational improvements continue to be realized and the mine enters higher grade zones. The 2026 production outlook excludes any potential production from the gold-bearing sludge material discovered in the electrowinning pregnant solution tank at Westwood. For further details, refer to the “Operations” section of each mine below.

 

Costs

 

YTD 2026 Full Year
Guidance3 2026
Côté Gold
Cash costs – excluding royalties ($/oz sold) $1,283 $900 – $1,050
Cash costs – including royalties3 ($/oz sold) $1,597 $1,200 – $1,350
AISC – excluding royalties3 ($/oz sold) $1,768 $1,475 – $1,625
AISC – including royalties3 ($/oz sold) $2,082 $1,775 – $1,925
Westwood
Cash costs ($/oz sold) $1,529 $1,500 – $1,650
AISC ($/oz sold) $1,980 $1,950 – $2,100
Essakane
Cash costs – excluding royalties ($/oz sold) $1,136 $1,150 – $1,300
Cash costs – including royalties3 ($/oz sold) $1,667 $1,600 – $1,750
AISC – excluding royalties3 ($/oz sold) $1,595 $1,550 – $1,700
AISC – including royalties3 ($/oz sold) $2,126 $2,000 – $2,150
Consolidated
Cost of sales1 ($/oz sold) $1,630 $1,425 – $1,575
Cash costs1,2 – excluding royalties ($/oz sold) $1,251 $1,100 – $1,250
Cash costs1,2 – including royalties3 ($/oz sold) $1,621 $1,425 – $1,575
AISC1,2 – excluding royalties3 ($/oz sold) $1,821 $1,675 – $1,825
AISC1,2 – including royalties3 ($/oz sold) $2,191 $2,000 – $2,150

 

  1. Consists of Côté Gold, Westwood and Essakane on an attributable basis of 70%, 100%, and 85%, respectively.
  2. This is a non-GAAP financial measure. See “Non-GAAP Financial Measures”.
  3. Guidance for cash costs and AISC, including royalties, assumes a $4,000 per ounce gold price in the estimate of royalties per ounce.

 

Cash costs on a consolidated basis, excluding royalties, are expected to be in the upper half of the range of $1,100 to $1,250 per ounce sold. Cash costs are expected to be lowest in the fourth quarter of the year, reflecting the expected increase in Côté Gold’s production.

 

AISC on a consolidated basis, excluding royalties, is expected to be in the upper range of $1,675 to $1,825 per ounce sold.

 

The guidance for cash costs and AISC, including royalties, was established using a gold price assumption of $4,000 per ounce for the year. The amount of royalties included in cash costs and AISC was $370 per ounce year-to-date, $45 per ounce higher than guidance, as the average realized price of gold sold YTD was $4,514, or $514 per ounce above the gold price assumption used in guidance estimates. As a result, the Company expects to exceed the upper end of the AISC guidance range when including the impact of higher royalties.

 

Royalty Sensitivities

 

$ per ounce sold
Gold Price Consolidated Côté Gold Essakane
$3,500 $270 $245 $350
$4,000 (guidance price) $325 $300 $450
$4,500 $390 $340 $540
$5,000 $440 $385 $600

 

 

The realized gold price in the first nine months of the year averaged $4,514 per ounce. The full year guidance for 2026 is based on the following assumptions (before the impact of hedging): an average realized gold price of $4,000 per ounce, USD/CAD exchange rate of 1.35, EUR/USD exchange rate of 1.18, average Brent oil price of $65 per barrel and West Texas Intermediate (WTI) price of $65 per barrel. On oil price, the Company estimates that for a $10 per barrel increase, the impact on the direct cost of fuel would increase costs by approximately $12 per ounce, exclusive of broader indirect inflationary pressures on input costs and the supply chain.

 

During the first nine months of 2026, price escalation of approximately 3% has been observed across certain commodity inputs, which remained within the Company’s inflation expectations. The Company continuously evaluates key commodity indices and forward supplier pricing guidance to proactively identify areas of potential cost inflation to inform any price mitigation measures that may be warranted. For further information on the expected impacts from fluctuation in guidance assumptions, refer to the Sensitivity Impact table included in the “Financial Review” section.

 

Capital Expenditures

 

YTD 2026 Updated Full Year Guidance 20261 Previous Full Year Guidance
($ millions) Sustaining Expansion Total Sustaining Expansion Total Sustaining Expansion Total
Côté Gold (70%) $ 84.5 $ 44.5 $ 129.0 $ 130 $ 85 $ 215 $ 160 $ 85 $ 245
Westwood (100%) 41.6 12.0 53.6 55 30 85 55 30 85
Essakane (100%) 145.0 1.7 146.7 195 5 200 165 5 170
$ 271.1 $ 58.2 $ 329.3 $ 380 $ 120 $ 500 $ 380 $ 120 $ 500
Corporate 0.1 – 0.1 – – – – – –
Total2 $ 271.2 $ 58.2 $ 329.4 $ 380 $ 120 $ 500 $ 380 $ 120 $ 500

 

  1. Capital expenditures guidance (±5%).
  2. Includes $7 million of capitalized exploration and evaluation expenditures also included in the Exploration Outlook guidance table.

 

Sustaining capital expenditures are expected to be approximately $380 million ±5%. Sustaining capital at Côté Gold, on an attributable basis, is now expected to total $130 million ±5%, lower than the original guidance of $160 million due to the reprioritization of resources and deferral of less critical projects to 2027.

 

Sustaining capital at Essakane is expected to be $195 million, higher than the guidance of $165 million due to a change in the mining sequence that resulted in additional waste stripping.

 

Expansion capital expenditures are expected to total $120 million ±5% in 2026. The expansion capital at Côté Gold is to de-risk the contemplated Côté expansion; early works include basic mill infrastructure and a significant pushback to expand the operating area of the pit. At Westwood, expansion capital is for development and test mining to support the study of options to increase mining volumes from underground in the eastern zone.

 

Exploration Outlook

 

YTD 2026 Full Year Guidance 2026
($ millions) Capitalized Expensed Total Capitalized Expensed Total
Exploration projects – greenfield $ 6.9 $ 20.9 $ 27.8 $ 11 $ 34 $ 45
Exploration projects – brownfield 7.7 1.4 9.1 7 2 9
$ 14.6 $ 22.3 $ 36.9 $ 18 $ 36 $ 54

 

 

Exploration expenditures for 2026 are expected to be approximately $54 million, the majority of which will be expensed. The Nelligan Mining Complex is the primary focus for exploration in 2026, with an estimated spend of approximately $24 million (including the construction of certain infrastructure to support an expanding program), followed by Côté Gold at approximately $5 million attributed to IAMGOLD, and Essakane at approximately $6 million.

 

Income Taxes Paid and Depreciation Outlook

 

($ millions) YTD 2026 Updated Full Year Guidance 2026 Previous Full Year Guidance 2026
Depreciation expense $360.8 $480 (±5%) $480 (±5%)
Income taxes paid $184.5 $215 – $225 $205 – $215

 

 

The Company expects to pay cash taxes in the range of $215 to $225 million during 2026. Cash tax payments do not occur evenly by quarter, as amounts paid in a quarter can include payments of the final balance of the prior year taxes and payments of instalments for the current year, both required to be made at times as prescribed by different countries.

There are no significant cash taxes expected in respect of the new global minimum top-up taxes.

 

Depreciation expense for 2026 is expected to be $480 million (±5%) corresponding with production levels and depletion of certain pit phases for which waste stripping costs have been capitalized.

 

ENVIRONMENTAL, SOCIAL AND GOVERNANCE

 

Health and Safety

 

The TRIFR in the third quarter was 0.58 as of September 30, 2026, compared to 0.56 as of September 30, 2025, and tracking at 0.57 for the year. IAMGOLD continues to advance its critical risk management program and is currently on track to achieve our target of all sites achieving verification objectives.

 

Environmental

 

There were no significant environmental incidents reported for the quarter.

 

Social Performance

 

During the third quarter of 2026, IAMGOLD continued engagements with local communities and supported community-based initiatives. Notably, Essakane supported Sahelian Arts and Culture Days for Peace in Dori, an event that brought people together through music, art, and cultural expressions. Westwood hosted Westwood en Ville in partnership with the Abitibiwinni First Nation, showcasing cultural activities to foster broader community engagement.

 

Indigenous Relations

 

As a Canadian business committed to responding to the Truth and Reconciliation Commission of Canada’s Calls to Action, IAMGOLD is continuing to advance a company-wide initiative to articulate how it works with Indigenous peoples beyond reconciliation, towards a future that builds upon the Company’s experiences and reflects its values.

 

Earlier this year, IAMGOLD launched a 5-pathway Reconciliation Plan, along with new mandatory awareness training for all its Canada-based employees titled “Indigenous Peoples of Canada: An Introduction to History and Relationship”. By the end of September 2026, 95% of Canadian employees had completed the training. Site-specific reconciliation plans aligned with IAMGOLD’s corporate reconciliation framework will reflect the distinct operating contexts and priorities of partner Indigenous communities. In September, Côté Gold published their plan and Westwood is continuing to advance their planning.

 

Culture and Inclusion

 

IAMGOLD includes annual objectives to support its efforts in integrating culture and inclusion into the strategy and corporate scorecard, for the annual objectives, and tracks metrics in site and corporate reports for visibility and measurement. As of September 30, 2026, women accounted for 33% of the Company’s executive leadership team.

 

OPERATIONS

 

Côté Gold Mine (IAMGOLD interest – 70%) | Ontario, Canada

 

Q3 2026 Q3 2025 YTD 2026 YTD 2025
Key Operating Statistics (100% basis, unless otherwise stated)
Ore mined (000s t) 3,797 3,841 10,422 10,126
Grade mined (g/t) 0.93 0.96 0.93 0.90
Operating waste mined (000s t) 5,008 6,770 14,811 18,275
Capital waste mined (000s t) 3,606 853 8,240 5,626
Total material mined (000s t) 12,411 11,464 33,473 34,027
Strip ratio1 2.3 2.0 2.2 2.4
Ore milled (000s t) 2,879 2,988 8,093 8,015
Head grade (g/t) 1.10 1.18 1.10 1.15
Recovery (%) 90 94 92 93
Gold production (000s oz) – 100% 92.0 106.0 262.9 275.2
Gold production (000s oz) – 70% 64.4 74.6 184.0 192.7
Gold sales (000s oz) – 100% 84.6 108.0 258.5 279.9
Gold sales (000s oz) – 70% 59.2 75.9 181.2 195.9
Average realized gold price2 ($/oz) $ 4,335 $ 3,484 $ 4,503 $ 3,285
Financial Results ($ millions – attributable interest)        
Revenues $ 257.0 $ 263.6 $ 817.3 $ 644.0
Cost of sales3 91.9 100.0 290.7 249.1
Production costs 78.0 81.8 238.2 206.2
(Increase)/decrease in finished goods (3.9 ) 0.3 (4.4 ) 0.2
Royalties4 17.8 17.9 56.9 42.7
Cash costs2 91.4 99.8 289.3 248.5
Sustaining capital expenditures2 29.1 27.7 84.5 73.1
Expansion capital expenditures2 17.4 8.3 44.5 18.0
Total sustaining and expansion capital expenditures2 46.5 36.0 129.0 91.1
Earnings from operations 120.9 110.4 393.5 261.6
Mine-site free cash flow2 81.5 135.6 343.7 287.1
Unit costs per tonne2        
Mine costs per operating tonne mined2 $ 4.77 $ 4.51 $ 4.81 $ 4.00
Mill costs per tonne milled2 $ 18.92 $ 22.01 $ 21.25 $ 19.68
G&A costs per tonne milled2 $ 8.45 $ 6.14 $ 8.62 $ 6.73
Operating costs per ounce5        
Cost of sales excluding depreciation ($/oz sold) $ 1,551 $ 1,323 $ 1,604 $ 1,272
Cash costs2 – excluding royalties ($/oz sold) $ 1,243 $ 1,084 $ 1,283 $ 1,051
Cash costs2 ($/oz sold) $ 1,544 $ 1,320 $ 1,597 $ 1,269
AISC2 – excluding royalties ($/oz sold) $ 1,755 $ 1,358 $ 1,768 $ 1,395
AISC2 – including royalties ($/oz sold) $ 2,056 $ 1,594 $ 2,082 $ 1,613

 

  1. Strip ratio is calculated as waste mined divided by ore mined.
  2. This is a non-GAAP financial measure. See “Non-GAAP Financial Measures”.
  3. Excludes depreciation – as disclosed in the segment note in the consolidated interim financial statements.
  4. Includes the 7.5% gross margin royalty and various net smelter return royalties.
  5. Cost of sales, cash costs excluding royalties cash costs and AISC per ounce sold may not be calculated based on amounts presented in this table due to rounding.

 

Operations

 

Côté Gold attributable gold production in the third quarter 2026 was 64,400 ounces (92,000 ounces | 100%), lower by 10,200 ounces or 14% than the prior year period:

  • Mining activity totaled a quarterly record of 12.4 million tonnes in the third quarter 2026, higher by 0.9 million tonnes or 8% than the same prior year period. Ore tonnes mined were 3.8 million tonnes, slightly lower than the prior year period, due to a slightly higher strip ratio of 2.3:1 as mining activities progressed in pushback areas. The average grade mined was 0.93 g/t in the third quarter 2026, a decrease of 3% over the prior year period, in line with expectations as mining was focused on opening the pit further through the planned pushback.
  • Mill throughput in the third quarter 2026 totaled 2.9 million tonnes, a decrease of 4% over the prior year period due to an extended annual shutdown in August and the transition to owner-only crushing. In September, the Côté plant averaged 37,100 tonnes per day totaling 1.1 million tonnes, above nameplate capacity of 36,000 tpd.
  • Head grades in the third quarter 2026 averaged 1.10 g/t, 7% lower than the prior year period, at average recoveries of 90%, lower than in prior quarters due to downtime on one of the plant’s two Vertimills early in the quarter. As part of ongoing plant optimization and debottlenecking, work has begun on a third Vertimill, expected to be installed in early 2027. The reconciliation between the reserve models, grade control models, mill feed and production continue to be well within expected tolerances.
  • Operational improvements continued through the quarter, the first full quarter without external contractor crushing and associated rehandling. These included record crusher and high-pressure grinding rolls (“HPGR”) throughput in September and improvements in process delivering ore to the mill. These improvements, combined with access to higher-grade mining zones, position the operation for improved performance in the fourth quarter.

 

The Company discontinued the use of external contractor crushing by the end of June 2026. This supplemental crushing had originally been contracted in 2025 to support operational targets due to constraints in the crushing circuit which were addressed through the installation of a second cone crusher at the beginning of the year. Processing cost improvements were realized in June as contracted crushing was reduced, followed by further improvements in September with average processing costs averaging $15.36 per tonne over the month, down from an average of $21.98 per tonne over the prior four quarters. Additional operational benefits from the debottlenecked crushing circuit have been realized downstream with improved wear rates on the high-pressure grinding rolls (HPGR) rollers with better sized material now feeding the HPGR. A longer HPGR lifespan is expected to translate into reduced maintenance costs and improved crushing circuit availability. Improvements to mining unit costs are expected to be realized in the coming quarters as the mining fleet previously required to support the external contractor crushing is redeployed on mining activities supporting an increase in the tonnes mined.

 

Financial Performance (70% basis) – Q3 2026 Compared to Q3 2025

 

Production costs of $78.0 million during the three months ended September 30, 2026, were $3.8 million or 5% lower than the same prior year period primarily due to the discontinuation of the external contractor crushing services and reduced mill maintenance costs relative to the prior year period, partially offset by increased diesel prices resulting from the conflict in the Middle East, increased water treatment and environmental costs, and increased costs to support continuous improvement initiatives.

  • The Company continues to prioritize its plans to reduce mining and milling costs exiting 2026 at approximately $4/t and $15/t, respectively, and expects to realize further reductions in 2027 onwards as the remaining productivity improvement initiatives are implemented.
  • Mining costs averaged $4.77 per tonne mined during the three months ended September 30, 2026, an increase from prior year period due to higher diesel costs, increased contractor deployment and pioneering work related to the pit pushback, and increased cost of explosives consumed.
  • Milling costs were $18.92 per tonne milled during the three months ended September 30, 2026. Unit costs decreased in the third quarter due to the discontinuation of the external contractor crusher and higher labour costs to fill vacant positions in the mill. Unit costs improved in September, averaging $15.36 per tonne milled, as operating and maintenance processes adjusted to fully owner-operated crushing and the plant achieved record crusher and HPGR throughput, with 1.1 million tonnes milled.

 

G&A costs were $8.45 per tonne milled during the three months ended September 30, 2026.

 

Cost of sales, excluding depreciation, of $91.9 million was $8.1 million or 8% lower than the prior year period, primarily due to lower production costs and timing of sales. Cost of sales per ounce sold, excluding depreciation, of $1,551 was $228 or 17% higher due to lower sales volume offsetting the lower cost of sales.

 

Cash costs, excluding royalties, of $73.6 million were $8.3 million or 10% lower than the prior year period, primarily due to lower production costs and timing of sales. Cash cost per ounce sold, excluding royalties, of $1,243, was higher by $159 or 15%, due to lower production and sales volume offsetting lower cash costs.

 

Royalties during the three months ended September 30, 2026, were $17.8 million or $301 per ounce (19% of cash costs), 1% lower compared to the prior year period due to lower production and sales volume, offsetting the impact of higher gold prices.

 

Cash costs, including royalties, of $91.4 million were $8.4 million or 8% lower than the prior year period, primarily due to lower production costs and timing of sales. Cash cost per ounce sold of $1,544 was higher by $224 or 17% due to lower production and sales volume offsetting lower cash costs.

 

AISC per ounce sold of $2,056 was higher by $462 or 29%, primarily due to lower production and sales volume and higher sustaining capital expenditures, offsetting lower cash costs per ounce sold.

 

Capital expenditures totaled $46.5 million ($66.5 million | 100%) in the third quarter 2026. Sustaining capital expenditures totaled $29.1 million ($41.7 million | 100%), including $15.0 million of tailings infrastructure and related earthworks, $11.5 million of mobile equipment and critical spares, and $2.6 million of capital waste stripping. Expansion capital of $17.4 million ($24.8 million | 100%) included $12.8 million capital waste stripping for the Phase 2 pit expansion along the periphery of the current pit and $4.6 million of related infrastructure improvements.

 

Mine-site free cash flow, on an attributable basis, was $81.5 million ($116.4 million | 100%) for the three months ended September 30, 2026, with revenues of $257.0 million from gold sales of 59,200 ounces at the realized gold price of $4,335 per ounce, resulting in operating cash flows of $125.3 million ($179.0 million | 100%) offset by capital expenditures totaling $43.8 million ($62.6 million | 100%).

 

2026 Outlook

 

Côté Gold attributable production in 2026 is expected to be at the lower end of the guidance range of 270,000 to 310,000 ounces (390,000 to 440,000 ounces | 100%). The focus in 2026 is on stabilization, optimization, improving the cost structure, and preparing for the contemplated throughput increase and inclusion of Gosselin into the mine plan. Short to medium term capital investment is planned to improve the operating efficiency and cost structure while also systematically investing to derisk future expansions.

 

Mining activities in 2026 are planning a total of approximately 48 million tonnes of material mined, which includes the pushback to open up the pit to improve mine efficiency and prepare for the envisioned expansion. Mining rates are expected to increase in the fourth quarter of the year as the mining fleet supporting the external contractor crusher becomes available, the pioneering of the push back is mostly complete and with the commissioning of three new haul trucks. Mill throughput is expected to average 36,000 tpd (nameplate) over the course of the fourth quarter. Plant head grades are expected to average between 1.05 g/t and 1.15 g/t. Gold production is expected to be higher in the fourth quarter of the year based on increased throughput and higher grades in the final quarter of the year.

 

Cash costs, excluding royalties, at Côté Gold are expected to exceed the top end of the guidance range of $900 to $1,050 per ounce sold. Cash costs are expected to decrease in the fourth quarter on higher volumes, increased production and improved unit costs. Côté Gold relies on diesel to operate the haul trucks, while the shovels and processing plant are connected to the grid. The cost estimates for 2026 used an oil price assumption of $65 per barrel for WTI. It is estimated that a $10 increase in the price of oil per barrel would approximately equate to a $7 per ounce increase in costs, exclusive of broader indirect inflationary pressures on input costs and the supply chain.

 

AISC, excluding royalties, are expected to be at the top end of the guidance range of $1,475 to $1,625 per ounce sold. See “Outlook” for guidance and sensitivities on royalties.

 

Sustaining capital expenditures guidance for Côté Gold is now expected to total $130 million ±5% ($185 million | 100%), lower than the original guidance of $160 million due to the reprioritization of resources and deferral of less critical projects to 2027.

 

Expansion capital of $85 million ±5% ($120 million | 100%) mainly relates to the planned strategic pit pushback that will provide both operational flexibility in the near term and optionality for an expansion of operations, including the acceleration of certain activities that could provide near-term increases in throughput capacity, including an additional Vertimill in early 2027.

 

Expansion Opportunities

 

The Company is planning to release an updated Côté Gold mine plan and Mineral Reserve estimate in the fourth quarter of 2026, which will be included in a subsequent Technical Report shortly thereafter. The study will incorporate the recently consolidated Côté and Gosselin Mineral Resources and operating assumptions based on production experience to date.

 

The updated mine plan is expected to demonstrate a significant expansion of Mineral Reserves and life of mine, while outlining near-term opportunities to progressively increase plant throughput beyond the current nameplate, through further debottlenecking and targeted plant improvements, to support sustained processing rates of approximately 40,000 tpd. In parallel, the Company is continuing to evaluate opportunities for a larger-scale expansion of the processing plant, supported by the size and quality of the consolidated Côté-Gosselin resource base and the potential to support a substantially larger operation over the long term. Technical, infrastructure, and permitting studies are ongoing to determine the optimal scale, configuration, and development path to maximize the long-term value of the operation.

 

Exploration

 

On June 1, 2026, the Company announced an updated Mineral Resource estimate for the Côté Gold Mine that integrated the Côté and Gosselin zones into a consolidated block model with updated economic assumptions, ahead of the upcoming Côté updated mine plan and technical report discussed above.

 

This updated estimate is with an effective date of March 31, 2026, and highlights include:

  • Côté Gold Measured and Indicated (“M&I”) Mineral Resources (100% basis) on a consolidated basis of 20.3 million ounces of gold, an increase of approximately 2.2 million ounces, or 12%, compared with the December 31, 2025, statement.
  • Côté Gold Inferred Mineral Resources (100% basis) on a consolidated basis of 3.5 million ounces of gold, an increase of approximately 1.3 million ounces, or 61%, compared with the December 31, 2025, statement.

 

The exploration program at Côté Gold is ongoing with a focus on the Côté, Gosselin and saddle area. The 2026 Gosselin zone exploration program includes approximately 10,000 metres of diamond drilling to test the north and north-east extensions of the Gosselin zone and approximately another 10,000 metres of diamond drilling to test other targets in the regional land position. Approximately 1,300 metres were completed in the third quarter (5,700 metres YTD).

 

An infill drilling program of 20,000 metres is ongoing on the Côté zone. Approximately 4,500 metres of surface diamond drilling were completed in the third quarter 2026 (14,900 metres YTD including approximately 1,200 metres of geotechnical drilling completed in the first quarter). The infill drilling program was planned to improve resource confidence within the northeastern extension of the Côté deposit and convert Inferred Resources into the Indicated Resources category.

 

Westwood Complex (IAMGOLD interest – 100%) | Quebec, Canada

 

Q3 2026 Q3 2025 YTD 2026 YTD 2025
Key Operating Statistics
Underground lateral development (metres) 1,132 837 3,525 2,965
Ore mined (000s t) – underground 99 90 309 277
Ore mined (000s t) – open pit 122 315 291 822
Ore mined (000s t) – total 221 405 600 1,099
Grade mined (g/t) – underground 8.09 6.42 8.77 6.67
Grade mined (g/t) – open pit 1.13 0.99 0.97 1.11
Grade mined (g/t) – total 4.24 2.19 4.98 2.51
Ore milled (000s t) 309 250 899 855
Head grade (g/t) – underground 8.00 6.52 8.76 6.75
Head grade (g/t) – open pit 0.85 1.13 0.94 1.22
Head grade (g/t) – total 3.06 3.04 3.61 3.00
Recovery (%) 94 93 93 92
Gold production (000s oz) 28.5 22.7 97.1 76.0
Gold sales (000s oz) 28.3 20.7 95.0 76.5
Average realized gold price1 ($/oz) $ 4,244 $ 3,515 $ 4,552 $ 3,229
Financial Results ($ millions)        
Revenues $ 120.6 $ 72.8 $ 434.5 $ 248.0
Cost of sales2 51.4 40.0 147.4 127.2
Production costs 51.8 44.8 153.3 132.2
(Increase)/decrease in finished goods (0.4 ) (4.8 ) (5.9 ) (5.0 )
Cash costs1 50.7 39.8 145.3 126.0
Sustaining capital expenditures1 8.3 17.7 41.6 48.8
Expansion capital expenditures1 5.3 – 12.0 –
Total sustaining and expansion capital expenditures1 13.6 17.7 53.6 48.8
Earnings from operations 59.8 24.1 245.1 80.2
Mine-site free cash flow1 51.7 6.2 218.2 59.4
Unit costs per tonne1        
Underground mining cost per tonne mined $ 321.58 $ 312.22 $ 307.23 $ 296.60
Open pit mining cost per operating tonne mined $ 10.32 $ 8.18 $ 10.31 $ 7.38
Milling cost per tonne milled $ 25.96 $ 36.43 $ 30.01 $ 27.94
G&A cost per tonne milled $ 18.11 $ 22.95 $ 18.30 $ 19.48
Operating costs per ounce3        
Cost of sales excluding depreciation ($/oz sold) $ 1,817 $ 1,937 $ 1,552 $ 1,664
Cash costs1 ($/oz sold) $ 1,794 $ 1,924 $ 1,529 $ 1,648
AISC1 ($/oz sold) $ 2,118 $ 2,793 $ 1,980 $ 2,310

 

  1. This is a non-GAAP financial measure. See “Non-GAAP Financial Measures”.
  2. Excludes depreciation – as disclosed in the segment note in the consolidated interim financial statements.
  3. Cost of sales, cash costs excluding royalties, cash costs and AISC per ounce sold may not be calculated based on amounts presented in this table due to rounding.

 

Operations

  • Westwood gold production in the third quarter 2026 was 28,500 ounces, higher by 5,800 ounces or 26% compared with the same prior year period.
  • Underground mining activity in the third quarter 2026 of 99,000 tonnes of ore was higher by 9,000 tonnes or 10% than the same prior year period, due to favourable stope sequencing and improved mining recovery. The grade of 8.09 g/t Au was higher than the prior period mainly due to mine sequencing and reduced dilution.
  • Open pit mining activity in the third quarter 2026 of 122,000 tonnes of ore was lower by 193,000 tonnes than the same prior year period primarily due to the continued focus this year on waste stripping activities as part of the mining sequence to open up access to ore.
  • Mill throughput in the third quarter 2026 was 309,000 tonnes, 59,000 tonnes higher than the prior year period due to an extended shutdown occurring in the prior year period, whereas the mill shutdown occurred in the second quarter 2026. The average grade of 3.06 g/t was 1% higher than the same prior year period due to a higher ratio of higher-grade underground ore to lower grade open pit ore.
  • The mill achieved recoveries of 94% in the third quarter 2026, slightly higher than the same prior year period.
  • During the quarter, the Westwood mill team identified gold-bearing sludge type material that had accumulated at the bottom of the pregnant solution tank in the electrowinning circuit. The material is believed to have accumulated over a number of years. The material has been recovered and placed in drums with a total combined weight of 14,700 kilograms. Samples, that are not statistically representative, indicated the solids content ranging from 19% to 27% and gold content in the solids ranging from 6% to 47%. For illustrative purposes, assuming an average for solids and an average for gold content, the sludge could contain approximately 30,000 ounces gold. This illustration is not an estimate of recoverable gold, payable gold, production or the financial benefit that may ultimately be realized by the Company. Furthermore, given the nature of the material, the collection process and the variability of assay results, the Company does not have a representative sample of the material as a whole. Accordingly, the illustrated estimate is subject to significant uncertainty, should not be regarded as a reliable estimate and the actual quantity of gold recovered may differ materially. The material needs to be processed by an external refinery, and the Company expects the gold ultimately recovered from the material to be reflected in its fourth quarter production results, subject to completion of the refining and assay process. There can be no assurance as to the quantity of gold that will ultimately be recovered or recognized, or the timing of such recovery or recognition.

 

Financial Performance – Q3 2026 Compared to Q3 2025

 

Production costs of $51.8 million were higher by $7.0 million or 16% than the same prior year period, primarily due to increased drilling and stope preparation activities in the underground mine and increased maintenance costs due to increased volume, partially offset by lower milling costs due to the mill shutdown occurring earlier in the year. Underground mining costs per tonne mined were $321.58, higher by $9.36 per tonne or 3% than the same prior year period, resulting from the increase in advanced stope preparation and drilling activities. Milling costs of $25.96 per tonne were lower by $10.47 per tonne or 29% as the mill shutdown occurred in the second quarter relative to the third quarter in the prior year.

 

Cost of sales, excluding depreciation, of $51.4 million was higher by $11.4 million or 29% compared to the same prior year period due to higher production costs and lower levels of stockpiling. Cost of sales per ounce sold, excluding depreciation, of $1,817 was lower by $120 or 6%, due to increased production and sales volume offsetting the higher cost of sales.

 

Cash costs of $50.7 million were higher by $10.9 million or 27% compared to the prior year period due to higher production costs. Cash costs per ounce sold of $1,794 were lower by $130 per ounce or 7%, due to increased production and sales volume partially offset by higher cash costs.

 

AISC per ounce sold of $2,118 was lower by $675 per ounce or 24%, primarily due to lower cash costs per ounce, lower sustaining capital and increased production and sales volume.

 

Sustaining capital expenditures of $8.3 million included underground development and rehabilitation of $4.3 million and mill and mobile equipment of $4.0 million. During the quarter, $5.3 million was incurred on the work program underground on the eastern side of the Bousquet Fault (the “Eastwood” zone), to support the study of options to expand the mine.

 

Mine-site free cash flow was $51.7 million for the three months ended September 30, 2026, based on revenues of $120.6 million from gold sales of 28,300 ounces at a realized gold price of $4,244 per ounce, generating operating cash flows of $65.5 million offset by capital expenditures totaling $13.8 million.

 

2026 Outlook

 

Westwood production is expected to be at the upper end of the guidance range of 110,000 to 130,000 ounces in 2026. The 2026 production outlook excludes any potential production from the gold-bearing sludge material discovered in the electrowinning pregnant solution tank at Westwood as described above. Underground mining is planned for between 900 to 1,000 tonnes per day, and the Grand Duc open pit life was extended into 2027 based on the improved economics in the current gold price environment. Mill throughput is expected to total 1.2 million tonnes in 2026 with blended head grades expected to average 3.5 g/t over the course of the year.

 

Cash costs at Westwood are expected to be in the range of $1,500 to $1,650 per ounce sold and AISC in the range of $1,950 to $2,100 per ounce sold.

 

Sustaining capital expenditures guidance is $55 million (±5%), primarily consisting of underground development in support of the mine plan, the continued renewal of the mobile fleet and fixed equipment, and certain asset integrity projects at the Westwood mill. Expansion capital of $30 million is primarily associated with development works to support the study of options to expand the mine in the eastern parts of Westwood underground that could be amenable to bulk mining. Additional extensions to the Grand Duc pit continue to be investigated as an accretive opportunity for supplemental mill feed.

 

Expansion Opportunities

 

The Company plans to publish an updated technical report for Westwood in the second half of 2027 which is expected to highlight the potential for bulk mining in the eastern zone at depth in Westwood. This approach could potentially support higher overall underground throughput which conceptually would allow for increased gold production at improved mining costs. Increasing the proportion of underground ore processed through the plant would also help offset the expected decline in open-pit feed once the low-grade Grand Duc open pit is depleted.

 

Essakane Mine (IAMGOLD interest – 90% for H1 2025, 85% thereafter) | Burkina Faso

 

Q3 2026 Q3 2025 YTD 2026 YTD 2025
Key Operating Statistics1
Ore mined (000s t) 2,971 3,172 7,672 7,787
Grade mined (g/t) 1.17 1.16 1.09 1.15
Operating waste mined (000s t) 2,739 5,352 8,258 17,438
Capital waste mined (000s t) 5,277 130 18,970 5,031
Total material mined (000s t) 10,987 8,654 34,900 30,256
Strip ratio2 2.7 1.7 3.5 2.9
Ore milled (000s t) 3,294 3,094 9,671 9,319
Head grade (g/t) 1.18 1.18 1.18 1.06
Recovery (%) 89 92 89 91
Gold production (000s oz) – 100% 110.5 108.4 326.4 289.1
Gold production (000s oz) – attributable 94.0 92.2 277.5 254.8
Gold sales (000s oz) – 100% 112.4 105.9 330.3 286.4
Average realized gold price3 ($/oz) $ 4,255 $ 3,493 $ 4,509 $ 3,233
Financial Results1 ($ millions)        
Revenues $ 478.9 $ 370.3 $ 1,491.7 $ 926.8
Cost of sales4 180.7 184.2 552.8 491.2
Production costs 123.8 149.0 377.5 413.6
(Increase)/decrease in finished goods 2.8 1.5 (0.2 ) (3.0 )
Royalties5 54.1 33.7 175.5 80.6
Cash costs3 180.2 183.9 550.6 490.3
Sustaining capital expenditures3 48.8 15.1 145.0 78.0
Expansion capital expenditures3 0.7 2.1 1.7 6.6
Total sustaining and expansion capital expenditures3 49.5 17.2 146.7 84.6
Earnings from operations 229.2 134.7 754.3 311.1
Mine-site free cash flow3 271.1 150.5 735.9 225.9
Unit costs per tonne3        
Open pit mining cost per operating tonne mined $ 5.44 $ 7.13 $ 5.00 $ 6.25
Milling cost per tonne milled $ 18.74 $ 21.83 $ 19.35 $ 19.84
G&A cost per tonne milled $ 9.14 $ 9.52 $ 9.99 $ 9.12
Operating costs per ounce6        
Cost of sales excluding depreciation ($/oz sold) $ 1,608 $ 1,740 $ 1,674 $ 1,714
Cash costs3 – excluding royalties ($/oz sold) $ 1,122 $ 1,419 $ 1,136 $ 1,430
Cash costs3 ($/oz sold) $ 1,603 $ 1,737 $ 1,667 $ 1,711
AISC3 – excluding royalties ($/oz sold) $ 1,582 $ 1,596 $ 1,595 $ 1,704
AISC3 – including royalties ($/oz sold) $ 2,063 $ 1,914 $ 2,126 $ 1,985

 

  1. 100% basis, unless otherwise stated.
  2. Strip ratio is calculated as waste mined divided by ore mined.
  3. This is a non-GAAP financial measure. See “Non-GAAP Financial Measures”.
  4. Excludes depreciation – as disclosed in the segment note in the consolidated interim financial statements.
  5. Includes contributions made by the Essakane mine to the development fund for local communities, equating to 1% of total revenues.
  6. Cost of sales, cash costs excluding royalties, cash costs and AISC per ounce sold may not be calculated based on amounts presented in this table due to rounding.

 

Operations

 

Essakane attributable gold production in the third quarter 2026 was 94,000 ounces (110,500 ounces | 100%), an increase of 1,800 ounces or 2% from the prior year:

  • Mining in the third quarter 2026 totaled 11.0 million tonnes, higher by 2.3 million tonnes or 27% compared to the same prior year period. Ore mined totaled 3.0 million tonnes in the quarter at an average grade of 1.17 g/t, a decrease of 6% and an increase of 1%, respectively over the same year prior period. Capital waste mined increased from the prior period as mining progressed to open up the Lao pit as per the mine plan.
  • Mill throughput in the third quarter 2026 was 3.3 million tonnes at an average head grade of 1.18 g/t, 6% higher and in line with the same prior year period, respectively.
  • The mill achieved recoveries of 89% in the third quarter 2026, 3% lower than the same prior year period, due to lower gravity circuit performance and higher concentrations of graphitic carbon and sulfur in the ore feed from direct feed material.

 

The security situation in Burkina Faso continues to be a focus for the Company. Security-related incidents are still occurring in the country, and more broadly, the West African region, which has put pressure and complexity on supply chains. The Company continues to take proactive measures to ensure the safety and security of in-country personnel and is constantly adjusting its protocols and activity levels at the site in response to the security environment. The Company continues to invest in the security and supply chain infrastructure in the region and at the mine site. It is also incurring additional costs to bring employees, contractors, supplies, and inventory to the mine.

 

As at June 30, 2026, the entire $680.7 million of IAMGOLD’s portion of the dividend declared in 2025 had been successfully repatriated, including interest payments of $14.4 million. In June 2026, Essakane declared its 2026 dividend of approximately $500 million representing the full distribution of its 2025 earnings. IAMGOLD’s 85% portion of the dividend net of taxes, is approximately $400 million of which $87.8 million has been received during the third quarter 2026 and $135.8 million subsequent to quarter end. See “Financial Review – Dividend Payments from Essakane”.

 

The average royalty rate was 11% in the third quarter 2026 compared to 9% in the same prior year period, in addition to the contributions to the development fund for local communities equating to 1% of total revenues. The increase reflects the April 2025 royalty decree enacted by the Government of Burkina Faso, which raised the royalty rate to 8% at gold prices above $3,000/oz, with the rate increasing by an additional 1% for each $500/oz thereafter. The previous rate was 7% on all gold sold at or above $2,000/oz.

 

On October 12, 2026, Burkina Faso’s Ministry of Energy, Mines and Quarries issued an order under the 2024 Mining Code and Local Content Law requiring holders of industrial mining permits to deliver all doré production to approved refineries in Burkina Faso, effective November 1, 2026. The Company received a temporary exemption from this requirement. Discussions with the Government continue with a view to ensuring that local refining can operate at applicable international industry standards.

 

Financial Performance – Q3 2026 Compared to Q3 2025

 

Production costs of $123.8 million were lower by $25.2 million or 17%, due to a decrease in mining and milling costs. Mining costs were lower due to less costs being included in production costs resulting from a higher proportion of capitalized waste in the period and lower costs to mine the Lao pit as saprolite and transition material requires less drilling and blasting, which reduced explosives and energy consumption during the quarter. Milling costs were lower due to a reduction in grinding activity required, which resulted in lower consumption of grinding media and overall energy requirements, partially offset by increased leaching costs due to higher consumption of cyanide to address ore complexity.

 

Cost of sales, excluding depreciation, of $180.7 million was lower by $3.5 million or 2%, as a 61% increase in royalties was offset by lower production costs. Cost of sales per ounce sold, excluding depreciation, of $1,608 was lower by $132 per ounce or 8%, primarily due to higher production and sales volumes.

 

Royalties were $54.1 million or $481 per ounce (30% of cash costs); an increase of $163 per ounce compared to the prior year period resulting from higher gold prices and higher production and sales volume.

 

Cash costs, excluding royalties, of $126.1 million were lower by $24.1 million or 16%, primarily due to lower production costs. Cash costs per ounce sold, excluding royalties, of $1,122 per ounce were lower by $297 per ounce or 21%, primarily due to higher production and sales volumes and lower cash costs.

 

Cash costs, including royalties, of $180.2 million were lower by $3.7 million or 2% mainly due to lower production costs, partially offset by higher royalties, and total cash costs per ounce sold, including royalties, of $1,603 per ounce were lower by $134 or 8%, primarily due to higher production and sales volumes and lower cash costs.

 

AISC per ounce sold of $2,063 was higher by $149 per ounce or 8% due to higher sustaining capital expenditures, higher royalties compared to the prior period, partially offset by higher production and sales volumes and lower cash costs.

 

Total capitalized stripping of $28.5 million was higher by $27.6 million, due to the initial pushbacks of a pit expansion in the adjacent Lao pit, resulting in higher overall waste tonnes mined in the period decreasing the proportion of waste tonnes classified as operating waste consistent with the 2026 mine plan.

 

Sustaining capital expenditures, excluding capitalized stripping, of $20.3 million included tailings management of $4.8 million, capital spares of $4.5 million, mobile and mill equipment of $4.1 million, resource development of $3.1 million, generator overhaul of $1.4 million and other sustaining projects of $2.4 million.

 

Mine-site free cash flow, on a 100% basis, was $271.1 million for the three months ended September 30, 2026, with revenues of $478.9 million resulting from gold sales of 112,400 ounces at a realized gold price of $4,255 per ounce, producing operating cash flows of $321.8 million, offset by capital expenditures totaling $50.7 million.

 

2026 Outlook

 

Essakane attributable production is expected to be in the range of 340,000 to 380,000 ounces (400,000 to 440,000 ounces | 100%). Mining activities will predominantly target Phase 7 of the Essakane Main Zone and the adjacent Lao pit, with an estimated target of 43 to 46 million tonnes of material mined at a strip ratio between 3:1 to 4:1 with increased volumes of waste mining at the Lao pit. Mill throughput is expected to total near 13 million tonnes with head grades averaging 1.10 g/t Au.

 

Cash costs, excluding royalties, are expected to be in the range of $1,150 to $1,300 per ounce sold. AISC, excluding royalties, are expected at the top end of the guidance range of $1,550 to $1,700 per ounce sold. Costs at Essakane are impacted by the Burkinabe royalty structure described above which are uncapped and linked to gold prices. See “Outlook” for guidance and sensitivities on royalties.

 

Essakane mainly relies on diesel and heavy fuel oil to power the processing plant and operate the mining fleet. The cost estimates for 2026 used an oil price assumption of $65 per barrel for Brent. Fuel supply and cost have not yet been materially impacted by the conflict in the Middle East, though risks to supply and price have increased with an approximate 3.5% increase to fuel prices occurring in September. Based on the usage between milling and mining, it is estimated that a $10 increase in the price of oil per barrel would approximately equate to a $20 per ounce increase in cash costs and all-in sustaining cost, respectively, exclusive of broader indirect inflationary pressures on input costs and the supply chain. The Company is actively monitoring the situation and implementing measures that are within its control.

 

Sustaining capital expenditures guidance is expected to be $195 million (±5%), higher than the previous guidance of $165 million due to a change in the mining sequence that resulted in more waste stripping. The higher amount of capitalized waste stripping is partly offset by lower cash cost and the cash cost and AISC guidance remains unchanged. The sustaining capital guidance includes approximately $110 million of capitalized waste stripping to progress Phase 6 and into the Lao pit, as well as the ongoing replacement of certain equipment to improve efficiency and maintenance costs at Essakane, and the annual tailings dam program. The capitalized waste stripping is higher than estimated in the December 2023 technical report due to inclusion of the Lao pit and extension of estimated mine life into 2029.

 

Mine Life Extension Opportunities

 

The Company plans to issue an updated technical report mid-2027. The report is expected to illustrate the potential extension of Essakane’s mine life up to 2035 with additional phases in the Essakane pit and adjacent open pits.

 

Continued security incidents or related concerns could have a material adverse impact on future operating performance. The Company continues to actively work with authorities and suppliers to mitigate potential impacts and manage supply continuity, while also investing in additional infrastructure and supply inventory levels designed to secure operational continuity.

 

PROJECTS

 

Nelligan Mining Complex | Quebec, Canada

 

On December 19, 2025, and December 22, 2025, the Company acquired all of the issued and outstanding shares of each of Northern Superior and Orbec, respectively, by way of court-approved plan of arrangement for consideration of approximately $329.0 million and $14.2 million, respectively, in shares of the Company and cash. The Northern Superior acquisition consolidated the Philibert, Chevrier, Lac Surprise, and Croteau projects with

Orbec’s early-stage Muus project, and IAMGOLD’s Nelligan, Monster Lake and Anik projects.

 

The combined assets, together the “Nelligan Mining Complex”, consolidates the Chibougamau region with a dominant land position of approximately 134,000 hectares. The Nelligan Mining Complex is now positioned as one of the largest pre-production gold camps in Canada. The close proximity of the primary deposits to each other supports the conceptual vision of a central processing facility being fed from multiple ore sources within a 17-kilometre radius.

 

On February 17, 2026, the Company announced its updated Mineral Resources for the Nelligan Mining Complex. On a consolidated basis, the Nelligan Mining Complex reported a significant increase in Indicated and Inferred Mineral Resources. Indicated Resources increased 1.1 million ounces to a total of 4.3 million ounces at an average grade of 0.99 g/t Au. Inferred ounces increased 1.9 million ounces to a total of 7.5 million ounces at an average grade of 1.08 g/t Au.

 

The Company plans to issue an inaugural technical report for the Nelligan Mining Complex in mid-2027.

 

IAMGOLD has budgeted approximately $24 million for exploration activities within the Nelligan Mining Complex for 2026. The goal of the program will be to conduct thorough testing of Philibert, expand Nelligan and continue to test Monster Lake at depth, all in support of a conceptual preliminary economic assessment in 2027. The Company is planning to test high-priority targets within the region.

 

In January 2026, the Company exercised the option to acquire the remaining 25% interest in the Philibert property held by SOQUEM for the payment totaling C$3.5 million, completing the consolidation of 100% of the Philibert property.

 

Nelligan

 

The Company holds a 100% interest in Nelligan located approximately 45 kilometres south of the Chapais Chibougamau area in Québec.

 

On February 17, 2026, the Company announced its updated Mineral Resources for Nelligan of 3.7 million Indicated gold ounces in 122.0 million tonnes (“Mt”) at 0.95 grams per tonne gold (“g/t Au”), and 4.6 million Inferred ounces (151.0 Mt at 0.96 g/t Au). This represents an 18% increase in Indicated ounces, or 575,000 ounces at the same grade; as well as it represents a 10% decrease in Inferred ounces, or 514,000 ounces, at the same grade. This result is due in part to the infill program conducted last year to increase the confidence in ounces from Inferred Mineral Resources. Mineralization remains open along strike and at depth as demonstrated by encouraging results obtained from the depth exploration program conducted in 2025 (see news release dated September 15, 2025).

 

A diamond drilling program of 18,000 metres of expansion and delineation drilling was initially planned for 2026. This program has been expanded up to a total of 30,000 metres for year 2026. Approximately 9,700 metres were completed in the third quarter (24,800 metres YTD). The additional drilling is mainly dedicated to infill drilling for resources conversion.

 

Monster Lake

 

The Company holds a 100% interest in the Monster Lake Gold Project, which is located approximately 15 kilometres north of Nelligan in the Chapais Chibougamau area in Québec.

 

On February 17, 2026, the Company announced its updated Mineral Resources for Monster Lake of 243,000 tonnes of Indicated Mineral Resources averaging 13.0 g/t Au for 102,000 ounces of gold, and 1,046,000 tonnes of Inferred Mineral Resources averaging 14.8 g/t Au for 499,000 ounces of gold. A slight increase in Indicated ounces and Inferred ounces is noted.

 

A diamond drilling program of 15,000 metres was originally planned in 2026 to increase confidence in the existing resource and test at depth the Megane zone following positive results obtained from the 2025 drilling. This program has been expanded to a minimum of 20,000 metres. The depth extension requires further drilling to add to the current resource (see news release dated September 15, 2025). Approximately 7,000 metres were completed in the third quarter (18,100 metres YTD).

 

Philibert

 

Following the acquisition of the remaining 25% interest in the Philibert property held by SOQUEM during the first quarter, the Company holds a 100% interest in the Philibert Project which is located approximately 10 kilometres north-east of Nelligan in the Chapais Chibougamau area in Québec.

 

A diamond drilling program of a minimum of 20,000 metres was originally planned and could increase to 30,000 metres depending on ground conditions. The drilling program aims primarily to convert a significant portion of the Inferred Resource to the Indicated Resource category, and where possible, exploration drilling could test other prospective targets on the project area. Approximately 8,700 metres were completed in the third quarter, (28,000 metres YTD) dedicated mostly to depth extensions of some of the zones.

 

Anik

 

The Anik Gold Project is owned at 75% by IAMGOLD after the Company elected to exercise its first option to acquire an undivided interest of 75% in the project in May 2025 pursuant to an option agreement signed on May 20, 2020, with Auriginal Mining, successor to Kintavar Exploration Inc. The project is contiguous with the Nelligan Gold project to the north and east. The Company holds an option to earn up to 80% interest in the project by meeting certain commitments.

 

A 1,600 metres diamond drilling program was planned in 2026 for testing different targets in the eastern continuation of the Nelligan Deformation Zone. The program was completed in the first quarter 2026, and results are not significant.

 

Exploration

 

In the third quarter 2026, drilling activities on active projects and mine sites totaled approximately 56,600 metres (161,600 metres YTD). For additional information regarding the brownfield and greenfield exploration projects, see “Operations”. The Company’s exploration expenditures guidance for 2026 is $54 million.

 

($ millions) Q3 2026 Q3 2025 YTD 2026 YTD 2025
Exploration projects – greenfield $ 3.7 $ 5.7 $ 27.8 $ 17.5
Exploration projects – brownfield1 4.3 3.4 9.1 10.4
Total – all operations $ 8.0 $ 9.1 $ 36.9 $ 27.9

 

  1. Exploration projects – brownfield for the third quarter 2026 included near-mine exploration and resource development of $3.2 million (third quarter 2025 – $2.8 million), and $7.7 million for YTD 2026 (YTD 2025 – $8.8 million), which are capitalized.

 

FINANCIAL REVIEW

 

Liquidity and Capital Resources

 

The Company’s capital allocation strategy is to maximize value through the allocation of internally generated cashflows to support its operations, fund growth opportunities, return capital to its shareholders, and strengthen its balance sheet. The Company’s internally generated cashflows are conceptually differentiated by its Canadian operations and Essakane in Burkina Faso.

 

Cashflows from the Company’s Canadian Operations are strategically allocated to support the funding of:

  • Sustaining and optimizing the Canadian portfolio to support stable, cash-generative performance.
  • The contemplated Côté Gold expansion to incorporate Gosselin.
  • The potential mine life extension of Westwood and underground expansion into the eastern zone.
  • The continued advancement of the Nelligan project.
  • The repurchase of 50% of the Côté Gold Gross Margin Royalty from Franco-Nevada.
  • Further strengthening its balance sheet.

 

The possible introduction of a dividend, which the Company is contemplating initiating in 2027.

 

Cashflows from Essakane (Burkina Faso) are expected to support its ongoing operations and potential extension of mine life, with cash in excess of working capital requirements repatriated using a combination of dividends and a shareholder account structure (see “Dividend Payments from Essakane”). Subject to applicable TSX approval, for the remainder of 2026, the Company intends to use cash received from Essakane to fund a Share Buyback program and will continue to evaluate this strategy as a source of return of capital for shareholders in 2027.

 

As at September 30, 2026, the Company had $766.6 million in cash and cash equivalents and net cash of $213.9 million. The Company has $nil drawn on the Credit Facility and approximately $845.8 million remains available, resulting in liquidity at September 30, 2026, of approximately $1,613.4 million.

 

Within cash and cash equivalents,

  • $56.6 million (70% basis) was held by the Côté Gold UJV. The Côté Gold UJV requires its joint venture partners to fund, in advance, two months of future expenditures and cash calls are made at the beginning of each month, resulting in the month end cash balance approximating the following month’s expenditure.
  • $321.0 million was held by Essakane in Burkina Faso. $135.8 million was transferred to Canada subsequent to quarter end.

 

Restricted cash totaled $68.6 million and relates to deposits required for environmental closure costs obligations related to Essakane and Westwood.

 

The Company’s liquidity position and capital allocation decisions will ultimately be determined by the performance of the Company’s operations, the price of gold, inflation expectations, currency exchange rates and the Company’s ability to successfully repatriate excess cash from Burkina Faso.

 

The Company’s liquidity position, comprised of cash and cash equivalents, short-term investments, and availability under the Credit Facility, together with expected cash flows from operations, is expected to be sufficient to support the Company’s normal operating requirements, capital commitments, and service the debt obligations as they become due. The Company’s ability to draw down on the Credit Facility is dependent on its ability to meet net debt to EBITDA and interest ratio covenants.

 

Readers are encouraged to read the “Caution Regarding Forward Looking Statements” and the “Risk Factors” sections contained in the Company’s 2025 Annual Information Form, which is available on SEDAR+ at www.sedarplus.ca and the “Caution Regarding Forward Looking Statements” and “Risk and Uncertainties” section of this MD&A.

 

Dividend Payments from Essakane

 

Excess cash at Essakane is repatriated through dividends and a shareholder account structure as needed, of which the Company will receive its share based on its ownership, net of withholding taxes. The shareholder account structure functions like an inter-company loan and allows for the Company’s portion of the dividend to be repaid using cash in excess of working capital requirements and aligns the interests of both IAMGOLD and the Government of Burkina Faso, including a preference for increased and/or more regular cash flow movements from Essakane.

 

Essakane declared a record dividend of approximately $855 million in June 2025, which represented the full distribution of past undistributed retained earnings up to and including 2024. IAMGOLD’s 85% portion of the dividend, net of taxes, was approximately $680.7 million and had been fully repatriated as at June 30, 2026.

 

In June 2026, Essakane declared its 2026 dividend of approximately $500 million representing its 2025 distributable earnings. The Government of Burkina Faso received its portion of the dividend totaling $74.0 million in June 2026. IAMGOLD’s 85% portion of the dividend, net of taxes, is approximately $400 million. The Company received $87.8 million during the third quarter 2026, and $135.8 million subsequent to quarter end. The remaining balance of approximately $176.4 million will be repatriated through dividend installments over the course of 2026 and early 2027. The payments will be funded using cash generated in excess of working capital requirements.

 

Share Buyback Program

 

During the third quarter 2026, the Company repurchased and cancelled approximately 7.6 million shares for approximately $134.7 million at an average price of $17.58 per share through its share buyback program under a normal course issuer bid (“NCIB”) that was approved by the Company’s Board of Directors and the TSX. Year to date, the Company repurchased and cancelled approximately 29.1 million shares for approximately $542.6 million at an average price of $18.63 per share. Total repurchases since inception in December 2025 up to September 30, 2026, are approximately 32.1 million shares for approximately $592.6 million at an average price of $18.47 per share.

 

The NCIB allows for the purchase of up to 57 million of its common shares over a twelve-month period, representing approximately 9.92% of IAMGOLD’s public float as at November 30, 2025, through the facilities of the TSX, the NYSE, or any other eligible Canadian alternative trading system on which the common shares are listed. The existing NCIB is approved to continue through December 11, 2026.

 

Subsequent to quarter end, the Company’s Board of Directors authorized the Company to seek TSX approval for a new NCIB for a further 12 months period. Subject to TSX approval, the new NCIB would permit the Company to purchase up to approximately 10% of IAMGOLD’s outstanding common shares. The Company intends to file a notice of intention with the TSX setting out the terms of the proposed NCIB.

 

All common shares purchased under the NCIB will be either cancelled or placed under trust to satisfy future obligations under the Company’s share incentive plan. This initiative reflects management’s confidence in the Company’s long-term value and its commitment to disciplined capital allocation. The program is expected to continue to be funded from operating cash flows.

 

The Company has established an automatic share purchase plan in connection with its NCIB to facilitate the purchase of common shares during times when IAMGOLD would ordinarily not be permitted to purchase common shares due to regulatory restrictions or self-imposed black-out periods. Before entering a black-out period, IAMGOLD may, but is not required to, instruct the broker to make purchases under the NCIB based on parameters set by IAMGOLD in accordance with the automatic share purchase plan, applicable securities laws and stock exchange rules. The actual number of common shares that may be purchased, if any, and the timing of such purchases, will be determined by the Company based on a number of factors, including the Company’s financial performance, the availability of cash flows, and the consideration of other uses of cash, including capital investment opportunities, returns to shareholders, and debt reduction. No ASPP was in effect at the end of the third quarter 2026.

 

The following table summarizes the carrying value of the Company’s long-term debt1:

 

September 30 December 31
($ millions) 2026 2025
Credit Facility $ – $ 200.0
5.75% senior notes ($450 million principal outstanding) 449.2 448.8
Equipment loans – 1.0
$ 449.2 $ 649.8

 

  1. Long-term debt does not include leases in place of $99.5 million as at September 30, 2026 (December 31, 2025 – $112.0 million).

 

Credit Facility

 

The Company has a $850 million secured revolving Credit Facility, which was originally entered into in December 2017 and subsequently increased and extended. The Credit Facility matures on June 17, 2030, and supports the Company’s requirements for a senior revolving facility for its overall business.

 

On June 17, 2026, the Company announced the strengthening of its financial position by amending its revolving Credit Facility, increasing total capacity from $650 million to $850 million, and extending maturity to June 17, 2030. The facility also includes an additional $250 million accordion feature, offering further liquidity potential, and remains fully undrawn as of the date hereof.

 

Key terms have improved, with lower interest margins (1.875%-2.875% vs. 2.75%-3.75%), reduced standby fees, and more flexible covenant limits, including an increase of the net debt to EBITDA ratio to 4.0x from 3.5x.

 

Overall, the amendments reduce borrowing costs, enhance financial flexibility, and expand liquidity, positioning the Company to better support capital allocation and growth initiatives while reflecting a stronger balance sheet.

 

As at September 30, 2026, the Credit Facility was undrawn and the Company issued letters of credit under the Credit Facility in the amount of $3.8 million as a supplier payment guarantee and $0.4 million as guarantees for certain environmental indemnities to government agencies, with $845.8 million remaining available under the Credit Facility.

 

The Credit Facility provides for an interest rate margin above the secured overnight financing rate (SOFR), banker’s acceptance prime rate and base rate advances which vary, together with fees related thereto, according to the total net debt to EBITDA ratio of the Company. The Credit Facility is secured by certain of the Company’s real assets, guarantees by certain of the Company’s subsidiaries and pledges of shares of certain of the Company’s subsidiaries. The key terms of the Credit Facility include certain limitations on incremental debt, certain restrictions on distributions and financial covenants, including net debt to EBITDA, Interest Coverage and a minimum liquidity requirement from October 15, 2027, to October 15, 2028. The Company was in compliance with its Credit Facility covenants as at September 30, 2026.

 

5.75% Senior notes

 

In September 2020, the Company completed the issuance of $450 million of senior notes at face value with an interest rate of 5.75% per annum (the “Notes”). The Notes are denominated in U.S. dollars and mature on October 15, 2028. The Notes can be redeemed at 100% of face value from October 15, 2026, onwards. Interest is payable in arrears in equal semi-annual installments on April 15 and October 15 of each year, beginning on April 15, 2021, in the amount of approximately $12.9 million for each payment. The Notes are guaranteed by certain of the Company’s subsidiaries.

 

Term Loan

 

In May 2023, the Company entered into a $400 million Term Loan. The Term Loan had a 3% original issue discount, bearing interest at a floating interest rate of either one month or three-month SOFR + 8.25% per annum. The Company repaid the full facility in 2025. With the repayment completed, the Term Loan has been fully extinguished and is no longer in effect, including all associated covenants and obligations.

 

Leases

 

At September 30, 2026, the Company had lease obligations of $99.5 million at a weighted average borrowing rate of 7.25%.

 

On April 29, 2022, the Company, on behalf of the Côté Gold UJV, entered into a master lease agreement with Caterpillar Financial Services Limited for $125 million, which was subsequently amended to increase the facility to $175 million.

 

On April 10, 2026, the lease agreement was converted to an uncommitted facility.

 

Certain pieces of mobile equipment at Côté Gold were delivered during the third quarter 2026.

 

Equipment loan

 

The Company had equipment loans with carrying value of $1 million as at December 31, 2025, secured by certain mobile equipment, with interest rates at 5.30% which matured in the third quarter 2026. The equipment loan has been fully repaid. The equipment loan was carried at amortized cost on the consolidated balance sheet.

 

Gold prepay arrangements

 

In December 2023 and April 2024, the Company entered into gold sale prepay arrangements and amendments to certain pre-existing prepay arrangements. In H1 2025, the Company delivered 75,000 ounces in equal monthly instalments thereby extinguishing the delivery obligations gold into the prepay arrangements. In the settlement of these obligations, the Company received proceeds totaling $59.9 million in Q1 2025 and $59.4 million in Q2 2025, respectively.

 

Surety bonds and performance bonds

 

As at September 30, 2026, the Company had (i) C$293.9 million ($206.8 million) of surety bonds, issued pursuant to arrangements with insurance companies, in support of environmental closure costs obligations related to Westwood and Côté Gold and (ii) C$32.1 million ($22.6 million) of performance bonds in support of certain obligations primarily related to the construction of fish habitat at Côté Gold.

 

As at September 30, 2026, there is no collateral required to be in place for surety and performance bonds, and the balance of $229.4 million remains uncollateralized.

 

During the third quarter 2025, the Company increased the bonds required by C$16.9 million ($12.2 million). During the second quarter 2026, the Company increased the bonds required by C$2.1 million ($1.5 million) and during the third quarter 2026, the Company further increased bonds by C$17.0 million ($11.9 million).

 

Income Statement

 

Revenues – Revenues were $856.5 million in the third quarter 2026 from sale of 199,900 ounces at an average realized gold price of $4,277 per ounce, higher by $149.8 million or 21% than the prior year period, due to the $785 per ounce increase in the realized gold price, partially offset by lower gold sales volume.

 

Cost of sales – Cost of sales excluding depreciation was $324.0 million in the third quarter 2026, lower by $0.2 million than the prior year period, primarily due to higher royalties at Côté and Essakane due to the higher gold price, and increased production costs at Westwood compared to the prior year period, partially offset by decreased production and sales volume and production costs at Essakane and Côté.

 

Depreciation expense – Depreciation expense was $126.5 million in the third quarter 2026, higher by $16.6 million or 15% than the prior year period primarily due to the amortization of deferred stripping assets at Côté and Essakane compared to the prior year period, partially offset by lower sales volume.

 

Exploration expense – Exploration expense was $8.4 million in the third quarter 2026, lower by $0.5 million or 6% than the prior year period due to increased exploration expenditures at the Nelligan Mining Complex and Côté Gold.

 

General and administrative expense – General and administrative expense was $21.1 million in the third quarter 2026, higher by $6.5 million or 45% than the prior year period, primarily due to $5.3 million in planned cloud technology implementation costs, $2.8 million higher labour and other administrative costs, and $0.3 million in increased share-based compensation, partially offset by $1.9 million in lower consulting fees.

 

Income tax expense – Income tax expense was $127.5 million in the third quarter 2026, higher by $83.1 million or 187% than the prior year period. It is comprised of a current income tax expense of $77.8 million and a deferred income tax expense of $49.7 million, higher than the prior year period for current income tax expense by $45.8 million or 143% and higher for deferred income tax expense by $37.3 million or 301%, respectively. The current income tax expense in the third quarter of 2026 was higher primarily due to higher income in Essakane and higher withholding taxes from higher intercompany dividends. The deferred income tax expense in the third quarter of 2026 was higher primarily due to the reduction of available deferred tax assets.

 

Operating Activities

 

In the third quarter 2026, operating activities generated cash flow of $461.1 million, higher by $180.3 million compared to the same prior year period. Cash flow from operations increased due to higher revenues driven by an increased realized gold price as compared to the prior year period. Cash flow provided by operations before working capital and taxes paid was $506.5 million in the third quarter, compared to $349.9 million in the prior year period.

 

Investing Activities

 

Net cash used in investing activities for the third quarter 2026 was $40.1 million, a decrease of $28.7 million from the same prior year period. Capital expenditures of $103.0 million increased by $40.7 million compared to the prior year period, with proceeds from other investing activities increasing by $69.4 million.

 

Financing Activities

 

Net cash used in financing activities for the third quarter 2026 was $148.4 million, an increase of $23.5 million from the same prior year period. Financing activities in 2026 are mainly related to share repurchases under the NCIB program and for 2025 were mainly related to debt repayment and servicing costs.

 

ABOUT IAMGOLD

 

IAMGOLD is an intermediate gold producer and developer based in Canada with operating mines in North America and West Africa, including Côté Gold (Canada), Westwood (Canada) and Essakane (Burkina Faso). The Côté Gold Mine (“Côté” or “Côté Gold”) is among the largest gold mines in production in Canada, which IAMGOLD operates in a 70|30 partnership with Sumitomo Metal Mining Co. Ltd. (“SMM”). In addition, the Company has an established portfolio of early stage and advanced exploration projects within high potential mining districts, including the large-scale Nelligan Mining Complex located in Quebec, Canada.

 

IAMGOLD employs approximately 3,900 people and is committed to maintaining its culture of accountable mining through high standards of Environmental, Social and Governance (“ESG”) practices. IAMGOLD is listed on the New York Stock Exchange (NYSE: IAG) and the Toronto Stock Exchange (TSX: IMG).

 

Posted November 6, 2026

Share this news article

MORE or "UNCATEGORIZED"


Peruvian Metals Provides Corporate Update on Production, New Tailings Results and the Process to Re-Instate the OTCQB Listing

Peruvian Metals Corp (TSX-V: PER) (OTC Pink: DUVNF) is pleased to... READ MORE

November 6, 2026

Doubleview Announces Closing of Upsized Flow-Through Private Placement

Doubleview Gold Corp. (TSX-V: DBG) (OTCQX: DBLVF) (WKN: A1W038) i... READ MORE

November 6, 2026

Pecoy Copper Announces Closing of Strategic Financing

Pecoy Copper Corp. (TSX-V: PCU) (FSE: D5E) (OTCQX: PCUUF) is plea... READ MORE

November 6, 2026

Imperial Reports Third Quarter 2026 Financial Results

Imperial Metals Corporation (TSX:III) reports financial results f... READ MORE

November 6, 2026

Copyright 2026 The Prospector News