Blue Moon Metals Inc. (TSX-V: MOON) (NASDAQ: BMM) is pleased to announce the completion of a feasibility study for its Nussir project, located in northern Norway. The Feasibility Study results are supported by an independent technical report prepared in accordance with National Instrument 43-101 – Standards of Disclosure for Mineral Projects, which is expected to be filed on SEDAR+ at www.sedarplus.ca within 45 days. The Feasibility Study was commissioned by Blue Moon and carried out by Worley Europe Limited with an effective date of April 14, 2026. The Feasibility Study provides an update to certain previously prepared studies on the Project, including a 2023 study of feasibility prepared in accordance with the Joint Ore Reserves Committee Code, and the technical report titled “Report 43-101 Technical Report On The Mineral Resources Of The Nussir And Ulveryggen Projects, Norway”, dated January 24, 2025 (as amended and restated on September 12, 2025) with an effective date of January 20, 2025, prepared by Adam Wheeler, B.Sc., M.Sc., C.Eng., Eur Ing., FIMMM. This Feasibility Study considers only the underground resource estimate in the Nussir deposit and not the Ulveryggen deposit. All financial figures herein are presented in United States dollars.
The Company believes the results of the Feasibility Study confirm the Project’s potential as a robust, long-life asset with strong economics, including base case average annual free cash flow of $77 million (and approximately $125 million at spot prices on March 4th, 2026). The FS outlines a 13-year mine life, while the deposit remains open to the west and at depth, providing significant upside potential for future resource growth and mine life extension. The opportunities section as outlined below, shows the economics of adding 5 years to the mine life utilizing 50% of the inferred resources adds 52% to the base case consensus pricing after-tax NPV 8%. The Feasibility Study provides strong support to allow Blue Moon to make a final investment decision and it confirms the timeline to hot commissioning of the process plant is Q3 2027.
Highlights:
Additionally, the Company has advanced the basic engineering for the Project and has placed purchase orders for the long lead equipment required for the process plant (SAG mill, Ball Mill and thickeners). The Company has also purchased the main power transformer for the project to de-risk Project execution schedule. So far, approximately $46.7 million has been spent by Blue Moon on the Project; the decline advance is 1,548 meters as of April 15, 2026, and is expected to be in proximity to the target mineralized material in mid-2026.
The FS was completed by Worley Europe Limited with inputs from technical studies completed by other specialist consultants. The FS represents a comprehensive study of the technical and economic viability of the selected development option that demonstrates the extraction of the defined Mineral Reserves is economically viable and can support a positive production decision by the Company.
| Table 1: Project Economics and Key Parameters | |||
| Commodity Pricing | Units | Consensus(1) | Spot(2) |
| Milling Capacity | tpd | 6,000 | 6,000 |
| Mine Life | Years | 13 | 13 |
| LOM Cu Production | kt | 185 | 185 |
| LOM CuEq Production | kt | 241 | 261 |
| LOM Average Cu Production(3) | ktpa | 14.6 | 14.6 |
| LOM Average CuEq Production(3) | ktpa | 19.0 | 19.6 |
| Average annual free cash flow(3) | US$m | $77.2 | $125 |
| Initial Capital Costs | US$m | $184 | $184 |
| Sustaining Capital Costs | US$m | $495 | $495 |
| LOM C1 Cash Cost (net of by-products) | US$/lb | $0.95 | $0.03 |
| LOM ASIC (net of by-product credits) | US$/lb | $2.05 | $1.14 |
| Post-tax NPV (0%) | US$m | $708 | $1,322 |
| Post-tax NPV (8%) | US$m | $235 | $559 |
| IRR | % | 19.0 | 31.2 |
(1) Consensus pricing assumes: 2028 $5.22/lb Cu, $4,207/oz Au, $61.15/oz Ag; 2029 $5.23/lb Cu, $3,971/oz Au, $55.07/oz Ag; LT $4.78 Cu, $3,515/oz Au, $45.26/oz Ag.
(2) Spot prices are based on March 4th, 2026: $5.84/lb Cu, $5,171/oz Au, $84.61/oz Ag
(3) The average values are based on average of the years with full production
Christian Kargl-Simard, CEO of Blue Moon states, “The completion of this Feasibility Study update marks yet another significant milestone for our Nussir project and re-affirms the strength and value of this asset and resource. Through our ongoing exploration efforts at Nussir, including 200 m step out holes at over 1 km depth, we believe this will be a generational copper mine, so we believe these results are just the beginning. In addition, due to the strong free cashflow generation of this asset and the equity spent on the Nussir Project to date, there is significant financing flexibility on the types of sources for the remaining capital costs.”
MINERAL RESOURCES ESTIMATE
The Mineral Resources used as the basis for the FS study are summarized below.
| Table 2: Mineral Resource Statement January 20, 2025 (amended and restated September 12, 2025) | |||||
| Classification | Tonnes(millions) | Cu Grade(%) | Au Grade (g/t) | Ag Grade(g/t) | Cu Eq Grade(%) |
| Measured | 2.69 | 1.08 | 0.18 | 12.8 | 1.31 |
| Indicated | 26.03 | 1.01 | 0.11 | 12.3 | 1.19 |
| Measured & Indicated | 28.72 | 1.02 | 0.12 | 12.3 | 1.20 |
| Inferred | 31.99 | 1.01 | 0.14 | 14.6 | 1.23 |
Notes:
MINERAL RESERVES ESTIMATE
The tonnage, grades, and classification of the Total Mineral Reserves captured within the FS Mine Plan are summarized below.
| Table 3: Mineral Reserves | |||||
| Classification | Tonnes (millions) | Cu Grade(%) | Au Grade(g/t) | Ag Grade(g/t) | Cu Eq Grade (%) |
| Proven | 2.64 | 0.80 | 0.13 | 10.15 | 1.01 |
| Probable | 22.34 | 0.81 | 0.09 | 10.36 | 0.99 |
| Proven & Probable | 24.98 | 0.81 | 0.09 | 10.34 | 0.99 |
Notes:
MINING AND PROCESSING
The mining method used for the FS is Long Hole Open Stoping (LHOS) method with ribs and sill pillars to consistently sustain the production and mill throughput design rate. Required infrastructure to support the mine operation have been included in the design, including materials handling equipment. Trucking and mobile equipment have been optimized in the mine design along with implementation of conveyors for both crushed ore and waste.
Figure 1: Long Section of Mine Design at Nussir
Underground mobile crushers are utilized followed by a grinding circuit including a semi-autogenous grinding (SAG) mill and a ball mill located on surface prior to flotation. The flotation concentrate is filtered using a plate and frame pressure filter and stored in a storage warehouse prior to shipping through the existing and operational port and ship loaders. The mine and process facility will be powered by an existing 132 kV power line. Fresh water requirements for the process plant and the mine will be provided from an existing water dam using an existing buried pipeline. A water treatment plant has been included to treat the underground mine water to a quality suitable for reuse within the processing plant, thereby reducing demand for freshwater abstraction from the water reservoir and to treat the excess mine water to a quality suitable for controlled discharge during upset conditions (e.g. processing plant shutdowns or maintenance), in accordance with applicable Norwegian and EU environmental standards.
Figure 2: Life of Mine Production
ENVIRONMENTAL AND PERMITTING
The primary permits required for mining projects in Norway have been obtained. These permits include an Extraction Permit for state-owned minerals (under the Minerals Act 2009), an approved Zoning Plan revision of the municipal land use plan to include the proposed mining area (under the Planning and Building Act), a Discharge Permit (under the Pollution Control Act) and an Operating License (under the Minerals Act). The Project has also obtained certain secondary approvals, including an approved Mine Waste Management Plan for the exploration decline development and a Baseline Marine Monitoring Plan that allows for further marine baseline studies in Repparfjord. Additional secondary permits are in progress and are proceeding in the normal course.
PROJECT TIMELINE
A project execution plan and target schedule have been developed as part of the Feasibility Study to outline the durations and key activities for achieving commercial production at the Project. The Project schedule defined the construction completion of October 2027, hot commissioning starting August 2027 and start of production December 2027.
| Table 4: Project Timeline | |
| Milestone | Target Date |
| EPC Contract Award | May 2026 |
| First Concrete Pour Mill Building | July 2026 |
| Mechanical Completion | October 2027 |
| Start of No-Load Commissioning | March 2027 |
| Start of System Handover to Operation | April 2027 |
| Start of Production and Ramp-up | December 2027 |
| Final Certification | March 2028 |
ECONOMIC IMPACT
The Company expects the Project to generate significant economic benefits at both the local and national levels. At peak construction, the Company expects to employ, directly or indirectly, approximately 200 personnel, and approximately 100 personnel during commercial production operations, with indirect employment estimated at two to three times these levels through supporting industries and services.
The Company is implementing strategies to maximize the number of long-term employees residing locally, which is expected to provide a sustained boost to the regional economy and support the creation of additional long-term indirect employment associated with population growth.
Based on the assumptions used in the Feasibility Study and applying current Norwegian fiscal regimes, the Project is expected to generate substantial government revenues over its life. Using long-term consensus commodity prices, life-of-mine Norwegian government royalties are estimated at approximately $18 million, with corporate taxes of approximately $275 million, for total government revenues of approximately $293 million.
At spot commodity prices, life-of-mine Norwegian government royalties are estimated at approximately $25 million, with corporate taxes increasing to approximately $365 million, for total government revenues of approximately $390 million over the life of the Project.
Opportunity Case
The FS reserve estimate excludes inferred material from the resource estimate. The potential conversion of this inferred material supports the opportunity case and showcases the potential of the life of mine extension to 17 years, considering the same production throughput.
| Table 5: Opportunity Case(1) Economics and Key Parameters | |||
| Commodity Pricing | Units | Consensus(2) | Spot(3) |
| Milling Capacity | tpd | 6,000 | 6,000 |
| Mine Life | Years | 17 | 17 |
| LOM Cu Production | kt | 294 | 294 |
| LOM CuEq Production | kt | 386 | 420 |
| LOM Average Cu Production(4) | ktpa | 16.0 | 16.0 |
| LOM Average CuEq Production(4) | ktpa | 20.9 | 22.8 |
| Average annual free cash flow(4) | US$m | $82.3 | $137 |
| Initial Capital Costs | US$m | $184 | $184 |
| Sustaining Capital Costs | US$m | $741 | $741 |
| LOM C1 Cash Cost (net of by-products) | US$/lb | $0.75 | $0.23 |
| LOM ASIC (net of by-product credits) | US$/lb | $1.83 | $0.85 |
| Post-tax NPV (0%) | US$m | $1,332 | $2,350 |
| Post-tax NPV (8%) | US$m | $358 | $784 |
| IRR | % | 19.6 | 31.1 |
(1) Opportunity case includes additional inferred resources (using 50% conversion rate) that are considered too speculative geologically to have been categorized as reserves.
(2) Consensus pricing assumes: 2028 $5.22/lb Cu, $4,207/oz Au, $61.15/oz Ag, 2029 $5.23/lb Cu, $3,971/oz Au, $55.07/oz Ag, LT $4.78 Cu, $3,515/oz Au, $45.26/oz Ag.
(3) Spot prices are based on March 3rd, 2026: $5.84/lb Cu, $5,171/oz Au, $84.61/oz Ag
(4) The average values are based on average of the years with full production
QUALIFIED PERSONS
The FS was prepared by both Worley Europe Limited Qualified Persons, and Mr. Adam Wheeler. Worley’s Qualified Persons and Mr. Adam Wheeler are independent of Blue Moon Metals and have reviewed and approved this news release. Chris Hughes-Narborough, Martin Prior, Roy R. Levesque, Susan Abell and Lumin Ma were engaged by Worley and are independent of the Company. The affiliation and areas of responsibility for each Qualified Person involved in preparing the FS, upon which the technical report will be based, are provided below.
The technical and scientific information of this news release has also been reviewed and approved by Mr. Reza Ehsani, P.Eng., a Blue Moon Officer, and a non-Independent Qualified Person, as defined by NI 43-101.
About Blue Moon
Blue Moon is advancing 5 brownfield polymetallic projects, including the Nussir copper-gold-silver project in Norway, the NSG copper-zinc-gold-silver project in Norway, the Blue Moon zinc-gold-silver-copper project in the United States, the Springer tungsten-molybdenum project in the United States, and the Apex gallium, germanium, copper, and silver project in United Staes. All 5 projects are well located with existing local infrastructure including roads, power and historical infrastructure. Zinc, copper, tungsten, gallium, and germanium are currently on the USGS and EU list of metals critical to the global economy and national security. Major shareholders include funds managed by Oaktree Capital Management, Hartree Partners LP, Wheaton Precious Metals, Altius Minerals Corporation, Baker Steel Resources Trust, LNS and Monial. More information is available on the Company’s website (www.bluemoonmetals.com).
For further information:
Blue Moon Metals Inc.
Christian Kargl-Simard
CEO and Director
Phone: (416) 230 3440
Email: christian@bluemoonmetals.com
As part of the financing package for the phased development of the commercial operations of its Mata... READ MORE
Group Eleven Resources Corp. (TSX-V: ZNG) (OTCQB: GRLVF) (FSE: 3GE) is pleased to announce new assay... READ MORE
Argenta Silver Corp. (TSX-V: AGAG) (OTCQX: AGAGF) (FSE: T1K) is pleased to report the third set of ... READ MORE
Maple Gold Mines Ltd. (TSX-V: MGM) (OTCQX: MGMLF) (FSE: M3G0) today announced assay results from 14 ... READ MORE
Uranium Royalty Corp. (NASDAQ: UROY) (TSX: URC) is pleased to announce that it has entered into an a... READ MORE