The Prospector News

Aya Gold & Silver Reports Strong Cash Flow and Silver Production of 526,703 Ounces in Q2-2023

You have opened a direct link to the current edition PDF

Open PDF Close
Uncategorized

Share this news article

Aya Gold & Silver Reports Strong Cash Flow and Silver Production of 526,703 Ounces in Q2-2023

 

 

 

 

 

Aya Gold & Silver Inc. (TSX: AYA) (OTCQX: AYASF) is pleased to announce interim financial and operational results for the second quarter ended June 30, 2023. All amounts are in thousands of US dollars unless otherwise stated.

 

Q2-2023 Highlights

 

Operational and Financial

  • Strong operational performance:
    • Silver production of 526,703 ounces (“oz”) in Q2-2023, a 15% increase from Q2-2022
    • Recoveries averaged 87.3% in Q2-2023, compared to 87.9% in Q2-2022
    • Ore processed increased to 72,190 tonnes (“t”) in Q2-2023 compared to 59,995t in Q2-2022
  • Revenue of $9.6 million in Q2-2023, a 12% increase from Q2-2022
  • Cash cost of $10.98 per oz in Q2-2023 compared to $10.95 per oz in Q2-2022 (¹)
  • Operating cash flow of $3.7 million in Q2-2023, a 234% increase compared to Q2-2022
  • Robust financial position with $52 million of cash, cash equivalents and restricted cash (²) compared to $42 million at December 31, 2022
  • Settled dispute with previous CEO and related Net-Profit Interest agreement, resulting in the dissolution of the NPI

 

Exploration and Development:

  • Completed 12,424 meters of drilling at Zgounder in Q2-2023
  • Conducted 4,634m of diamond drill hole drilling on Zgounder Regional properties in Q2-2023:
    • Preliminary results returned anomalous zinc and copper values including silver intercepts
  • Completed 18.7 kilometers (“km”) of the 36km DDH program at Boumadine in Q2-2023:
    • Extended the strike 400m to 3.8km, which remains open in all directions
    • Mapping identified a new at-surface northwest zone that extends over 1.5km
  • Acquired Tirzzit historical copper mine property, which is 67.7km², and rights for $4.7 million

 

Zgounder Expansion:

  • Advanced Zgounder Mine expansion in Q2-2023:
    • Overall project 45% complete and tracking on budget
    • Underground development on track, with 65% of lateral and 42% of vertical development completed
    • Completed detailed engineering, ball mill and crushing equipment on schedule
    • Mobilised open-pit contractor, commenced in-pit stripping and produced first ore
    • Continued construction of the new tailings and water storage facilities on schedule

 

(1) The Corporation reports non-GAAP measures, which include cash costs per silver ounce and free cash flow, which are widely used in the mining industry as a benchmark for performance, but do not have a standardized meaning and the methods used by the Corporation to calculate such measures may differ from methods used by other companies with similar descriptions. See “Non-GAAP Measures” on page 15 of the Corporation’s Q2-2023 MD&A for a reconciliation of non-GAAP to GAAP measures.
(2) Non-GAAP Measures, consisting of cash and cash equivalents of $49,568,497 and restricted cash of $2,540,987.

Long-term Sustainability of Zgounder Operations: 

  • Continued construction of the 90km power line to connect Zgounder to renewable grid power
  • Provided over 3,040 hours of health & safety training
  • Completed emergency response station and took delivery of mine rescue vehicle and equipment

 

“Continuing our strong start to the year, Zgounder delivered another exceptional quarter with strong financials and solid execution. We benefited from above-capacity milling rates and higher silver prices, which drove strong cash flow and silver production of 526,703 ounces as well as lower cash costs,” said Benoit La Salle, President and CEO. “We continue to execute on our Zgounder expansion, which is 45% complete and on budget, and are well-positioned to achieve our full-year production and cost guidance.

 

In July, we published our 2022 Sustainability Report highlighting how we have accelerated integration of ESG and climate change across Aya. We have aligned our operations with the recommendations of the TCFD and tied executive compensation with strategic objectives linked to key ESG performance indicators.

 

Our exploration success and resource growth continued in the quarter with the strike extension to the south and the discovery of a northwest zone at Boumadine. We also acquired the historical Tirzzit copper mine, which adds seven prospective copper-silver permits near Zgounder. In the near-term, we are adding drill rigs at Zgounder and Boumadine and mobilizing at Tirzzit and expect to further extend the Boumadine Main Trend, which will translate into additional resources in Q1-2024.”

 

Q2-2023 Operational and Financial Highlights

 

Key Performance Metrics* Q2-2023 Q2-2022 Variation
Operational
Ore Mined (t) 103,231 62,221 66 %
Ore Processed (t) 72,190 59,995 20 %
Average Grade (g/t Ag) 265 273 (3 %)
Mill Recovery (%) 87.3 % 87.9 % (<1%)
Silver Ingots Produced (oz) 202,559 219,762 (8 %)
Silver in Concentrate Produced (oz) 324,144 239,299 35 %
Total Silver Produced (oz) 526,703 459,061 15 %
Silver Ingots Sold (oz) 164,707 196,556 (16 %)
Silver in Concentrate Sold (oz) 287,816 242,524 19 %
Total Silver Sales (oz) 452,523 439,080 3 %
Avg. Net Realized Silver ($/oz) 21.26 19.53 9 %
Cash Costs per Silver Ounce Sold (¹) 10.98 10.95 <1%
 

Financial

Revenue 9,621 8,574 12 %
Cost of sales 6,876 5,811 18 %
Gross Margin 2,745 2,763 (1 %)
Operating (loss) (36) 506 (107 %)
Net Earnings (loss) (525) 725 (172 %)
Operating Cash Flow 3,674 1,100 234 %
Cash and Restricted Cash (2) 52,109 67,945 (23 %)
Shareholders
Earnings (Loss) per Share – basic (0.00) 0.01 NM
Earnings (Loss) per Share – diluted (0.00) 0.01 NM
(1,2) See footnotes (1, 2) on first page

Second Quarter 2023 Financial & Operational Highlights

 

  • Quarterly silver production of 526,703 oz, comprising 324,144 oz in silver concentrate and 202,559 oz in silver bars.
  • Mill average feed grade of 265 grams per tonne (“g/t”) Ag was reported in Q2-2023 compared to 273 g/t Ag in Q2-2022, a decrease of 3%.
  • Milling operations reached 793 tonnes per day (“tpd”), surpassing design capacity of 700 tpd.
  • Average combined mill recovery of to 87.3% in Q2-2023 compared to 87.9% in Q2-2022, a decrease of 0.6%.
  • Plant availabilities reached 93.4% and 96.6% for the flotation and cyanidation plants, respectively.
  • Cash flow generated by operating activities of $3,674 in Q2-2023 compared to cash flow of $1,100 in operating cash flow in Q2-2022.
  • Revenue from silver sales totaled $9,621 (Q2-2022 – $8,574) in Q2-2023, an increase of 12% representing an average realized price of $21.26/oz. (Q2-2022 – $19.53/oz).
  • Operations generated a gross margin of $2,745 in Q2-2023, a 1% decrease compared to Q2-2022.
  • Net loss for the quarter was $(525) (diluted EPS of $(0.00)) in Q2-2023, compared to net earnings of $725 (diluted EPS of $0.01) in Q2-2022.

 

Q2-2023 Operations Review

 

In Q2-2023, Zgounder Mine operations focused on the ramp-up of the underground mine, completing mobilization of the open pit contractor and finalizing the open-pit definition drilling program. The 1,950m underground level is now fully operational, and access to the 1,925m level is in construction. Open-pit stripping commenced in June, and ore production occurred in July. A total of 103,231t of ore was mined and 72,190t was processed in Q2, adding over 30kt of ore in inventory, in line with the 2024 commissioning plan.

 

The quarter saw completion of the new emergency response and mine rescue station as well as on-site delivery of mine rescue equipment and an emergency vehicle. Consequently, training for the mine rescue and emergency response teams has been scheduled in the second half of the year. Over 4,075 hours of training have been dispensed year to date, a 150% increase compared to H1-2022 which reflects the Corporation’s commitment to enhancing the health and safety culture at Zgounder.

 

Zgounder Development

 

Construction of the plant and surface infrastructure continued to track on budget. At the end of Q2-2023, the mine expansion project was 45% complete, compared to 32% at end of Q1-2023.

 

Construction of the processing plant was 40% complete, with engineering near-complete and procurement well advanced. Earthworks were completed in the quarter, and most concrete foundations were poured. Delivery of several long-lead equipment items are expected on site in Q3-2023, including the ball mill.

 

Underground development continued to advance strongly in the quarter. Over 6,500m of lateral and ramp accesses have now been completed, representing 65% of the total lateral infrastructure. Most levels between 1,925m and 2,100m are now connected to the underground ramp. The main ventilation shaft has been completed, and installation of primary fans is planned for Q3-2023. To date, 253m of vertical raises have been completed, 42% of the total development. In June, the open pit contractor was mobilized, and open pit operations commenced. Overall, open pit and underground mine development are 47% advanced.

 

At quarter-end, construction of the tailing storage facility was progressing well and was 55% complete. The two water storage basins were 74% complete with only the lining installation remaining, in time before the rainy season. Other infrastructure, such as the camp, roads, workshops, and warehouses, were 55% completed. Finally, the power line and electrical substations progressed to 27% completion.

 

At the end of Q2-2023, $132 million had been committed across all capital cost categories, and $54 million had been incurred. The Aya project team remains confident of completing the project within the original budget of $159 million including contingency.

 

The table below presents construction progress by main project area:

 

Area Progress
Process Plant 40 %
Underground and Open-Pit Mines 47 %
Tailings 55 %
Water Management 74 %
Electrical Infrastructure 27 %
On-site Infrastructure 55 %

 

Q2-2023 Exploration

 

Zgounder

 

In Q2-2023, drilling at Zgounder focused on delineating near-mine targets both laterally and at depth. A total of 12,424m of DDH and reverse circulation drilling was conducted on Zgounder in Q2-2023 (exploration and definition drilling) including T28 and YAK underground drilling. At quarter-end, two underground rigs were active on the property and the 26,000m underground DDH program was 17% complete. Given that the development of the 1,950m level is complete and the 1,925m level is near-complete, the exploration program is expected to be expanded in H2-2023.

 

Notably, surface RC drill hole ZG-RC-23-2260-70 intersected 1,611 g/t Ag over 27m including 4,771 g/t Ag over 5.0m, confirming ongoing high-grade mineralization in the open-pit area. Furthermore, hole ZG-23-02 returned 1,753 g/t Ag over 6.5m, defining high-grade mineralization from surface in the east outside of the resource envelope.

 

Zgounder Regional

 

At the end of June 2023, a total of 8,582m had been drilled on the Zgounder Far West, Tala and Izza areas of the Zgounder Regional permits. Preliminary results released at the end of May returned anomalous Zn, Cu and Ag values that will be drill tested in parallel to new zones. Hole ZGW-22-06 in the Zgounder Far West intercepted 1.22% Zn over 85.5m including 1.91% Zn over 5.0m. In the Tala area, hole AM-22-001 intercepted 0.93% Cu over 6.0m including 1.27% Cu over 3.0m.

 

Boumadine

 

Five drill rigs were active on the Boumadine property throughout the second quarter with a total of 31,395m drilled in H1-2023. The 2023 drill program, which was 85% complete at quarter-end, was completed in July. The aim of the infill and exploration drilling was to explore and extend the strike along the main trend in the Central and South Zones. In early July, results from Q2-2023 drilling were released, confirming the extension of the main trend mineralization by 400m to 3.8km in strike to the south with BOU-DD23-125, BOU-DD23-136 and BOU-DD23-142 intersecting high-grade mineralization in the form of massive sulphide veins.

 

In parallel, results from surface detailed mapping were received in Q2-2023 which identified a new at-surface northwest zone at Boumadine. The surface samples returned values up to 460 g/t AgEq along a 1.5km structure of N030 orientation, demonstrating the potential outside of the Boumadine Main Trend (see Figure 7). The mapping revealed two major sets of faulting events: a N030 faulting event that cross-cut Boumadine Main Trend (N340) and may be responsible for the Au-Zn enrichment of the mineralization; and a N070 fault event cutting both N340 and N070 structures which seem responsible for the Ag-Pb enrichment. A total of 127 surface grab samples were also taken, with 36 still pending results.

 

The quarter saw a first site visit by RSC Consulting Limited, which has been mandated to conduct a NI 43-101-compliant mineral resource estimate of Boumadine. Furthermore, an on-site sample preparation laboratory was commissioned on the project site, which will greatly improve sample turnaround times.

 

The technical information relating to Zgounder, Zgounder Regional and Boumadine properties was reviewed and approved by David Lalonde, B. Sc, Head of Exploration, designated as a Qualified Person under National Instrument 43-101.

 

Acquisition of Tirzzit

 

On June 28, 2023, the Corporation acquired Tirzzit, a collection of seven permits located 25 km from the Zgounder Silver Mine in the Kingdom of Morocco.

 

The Corporation issued 622,728 of its shares at C$8.36 (having a value of $3.9M) and paid $800,000 in cash for a total consideration of $4.7 million. The assets acquired include the following:

  • Seven permits, comprising five exploration permits and two mining licenses, one of which hosts a high-grade historical copper mine.
  • A property totaling 67.7 square km.

 

The transaction remains subject to administrative procedures in the Kingdom of Morocco.

 

About Aya Gold & Silver Inc.

 

Aya Gold & Silver Inc. is a rapidly growing, Canada-based silver producer with operations in the Kingdom of Morocco.

 

The only TSX-listed pure silver mining company, Aya operates the high-grade Zgounder Silver Mine and is exploring its properties along the prospective South-Atlas Fault, several of which have hosted past-producing mines and historical resources. Aya’s Moroccan mining assets are complemented by its Tijirit Gold Project in Mauritania, which is being advanced to feasibility.

 

Aya’s management team is focused on maximising shareholder value by anchoring sustainability at the heart of its operations, governance, and financial growth plans.

 

Posted August 11, 2023

Share this news article

MORE or "UNCATEGORIZED"


Arizona Sonoran Announces Royal Gold’s Purchase of Existing NSR on the Cactus Project

Arizona Sonoran Copper Company Inc. (TSX:ASCU) (OTCQX:ASCUF)  an... READ MORE

February 13, 2025

Emerita Intersects 9.3 Meters Grading 1.1% Copper and 1.2 G/T Gold with Additional Base Metal Sulphides at El Cura Deposit

Emerita Resources Corp. (TSX-V: EMO) (OTCQB: EMOTF) (FSE: LLJA) c... READ MORE

February 13, 2025

Abcourt Intersects 41.6 g/t Over 0.7 Metre in the 785N Zone at Depth of the Sleeping Giant Mine

Abcourt Mines Inc.  (TSX-V: ABI) (OTCQB: ABMBF) announces the re... READ MORE

February 13, 2025

Lundin Mining Announces 2024 Mineral Resource and Mineral Reserve Estimates

Lundin Mining Corporation (TSX: LUN) (Nasdaq Stockholm: LUMI) rep... READ MORE

February 13, 2025

Kinross reports 2024 fourth-quarter and full-year results

Delivered on all key guidance metrics Achieved record free cash f... READ MORE

February 13, 2025

Copyright 2025 The Prospector News