Amerigo Reports Q3-2021 Production Results

You have opened a direct link to the current edition PDF

Open PDF Close
Uncategorized

Share this news article

Amerigo Reports Q3-2021 Production Results

 

 

 

 

 

Quarterly copper production of 16 million pounds, 9% over Q3 guidance

 

Cash cost of $1.62/lb, 8% below Q3 guidance and lowest quarterly cash cost of 2021

 

Annual MVC plant maintenance shutdown successfully completed on schedule

 

Amerigo Resources Ltd. (TSX: ARG) (OTC:ARREF) is pleased to announce production results for the quarter ended September 30, 2021 from Minera Valle Central the Company’s 100% owned operation located near Rancagua, Chile. Dollar amounts in this news release are in U.S. dollars.

 

In Q3-2021, MVC produced 16 million pounds of copper at a cash cost1 of $1.62 per pound and 0.3 M lbs of molybdenum.

 

Q3-2021 copper production was at 109% of guidance2 (YTD-2021: 101% of guidance2), due to higher fresh tailings tonnage and grade. During the quarter, MVC also successfully completed a series of planned plant modifications which now allow it to process a higher throughput of fresh tailings without sacrificing recovery. Production from fresh tailings in Q3-2021 accounted for 54% of quarterly production.

 

Molybdenum production in Q3-2021 was at 100% of guidance2 (YTD-2021: 95% of guidance2), marginally affected as more copper production comes from fresh tailings than from Cauquenes, as fresh tailings have lower molybdenum content.

 

           
  Q3-2021 Q2-2021 Q1-2021 Q4-2020 Q3-2020
Fresh tailings          
Tonnes per day 137,650 129,153 128,238 136,011 119,285
Operating days 84 89 90 92 92
Tonnes processed 11,562,611 11,533,405 11,541,378 12,512,980 10,974,235
Copper grade 0.152% 0.144% 0.143% 0.135% 0.136%
Copper recovery 22.3% 20.2% 19.3% 19.3% 20.4%
Copper produced (M lbs) 8.62 7.37 7.03 7.17 6.68
Cauquenes tailings          
Tonnes per day 52,981 54,026 55,457 54,541 54,292
Operating days 81 87 87 91 79
Tonnes processed 4,267,203 4,701,475 4,811,171 4,985,031 4,362,040
Copper grade 0.238% 0.230% 0.242% 0.247% 0.245%
Copper recovery 33.0% 31.9% 33.1% 34.2% 34.5%
Copper produced (M lbs) 7.37 7.61 8.47 9.28 8.00
Copper produced (M lbs) 15.99 14.99 15.50 16.45 14.68
Copper delivered (M lbs) 16.90 15.13 15.11 15.90 14.92
Cash cost ($/lb) 1.62 1.81 1.88 1.65 1.80
Molybdenum produced (M lbs) 0.32 0.33 0.40 0.50 0.37
Molybdenum sold (M lbs) 0.34 0.33 0.36 0.50 0.37
           

 

“Amerigo completed Q3-2021 with very strong production results. The annual plant maintenance shutdown was completed successfully and on schedule, and full production operations resumed on October 2, 2021. A total of 1,390 maintenance tasks and projects were completed safely and on time by our team in Chile to ensure MVC’s plant continues to operate as expected”, said Aurora Davidson, Amerigo’s President and CEO.

 

Q3-2020 cash cost of $1.62/lb was 8% lower than the Company’s Q3 cash cost guidance of $1.76/lb3 due to higher than projected production and lower than anticipated power, steel and lime costs.

 

MVC’s average copper price in Q3-2021 was $4.23/lb, compared to $4.44/lb in Q2-2021.

 

On September 30, 2021, the Company’s cash and restricted cash balance was $71 million (an increase of $18 million from June 30, 2021) and outstanding bank debt was $35 million (unchanged from June 30, 2021).

 

Release of Q3-2021 financial results on November 3, 2021

 

Amerigo will release Q3-2021 financial results at market open on Wednesday, November 3, 2021.

 

About Amerigo and MVC

 

Amerigo Resources Ltd. is an innovative copper producer with a long-term relationship with Corporación Nacional del Cobre de Chile the world’s largest copper producer.

 

Amerigo produces copper concentrate and molybdenum concentrate as a by-product at the MVC operation in Chile by processing fresh and historic tailings from Codelco’s El Teniente mine, the world’s largest underground copper mine.

 

Posted October 12, 2021

Share this news article

MORE or "UNCATEGORIZED"


Reunion Gold Infill Drilling Continues to Expand the Zone of High-Grade Gold Mineralization on Block 6 at its Oko West Project, Guyana

Highlights include: Hole D-375 intersecting 60.4 m @ 1.50 g/t Au,... READ MORE

April 15, 2024

Great Pacific Gold to Acquire Papua New Guinea Focused Tinga Valley Copper & Gold Corp.

Highlights: 347 sq km granted exploration license located 140 km ... READ MORE

April 15, 2024

i-80 Gold Announces High-Grade Results from Underground Drilling at Cove

New results include 29.6 g/t Au over 7.2 m, 18.7 g/t Au over... READ MORE

April 15, 2024

Calibre Intercepts High-Grade Gold & Silver Mineralization from Several Targets at its Eastern Borosi Mine Complex; Drilling Intersects Include 10.81 g/t Gold over 3.4 metres, 9.64 g/t Gold over 3.3 metres, 1,431.6 g/t Silver over 2.9 metres and 642.3 g/t Silver over 5.0 metres

Calibre Mining Corp. (TSX: CXB) (OTCQX: CXBMF) is pleased to anno... READ MORE

April 15, 2024

SILVER VIPER CLOSES FIRST TRANCHE OF LIFE OFFERING

Silver Viper Minerals Corp. (TSX-V: VIPR) (OTC: VIPRF) is please... READ MORE

April 13, 2024

Copyright 2024 The Prospector News