Blue Moon Metals Inc. (TSX-V: MOON), is pleased to announce an updated Mineral Resource estimate and the results of a Preliminary Economic Assessment for the Blue Moon volcanogenic massive sulphide deposit, located in Mariposa County, California, which will be summarized in an independent National Instrument NI 43-101 Technical Report within 45 days. The study was commissioned by Blue Moon and carried out by Micon International Ltd. and Resource Development Associates, Inc.. It provides a base case assessment for the development of the Project as an underground mine with onsite production of saleable zinc and copper concentrates.
Highlights
Table 1: PEA Results Summary
PEA Base Case | -10% Pricing |
+10% Pricing |
Long-term Consensus Price Forecast(3) |
Spot Prices (Feb. 2025 avg.) |
|||||||
After-Tax NPV ($M, 8% discount rate)(2) | $244 | $163 | $324 | $260 | $340 | ||||||
After-Tax IRR (%)(2) | 38% | 29% | 46% | 39% | 48% | ||||||
First 6 Years of After-Tax Cashflow ($M) | $367 | $293 | $442 | $382 | $458 | ||||||
Payback Period (years) | 2.4 | 2.9 | 2.0 | 2.3 | 1.9 | ||||||
C1 Cost ($/lb ZnEq) | $0.60 | $0.60 | $0.61 | $0.60 | $0.55 | ||||||
LOM Average Head Grade (ZnEq %) | 12.55 | 12.66 | 12.47 | 12.72 | 13.83 | ||||||
Nominal processing capacity (tonnes per day) | 1,800 | ||||||||||
Initial Capital Cost ($M) | $144.5 | ||||||||||
Sustaining Capital Cost ($M) | $64.5 | ||||||||||
Life of Mine Capital Cost ($M) | $209.0 | ||||||||||
Average annual payable production (LOM) | Copper | 7,237 | 000’lbs | ||||||||
Zinc | 62,260 | 000’lbs | |||||||||
Gold | 22,566 | oz | |||||||||
Silver | 681,784 | oz | |||||||||
ZnEq | 151,046 | 000’lbs | |||||||||
Metal prices assumed | Copper $/lb | 4.20 | 3.78 | 4.62 | 4.75 | 4.23 | |||||
Zinc $/lb | 1.25 | 1.13 | 1.38 | 1.26 | 1.27 | ||||||
Gold $/oz | 2,200 | 1,980 | 2,420 | 2,181 | 2,895 | ||||||
Silver $/oz | 27.0 | 24.3 | 29.7 | 26.16 | 32.18 | ||||||
Notes:
The economic analysis contained in this news release are preliminary in nature and includes Inferred Mineral Resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as Mineral Reserves. There is no certainty that the PEA will be realized. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.
President and CEO of Blue Moon, Christian Kargl-Simard stated:
“The positive results of the independent PEA support the significance of the Blue Moon deposit. The Project’s attractive economics compare well with other zinc development projects globally across valuation metrics, including cash cost, IRR and capital cost. The United States imports the majority of its required zinc, making the Project strategically significant for its trillion dollar bipartisan infrastructure bill. In addition, the current economics do not include any credits for germanium, gallium, aggregates, pyrite, barite and gypsum, all of which are recommended for future study analysis. Blue Moon plans to continue engineering and project development activities on its private land package to further advance the Project towards a future construction decision, with the next step being permitting an exploration ramp for infill and exploration drilling to support a feasibility study. Baseline environmental studies are underway to support the ramp development, with construction expected to start in 2026, subject to permitting.”
PEA Contributors
The following companies have undertaken focused work programs since October 2024 that have been referenced in preparation of the PEA for Blue Moon:
Mineral Resource Estimate
In conjunction with the PEA, the Company announced a Mineral Resource Estimate for the Project with an effective date of December 24, 2024. Mineral resources in this news release were estimated in accordance with the Canadian Institute on Mining, Metallurgy and Petroleum Definition Standards for Mineral Resources and Reserves, prepared by the CIM Standing Committee on Reserve Definitions and adopted by the CIM Council on May 14, 2014.
The MRE is based on 87 drill holes totaling 122,364 feet of drilling with 2,631 individual assay intervals. High grade outliers were capped prior to compositing for grade estimation. Gold, silver, copper, lead and zinc mineralization was estimated using inverse distance weighting techniques based on the anisotropy of the deposit. Three-dimensional geology models were constructed to identify the mineralized domains of the deposit. Mineralization is constrained geologically to the mineralized domains to accurately reflect the in-situ mineralization. The mineral resource estimate was completed using Vulcan software in a 3D block model, with blocks ranging from 10x10x10 feet down to 0.1x10x10 feet which are sizes that capture the volume of the veins and are reflective of the selective mining unit envisioned for underground mining of the deposit.
Table 2: Blue Moon Project Indicated Mineral Resources Effective Date December 24, 2024
Domain (Vein) | ZnEq Cutoff | Tons | ZnEq % | Cu % | Pb % | Zn % | Au opt | Ag opt | |
Main | 2.9 | % | 3,073,000 | 12.66 | 0.78 | 0.16 | 5.90 | 0.04 | 1.14 |
East | 2.9 | % | 498,000 | 18.99 | 0.47 | 0.63 | 6.64 | 0.09 | 3.72 |
West | 2.9 | % | 78,000 | 9.5 | 0.62 | 0.33 | 4.41 | 0.03 | 0.93 |
Total | 3,650,000 | 13.46 | 0.73 | 0.23 | 5.97 | 0.04 | 1.49 | ||
Metal | Cu Mlbs | Pb Mlbs | Zn Mlbs |
Au Moz |
Ag Moz |
||||
Main | 47.94 | 10.08 | 362.76 | 0.11 | 3.51 | ||||
East | 4.67 | 6.29 | 66.15 | 0.04 | 1.85 | ||||
West | 0.97 | 0.52 | 6.91 | 0.00 | 0.07 | ||||
Total | 53.59 | 16.90 | 435.83 | 0.16 | 5.43 |
Table 3: Blue Moon Project Inferred Mineral Resources Effective Date December 24, 2024
Domain (Vein) | ZnEq Cutoff | Tons | ZnEq % | Cu % | Pb % | Zn % | Au opt | Ag opt | |
Main | 2.9 | % | 3,261,000 | 11.41 | 0.52 | 0.23 | 5.68 | 0.04 | 1.15 |
East | 2.9 | % | 994,000 | 15.49 | 0.59 | 0.56 | 5.04 | 0.07 | 2.43 |
West | 2.9 | % | 173,000 | 6.28 | 0.73 | 0.22 | 1.98 | 0.02 | 0.40 |
Total | 4,428,000 | 12.12 | 0.54 | 0.30 | 5.39 | 0.04 | 1.41 | ||
Metal | Cu Mlbs | Pb Mlbs | Zn Mlbs |
Au Moz |
Ag Moz |
||||
Main | 33.65 | 14.74 | 370.27 | 0.11 | 3.76 | ||||
East | 11.80 | 11.20 | 100.11 | 0.07 | 2.42 | ||||
West | 2.52 | 0.74 | 6.84 | 0.00 | 0.07 | ||||
Total | 47.97 | 26.68 | 477.22 | 0.19 | 6.25 |
Notes:
Mining
The method proposed in the PEA is underground mining at 1,800 tonnes per day throughput at the mill that can be conventionally extracted using long-hole drilling, stoping and ramp haulage using diesel loaders and articulated trucks, with back-filling of mined voids using cemented tailings. The underground mine design proposes ramp access for workers and materials, with ventilation raises providing a second egress. A contractor-owned fleet of mobile mining equipment is assumed to operate throughout the mine life, while fixed infrastructure (power distribution, pumps, piping, ventilation fans, etc.) are included in initial capital costs. Pre-production mine development costs are also capitalized. However, the base case development schedule assumes the existence of an exploration decline to the first mining level, expected to be completed as part of a program of confirmatory drilling of the mineral resource, and hence the cost of that program (estimated at approximately $30 million) is treated as a sunk cost for the purposes of this PEA.
Waste rock from the underground mining will be utilized as far as practical, and subject to satisfactory testwork results, in the construction of roads and the tailings storage facility. Up to 50,000 tons per year will be hauled off site to be crushed and sold as aggregate in the local market. Excess waste rock will be stockpiled on site near the mine portal.
Metallurgy and Processing
A program of metallurgical testwork was undertaken using two mineralized samples by Lakefield Research in Ontario in 1988 under the direction of Wright Engineers Limited on behalf of Westmin Resources Limited. The preliminary program of work completed by Lakefield Research comprised chemical and mineralogical analyses, hardness testing, batch and locked cycle flotation, flotation concentrate analyses, gravity separation and preliminary settling tests on samples of zinc concentrate and zinc rougher tailings.
Lakefield Research completed 26 separate bench-scale batch flotation tests and one locked cycle test to primarily investigate the sequential flotation of copper and zinc from the two samples. A total of eight batch tests were undertaken using Sample 1, which considered primary grind size, rougher concentrate regrind, flotation reagent combinations and dosage rates, and the recovery of pyrite from the zinc tailings. Sixteen batch tests used Sample 2 and these tests also investigated grind size, rougher concentrate regrinding, reagents, pyrite recovery as well as the potential to separate copper from the bulk copper concentrate. Although there are insufficient details concerning the selection and provenance of the testwork samples to confirm that they were representative of the entire Blue Moon mineral resources, it can be reasonably assumed that they were representative of the styles of mineralization occurring on the Blue Moon property. Conclusions from the 1988 testwork program are as follows:
Mineralized material brought from underground will be transported from the mine portal to the crushing plant by means of haul trucks tipping directly into an ore bin. A vibrating grizzly feeder will feed the material from the bin to the primary crusher, which will allow finer material to bypass the crusher. The primary crusher will reduce run-of-mine feed material to 80% passing 5 inches. Conveyors will transport the crushed product to a stockpile.
The PEA grinding circuit comprises a semi-autogenous grinding (SAG) mill operated in an open circuit configuration along with a ball mill operated in closed-circuit with a hydro-cyclone cluster. The overall grinding circuit will be designed to reduce the incoming ore from an 80% passing particle size of 5 inches (127 mm) to a final product size of 74 µm found in the hydro-cyclone overflow stream.
The copper flotation circuit will prioritize the recovery of copper mineral from the slurry stream and produce a concentrate that will later be dewatered. The tailings stream from the copper rougher bank and the first copper cleaner bank will feed the zinc flotation conditioning tanks and mixed with appropriate flotation reagents. The discharge from the final conditioner will feed the first zinc rougher flotation cell. The concentrate collected from roughers shall report to the zinc regrind circuit while (optionally) zinc rougher tailings will feed a pyrite flotation circuit.
Each concentrate stream reports to a dedicated thickener. The underflows will each report to a dedicated agitated filter feed tank and dedicated tower filter press producing a filter cake containing about 8% moisture by weight. Filtered concentrate will be loaded by conveyor into lined shipping containers which will transport the material to market.
The paste backfill that will be used in the underground mine operation will utilize a paste mixture prepared from cement, process water and tailings of the mineral processing plant. The filtered pyrite and tailings material will both report to a paste mixer which will combine the filter cake with a cement binder and adjustment water to reach a desired paste density. This paste will be pumped through the underground distribution network until it reaches the stopes to be filled. Tailings not utilized as backfill will be stored on surface in a lined dry-stack tailings storage facility.
Infrastructure
The major infrastructure items considered and costed in the PEA support a mining and milling operation that is expected to operate 24-hours per day, seven-days per week. The design of project infrastructure has prioritized environmental protection, workforce safety, and operating efficiency while minimizing community impacts. Major infrastructure items include, but are not limited to the following:
Initial Capital Costs
The initial capital expenditures for the Project were estimated by Micon using a combination of budgetary quotes from vendors, historical pricing from comparable projects, and parametric calculations based on similar equipment and infrastructure, as summarized in Table 4. Capital expenditures to be incurred after the start-up of operations are assigned to sustaining capital and are projected to be covered by operating cash-flows. Project contingencies have been added where applicable, excluding capitalized operating costs, which results in an overall contingency of $28.5M or 24.6% of initial capital before contingency.
Table 4: Initial Capital Cost Estimates
Item | Pre-Production Capital ($M) |
Capitalized Pre-Production Development | 18.4 |
Process Plant | 39.1 |
Backfill Plant | 8.9 |
Tailings disposal | 7.0 |
On-site Infrastructure | 8.8 |
Off-site Infrastructure | 1.9 |
Common Services | 16.0 |
Indirect – site costs | 2.9 |
Indirect – spares & first fills | 3.1 |
EPCM | 7.7 |
Owners Cost | 2.2 |
Contingency | 28.5 |
Total initial capital expenditure | 144.5 |
Notes:
Sustaining Capital Costs
Micon estimates the LOM sustaining capital for Blue Moon to be $64.5M, which is expected to be funded by operating cash flows. The sustaining capital estimate is primarily for the expansion of the tailings storage facility, and maintaining the surface plant and infrastructure. Micon has assumed closure bonding is covered by a corporate surety, and a cost for reclamation and closure at the end of LOM of $15.0M, net of the realisable residual (scrap) value of equipment.
On Site Direct Operating Costs
The estimated direct Opex for Blue Moon totals $116.24/t of mill feed – see Table 5. Micon has estimated the Opex based on estimates of contractor mining rates, processing consumables, spares, power and labour costs, industry benchmarking, proprietary information and its professional experience.
Table 5: On Site Operating Cost for Base Case
Area | LOM Average Cost ($/t processed) |
Mining | $75.02 |
Processing | $36.11 |
G & A | $5.10 |
Total: | $116.24 |
Notes:
Off-Site Costs (Concentrate Transport, Treatment, and Refining Charges)
Projected Treatment and Refining Charges and transport charges for the copper, and zinc concentrates were developed by Micon based on industrial benchmarks and in-house data. Over the life of the mine, these charges equate to $22.58/t processed. Blue Moon anticipates that the copper and zinc concentrates are likely to be sold primarily to smelters in Asia. Off-site costs are comprised of freight charges (highway and ocean), port handling fees, and smelter treatment and refining charges.
Taxes and Employment
California state production and corporate taxes, and US Federal taxes have been accounted for, resulting in an overall corporate tax burden of $188 million, or approximately 28%, excluding payroll taxes, etc. – see Table 6.
Table 6: LOM Tax Contributions
Item | US$’000 |
California Royalties on Gold and Silver | 1,850 |
California Corporate Income Tax | 57,300 |
USA Federal Income Tax | 123,699 |
Payroll taxes (approximate) | 67,710 |
Total | 250,558 |
Over 1,000 direct temporary jobs will be created during the 15-month construction period, consisting of a full range of skilled and unskilled labor, management, supervisory, safety, quality, and environmental personnel.
Once in operation, the Blue Moon Mine is expected to employ an estimated 250 personnel on site. It is the Company’s intent to work with the local communities in advance of production to facilitate the training and skills development needed to operate the mine. Moreover, it may be expected that there will be a “multiplier effect” in the surrounding communities and region to meet the Project’s need for local services, supplies, and infrastructure to support construction and operations, potentially amounting to several times the direct employment headcount.
Environmental and Community Matters
Detailed environmental, social, and technical studies were undertaken in the 1980s and 1990s under previous management of the property, as part of a permitting process for a vertical underground shaft and associated mining/processing infrastructure. The prior permitting process culminated with the issuance of a Conditional Use Permit and Reclamation Plan by the Mariposa County Planning Commission in 1989 and a water discharge permit from the Central Valley Regional Water Quality Control Board in 1990. Although that project was not developed, those studies provide an indication of baseline conditions in the project area, and can be used to inform the approach to future studies.
As the Project design advances, updated technical and environmental studies will be necessary to comply with the California Environmental Quality Act.
In operation, the Project will recirculate process water within the plant and return water from the tailings pond to minimise the quantity of make-up water required. No discharge of contact water is anticipated. The proposed site layout minimises the Project’s footprint and limits surface disturbance to privately-owned land.
Responsible closure planning will be integrated into all phases of the Blue Moon Project and undertaken in compliance with Federal and California State requirements and GIIP, for example the ICMM Guidance for Integrated Mine Closure. A Reclamation Plan, prepared pursuant to the requirements the California Surface Mining and Reclamation Act, will be developed and submitted to the regulatory authorities as part of the project permitting process, and must be approved before mining commences. Financial assurance (reclamation bond) will be posted with responsible agencies, and reviewed annually. The approach to closure planning will focus on returning the land to pre-mining conditions, to the extent possible. It will minimize any potential negative environmental and social impacts, enhance environmental and social benefits, and take due consideration of public health and safety.
Opportunities and Future Work
The Project has significant exploration potential which could result in expansion of the identified mineral resources. Historical data from past exploration of the Blue Moon Mine will be digitised to facilitate its use in guiding future work. Core from previous drilling programs will be preserved where possible and sampled for re-assay to improve confidence in the resource estimate. These samples could also be used to test the distribution, and in due course quantify the potential for economic recovery, of other metals and minerals associated with the Blue Moon deposit, including gallium, germanium, indium, barite, gypsum and pyrite.
A significant portion of the unmineralized rock arising from mine development might be used to produce aggregate for sale in the district, and the potential for crushing and screening this material at a nearby facility will be investigated.
A drill program that will allow the collection of fresh, representative samples of the mineralized zone is needed in order to conduct further metallurgical testwork on the comminution and flotation processes required to produce saleable concentrates. Ideally, this drill program should be conducted from an exploration ramp that would be mined from the southern end of the Blue Moon deposit, descending to the north to facilitate its eventual use as a primary access for underground mine development and production. The exploration ramp and underground drill program will also facilitate collection of geotechnical data to inform the mine planning process. Further engineering work is also required to advance knowledge of the hydrogeological conditions in the Project area to refine site-wide water management models.
Technical Information and Quality Control & Quality Assurance
The company utilizes site personnel to enforce a quality control/quality assurance program. Samples are logged and tracked prior to sealing and shipping. Quality control is monitored by the insertion of blind certified standard reference materials and blanks into each sample shipment. All resource sample shipments are sealed and shipped to ALS Chemex in Reno, Nevada, for preparation and then on to ALS Chemex in Reno, Nevada, or Vancouver, B.C., for assaying. ALS Chemex’s quality system complies with the requirements for the International Standards ISO 9001:2000 and ISO 17025:1999. Analytical accuracy and precision are monitored by the analysis of reagent blanks, reference material and replicate samples. Finally, representative blind duplicate samples are forwarded to ALS Chemex and an ISO compliant third-party laboratory for additional quality control.
During the site visit, the Independent Qualified Person, Scott E. Wilson, performed data verification by examining core materials at the site, and has selected check samples to develop independent verifying assays of intervals by ALS Global Laboratories in Reno, NV. Geologic data development processes were reviewed and observed during a site visit. All drilling geologic description, assaying data and geochemical data have been provided in a database format to Resource Development Associates Inc. for the purpose of estimating the resource.
Qualified Persons
The following QPs will co-author the technical report that will be based on the PEA. These QPs have reviewed and approved the scientific and technical information in this news release that pertain to the sections of the PEA technical report that they are responsible for.
Geology & Mineral Resource | Scott Wilson, C.P.G, RDA |
Metallurgy | Richard Gowans, P.Eng. |
Mining | Peter Szkilnyk, P.Eng. |
Process Plant, Infrastructure | Abel Obeso Muniz, P.Eng. |
Tailings and Water Management | Peter Stevens, C.Geol, ARSM |
Environmental & Community | Becky Humphrey, CEnv, MIMMM |
Economic Evaluation | Christopher Jacobs, CEng, MIMMM |
Each of the individuals above are QPs for the purposes of NI 43-101. All scientific and technical information in this press release in respect of the Project and or the PEA is based on information prepared by or under the supervision of those individuals. The Mineral Resource estimate in this news release has been classified in accordance with CIM Definition Standards – For Mineral Resources and Mineral Reserves (May 14, 2014).
In accordance with NI 43-101, a Technical Report will be filed on SEDAR+ within 45 days of the disclosure of this news release. The technical and scientific information of this news release has been reviewed and approved by Mr. Dustin Small, P.Eng., a non-Independent Qualified Person, as defined by NI 43-101.
About Blue Moon
Blue Moon is advancing 3 brownfield polymetallic projects, including the Nussir copper-gold-silver project in Norway, the NSG copper-zinc-gold-silver project in Norway and the Blue Moon zinc-gold-silver-copper project in the United States. All 3 projects are well located with existing local infrastructure including roads, power and historical infrastructure. Zinc and copper are currently on the USGS and EU list of metals critical to the global economy and national security. More information is available on the Company’s website (www.bluemoonmetals.com).
Pan American Energy Corp. (CSE: PNRG) (FRA: SS60) announces that ... READ MORE
Highlights: Expansional results from key target areas at the B26 ... READ MORE
Results Indicative of Expansion Potential Highlight Intercepts... READ MORE
Continued Operating Outperformance and Musselwhite Addition Provi... READ MORE
enCore Energy Corp. (NASDAQ: EU) (TSXV: EU) America’s Cle... READ MORE