The Prospector News

i-80 Gold Announces Positive Updated Preliminary Economic Assessment on the Cove Project, Nevada; After-Tax NPV(5%) of $271 Million with an After-Tax IRR of 30% at US$2,175/oz Au

You have opened a direct link to the current edition PDF

Open PDF Close
Uncategorized

Share this news article

i-80 Gold Announces Positive Updated Preliminary Economic Assessment on the Cove Project, Nevada; After-Tax NPV(5%) of $271 Million with an After-Tax IRR of 30% at US$2,175/oz Au

 

 

 

 

 

i-80 GOLD CORP. (TSX: IAU) (NYSE: IAUX) is pleased to announce the results of an updated preliminary economic assessment for the Cove Project, an advanced underground exploration project located on the Battle Mountain-Eureka Trend in Northern Nevada, United States. The 2025 PEA confirms that the high-grade Cove Project has the potential to become a key component of the Company’s regional “hub-and-spoke” mining and processing strategy.

 

The 2025 PEA replaces the previous PEA for the Project completed in 2021. The Study has been updated to reflect a remodeling of the deposit using a more confined mining geometry, further advancement of the hydrology model, as well as using updated precious metals prices, capital and  operating costs. All amounts are in United States dollars, unless otherwise stated.

 

“The 2025 PEA for the Cove Project represents an important first step in delivering updated technical information across i-80 Gold’s asset portfolio. The results validate our planned regional hub-and-spoke model of feeding a central processing plant with high-grade material from three underground mines, which is expected to form the production base for i-80 Gold moving forward. In the coming weeks, we look forward to releasing updated PEAs for Granite Creek (both open pit and underground) and the Ruby Hill Complex (Archimedes underground and Mineral Point open pit),” stated Richard Young, Chief Executive Officer of i-80 Gold.

 

2025 PEA Highlights

 

Mineral Estimates, Production and Mine Life

  • Underground gold mine with a life of mine of approximately 8 years.
  • Average annual gold production of approximately 100,000 ounces of gold following ramp up.
  • Estimated LOM cash costs(1) of $1,194 per ounce and all-in-sustaining costs(1) of $1,303 per ounce.
  • Updated mineral resource estimate resulting in an indicated gold mineral resource of 311,000 oz at 8.2 grams per tonne (“g/t”) and an inferred gold mineral resource of 1.16 Moz at 8.9 g/t.
  • The current infill drill program conducted over the past two years is not included in the 2025 PEA, however, all drill results will be included in the feasibility study targeted for completion in the fourth quarter 2025.
  • Several underground exploration targets to be followed up in the coming years to potentially extend the mine life beyond the current 8 years.

 

Project Economics

  • Based on a $2,175/oz gold price, the Project’s undiscounted after-tax cash flows(2) total $397 million with an after-tax net present value (“NPV”) of $271 million(2), assuming a 5% discount rate, generating a30% internal rate of return (“IRR”).
  • Based on a spot gold price of $2,900/oz, the Project’s undiscounted after-tax cash flows(2) total $793 million with an after-tax NPV of $582 million(2), assuming a 5% discount rate, generating a IRR of 52%.
  • Mine Construction capital estimated at $157 million, nearly 60% of which is earmarked for dewatering activities.
  • LOM sustaining capital estimated to total $49 million.
  • All operating, processing, pre-production, mine construction, and sustaining costs have been updated relative to the 2021 PEA to reflect current market pricing.

 

Mining and Processing

  • Mining to use a combination of cut-and-fill and bench-and-fill methods unchanged from the previous study.
  • Nearly 60% of the material mined is anticipated to be processed at i-80 Gold’s Lone Tree autoclave facility (see Figure 3) and the remainder processed at a third-party roasting facility with whom the Company has an established contract.
  • Average gold grade processed of 10.4 g/t with an average gold recovery of 86% (autoclave) and 79% (roaster).
  • A summary of key valuation, cost, and operating metrics is presented in Table 1 below. For more detailed metrics presented on an annual basis, see Cove Project Detailed Cash Flow Model in Appendix.

 

Table 1: Summary of 2025 PEA Key Operating and Financial Metrics

 

Project Economics Unit
Gold Price $/oz $2,175
Silver Price $/oz $27.25
Pre-Tax NPV(5%)(2) $M $337
After-Tax Cash Flow(2) $M $397
After-Tax NPV(5%)(2) $M $271
After-Tax IRR % 30 %
Production Profile
Mine Life years 8
Mineralized Material Mined 000s
tonnes
2,675.6
Gold Grade of Mineralized Material Mined g/t Au 10.4
Silver Grade of Mineralized Material Mined g/t Ag 6.2
Waste Tonnes Mined 000s
tonnes
226.1
Total Tonnes Mined 000s
tonnes
2,901.8
Total Mineralized Material Processed 000s
tonnes
2,675.6
Gold Grade Processed g/t Au 10.4
Silver Grade Processed g/t Ag 6.2
Average Gold Recovery % 83 %
Average Silver Recovery % 24 %
Total Gold Recovered 000s oz 739.6
Total Silver Recovered 000s oz 114.5
Average Annual Gold Production (LOM) 000s oz 92.4
Average Annual Gold Production
(following production ramp up)
000s oz 100
Unit Operating Costs
LOM Operating Cost
Mineralized Material Mined $/t 142.2
Mineralized Material and Waste Mined $/t 141.0
Processed $/t milled 80.0
Transportation Costs $/t milled 20.8
Electricity Dewatering $/t milled 26.5
G&A $/t milled 21.5
LOM Total Cash Costs(1)
(net of by-product credit)
$/oz $1,194
LOM All-in Sustaining Costs(1)
(net of by-product credit)
$/oz $1,303
Total Capital Costs
Pre-Development Capital $M $17.3
Construction Capital $M $157.4
LOM Sustaining Capital $M $49.1
Closure Costs $M $31.3
Total Capital & Closure Costs(3) $M $255.1

 

“The Study highlights the value Cove brings to our gold portfolio, showcasing high-grade mineralization on a brownfield site in a top-tier mining jurisdiction, with low capital requirements and a high return on invested capital,” added Matthew Gili, President and Chief Operating Officer of i-80 Gold. “The Study primarily updates the 2021 PEA’s economic model and includes findings from hydrological studies, which have increased our understanding of the Project’s dewatering needs. Additionally, the completion of an exploration decline has enabled infill resource drilling and advanced metallurgical test work, which will be included in a feasibility study planned for the fourth quarter of 2025.”

 

Mineral Resource Update

 

The 2025 PEA is based on a revised resource model with no additional drilling results included, relative to the 2021 PEA. The updated resource estimate has been calculated using stope optimizer software, whereas the previous mineral resource was not. The new methodology generates optimal mineable stope geometries while considering several factors including geological constraints, grade distribution and stope dimensions. This significantly improves the accuracy of mineral resource estimates and has become an industry standard for underground deposits in Nevada.

 

The updated mineral resource estimate includes a total of 311,000 ounces of gold at 8.2 g/t Au in the indicated category and 1,156,000 ounces of inferred resources at 8.9 g/t in the inferred category (see Table 2). The majority of the indicated resource is currently hosted in the Helen deposit (see Figure 1). The updated estimate resulted in additional mineralized body constraints resulting in indicated and inferred tonnes decreasing by 6% and 13% respectively. Moreover, gold ounces decreased by 20% in the indicated and inferred categories, however the updated mineral resource represents more mineable shapes than the prior resource estimate.

 

The ongoing Cove drilling program has been designed to infill mineralization in the Helen and Gap zones ahead of a planned feasibility study in 2025. The Project offers substantial exploration potential as the bulk of the work completed to date has been focused on the main deposit areas only. Exploration from 2014 through 2019 resulted in the identification of several new zones of mineralization that have received minimal follow-up, including mineralization in the 2201 zone (153,000 tonnes at 26.7 g/t Au) beneath the Cove pit (see Figure 1).

 

Table 2: Cove Mineral Resource Estimate as at December 31, 2024

 

Indicated Mineral Resources
Tonnes Au Ag Au Ag
(000) (g/t) (g/t) (000 oz) (000 oz)
Helen 674 9.3 2.6 201 55
Gap 254 7.5 8.9 61 72
CSD 249 6.0 55.0 48 441
Total Indicated 1,178 8.2 15.0 311 569
Inferred Mineral Resources
Tonnes Au Ag Au Ag
(000) (g/t) (g/t) (000 oz) (000 oz)
Helen 1,582 8.4 2.9 427 146
Gap 2,022 8.4 9.0 543 585
CSD 290 5.9 57.8 55 538
2201 153 26.7 34.8 131 171
Total Inferred 4,046 8.9 11.1 1,156 1,439
 

Notes to table above:

I. Mineral resources have been estimated at a gold price of $2,175 per troy ounce and a silver price of $27.25 per troy ounce;
II. Mineral resources have been estimated using gold metallurgical recoveries ranging from 73.2% to 93.3% for roasting and 78.5% to 95.1 % for pressure oxidation;
III. Roaster cutoff grades range from 4.15 to 5.29 Au g/t (0.121 to 0.154 opt) and pressure oxidation cutoff grades range from 3.83 to 4.64 Au g/t (0.112 to 0.135 opt);  
IV. The effective date of the mineral resource estimate is December 31, 2024;
V. Mineral resources, which are not mineral reserves, do not have demonstrated economic viability. The estimate of mineral resources may be materially affected by environmental, permitting, legal, title, socio-political, marketing, or other relevant factors;
VI. An inferred mineral resource is that part of a mineral resource for which quantity and grade or quality are estimated on the basis of limited geological evidence and sampling. Geological evidence is sufficient to imply but not verify geological and grade or quality continuity. An inferred mineral resource has a lower level of confidence than that applying to an indicated mineral resource and must not be converted to a mineral reserve. It is reasonably expected that the majority of Inferred Mineral Resources could be upgraded to Indicated Mineral Resources with continued exploration; and
VII. The reference point for mineral resources is in situ.

 

Economic Analysis

 

Cove’s NPV and IRR in relation to fluctuations in the long-term gold price are demonstrated in Table 3 and the Project’s cost sensitivities are illustrated in Figure 2 below.

 

Table 3: Cove Project Gold Price Sensitivity After-tax Analysis

 

Gold Price ($/oz)
$1,850 $2,000 $2,175 $2,500 $2,750 $2,900 $3,000
NPV5%(2) ($M) $134 $198 $271 $409 $516 $582 $626
IRR (%) 19 % 24 % 30 % 40 % 47 % 52 % 54 %

 

 

Project Overview

 

The Project is located 25 miles southwest of the town of Battle Mountain, in the McCoy mining district in the Fish Creek Mountains of Lander County, Nevada (see Figure 3). The Cove deposit was mined by Echo Bay Mines Ltd. (Echo Bay) between 1988 and 2000 during which period the Cove deposit produced 2.6 million ounces of gold and 100 million ounces of silver. Gold and silver production from heap leach pads continued until 2006. The Project benefits from extensive historical geological datasets, its location in a jurisdiction with deep mining pedigree, and access to both local and regional infrastructure, including proximity to paved highways, electrical power, pre-existing mine infrastructure, and a skilled labor force.

 

i-80 Gold’s predecessor purchased the Cove project in 2012 and has since conducted significant exploration and infill drilling, metallurgical testing, and has advanced the permitting process. The Company expects to begin expending development capital, primarily for dewatering activities in late 2027 or early 2028 and for production to ramp up during 2029.

 

Geology and Mineralization

 

The Cove deposit consists of Helen, Gap, CSD, and 2201 zones. They are located beneath the historically mined Cove open pit and extend approximately 2,000 feet northwest from the pit (see Figure 1). The current mine plan includes Helen and Gap while CSD and 2021 could be included in a future mine plan, subject to the completion of additional technical work.

 

Three main types of mineralization occur at Cove. The Helen and Gap zones are Carlin-style disseminated refractory gold deposits. The Cove South Deep (CSD) gold and silver mineralization is similar in character to that at Helen and Gap but is characterized by silver to gold ratios of 50:1 to over 100:1. The 2201 zone is comprised of disseminated sulfides within sheeted stockwork veins and massive sulfide lenses replacing carbonate. Both styles of mineralization in the 2201 zone contain locally high concentrations of lead and zinc in addition to gold and silver. Structural controls on mineralization include the broad, gently southeast-plunging Cove anticline, several northeast striking dike-filled normal faults (Cay, Blasthole, Bay, 110, Gold Dome), mafic sills, and rheology contrasts.

 

Although most well-known Carlin-type deposits are hosted in Paleozoic slope and shelf carbonates, host rocks at Cove are silty to massive limestones and dolomites of the Triassic Star Peak Group. Limestone and silty limestone of the Favret Formation (approximately 700 feet thick) are the primary host for Carlin-style mineralization, and the Dixie Valley Formation conglomerates are the primary host of polymetallic vein mineralization in the 2201 zone.

 

Mining and Processing

 

The Study demonstrates an initial 8-year mine life with average annual gold production of approximately 100,000 ounces of gold following ramp up. The Study represents a preliminary point-in-time estimate of the mine plan. Once underground infrastructure is constructed a significant exploration program is planned to follow up on earlier positive drill results in a more cost-effective manner with a goal of extending the mine life beyond the current 8 years.

 

The high-grade mine will be accessed by a single ramp extending from the surface (elevation 4,625 ft) to the lowest extent of planned mining (elevation 3,430 ft). The access ramp will be large enough to accommodate 30-ton trucks. A series of raises will provide secondary egress and ventilation. A mining contractor will extract the mineralization using drift and fill mining methods at an average rate of approximately 1,100tonnes per day.

 

Metallurgical testing has demonstrated that both Helen and Gap resources are generally refractory and require an oxidation process to increase gold extraction using whole cyanidation of mineralized material. Composite testing has shown that Helen samples are generally more amenable to roasting and carbon-in-leach (“CIL”) processing, while the Gap zone is more amenable to an autoclave process followed by CIL. Upon the commencement of mining and processing, a detailed and systematic mineralized material control sampling program will be utilized to determine which of the two facilities (roaster vs. autoclave) the material should be routed to, to maximize recovery rates.

 

The PEA incorporates toll-milling arrangements with associated over-the-road trucking costs for both process streams. The PEA contemplates the use of the Lone Tree autoclave (owned by the Company and in respect of which an autoclave refurbishment class 3 engineering study is expected to be completed in 2025) and a third-party roaster for which a toll-milling agreement has been negotiated for the treatment of that material.

 

Capital Cost Summary

 

Mine construction capital is estimated to be $157.4 million. Approximately 60% of capital expenditures is for dewatering activities with the balance to be used for portal and underground development to gain access to the mineralized bodies (see Table 4). The low development capital required to construct Cove is due in part to the existence of significant infrastructure, including a portal to the Helen deposit and 5,739 feet of development work already completed. Permitting activities are well underway (see Permitting section for more detail). The permitting process is expected to take approximately three years to complete followed by 18 months of construction which is primarily dewatering and underground development, as well as some light surface infrastructure work.

 

Cove is expected to generate an estimated $379 million in net cash flow over the current 8-year mine life (see Figure 5).

 

Table 4: Capital Cost Estimates

 

Pre-
Development
Mine
Construction
Sustaining
($M) ($M) ($M)
Environmental, Permitting and Feasibility $7.0
Dewatering – Helen $39.5
Dewatering – Gap $48.4
Electrical Service and Powerline $10.5
Mine Development – Helen $24.8 $21.0
Mine Development – Gap $0.4 $20.3
Mine Facilities $2.2 $1.3
Pre-production Expense $5.0 $3.6
Resource Conversion Drilling $2.0
Contingency
(15% Drilling and Development; 25% Facilities)
$3.3 $28.0 $6.5
Total Capital Cost(3) $17.3 $157.4 $49.1

 

 

Operating Cost Summary

 

The 2025 PEA estimates a cash cost(1) of $1,194 per ounce of gold and an all-in sustaining costs(1) of $1,303 per ounce of gold for the LOM (see Table 5). Figure 6 illustrates these operating costs over Cove’s estimated production profile.

 

Table 5: Total and Unit Operating Costs

 

Total Costs Unit Cost Cost per Ounce
($M) ($/t milled) ($/oz Au)
Mining $408 $152 $552
Transportation & Processing $270 $101 $365
Electrical Power $71 $26 $96
G&A, Royalties & Net Proceeds Tax $138 $51 $186
By-Product Credits ($3) ($1) ($4)
Total Operating Cost/Cash Cost $883 $330 $1,194
Closure & Reclamation $31 $12 $42
Sustaining Capital $49 $18 $66
All-in Sustaining Costs(1) $963 $360 $1,303

 

 

Permitting

 

National Environmental Policy Act (NEPA) associated permitting activities continue to progress with all baseline study reports and the Plan of Operations Amendment having been submitted to the Bureau of Land Management (BLM).  The permitting action is anticipated to require a Notice of Intent to Complete an Environmental Impact Statement (EIS).  Following the EIS notification process, a public scoping period will be completed and a draft EIS will be prepared and subsequently posted for public review and comment.  The public comments and associated responses will be incorporated into the Final EIS document for BLM acceptance.

 

Nevada Division of Environmental Protection (NDEP) permitting activities are also in progress, focusing on the submittal and subsequent acceptance of modification applications to the site’s Water Pollution Control Permits and Reclamation Permit, in addition to, a new Air Quality Operating Permit application, submittal, and issuance.

 

These permitting activities are well underway and are expected to take approximately three years to complete from the effective date of the technical report, with permits anticipated by the end of 2027.

 

Next Steps to Feasibility Study

 

As stated earlier, a feasibility study under NI 43-101 with an updated mineral resource estimate is expected to be completed in the fourth quarter of 2025, in addition to a report prepared under S-K 1300. The updated resource will include 45,000 meters of drilling conducted since the completion of the exploration drift in the first quarter of 2023. Below is a summary of additional work to be conducted.

 

Resource Delineation and Exploration

  • Complete the ongoing underground resource delineation drilling and incorporate this data into the updated resource model.

 

Mining

  • A geotechnical characterization program is being implemented along with resource delineation for use in mine planning.
  • Complete additional testing of potential backfill sources to optimize the cemented rock fill mix design.
  • Complete a ventilation simulation to predict diesel particulate matter, carbon monoxide, and other contaminate concentrations.

 

Metallurgical Testing

 

The current resource delineation drilling program will provide samples needed for additional metallurgical testing to confirm the variability and viability of Helen and Gap resources to roasting and pressure oxidation (autoclave) with CIL. The objectives for the testing include:

  • Determine the location and number of samples required to represent the resources through geo-metallurgical analysis.
  • Assess the variability of the responses to roasting and calcine cyanidation across the resources.
  • Assess the variability of the responses to pressure oxidation (autoclave) and residue cyanidation across the resources.
  • Consider tests to optimize pressure oxidation (autoclave), such as temperature, retention time and acid strength.
  • Testing to establish head grade and extraction relations to support more detailed resource modelling.
  • Establish mineralogy impact and determine geologic domains.
  • Collect additional comminution data to assess hardness variability within the resources.

 

Technical Disclosure and Qualified Persons

 

The 2025 PEA was prepared in accordance with National Instrument 43-101 Standards of Disclosure for Mineral Projects (“NI 43-101”). The full 2025 PEA will be filed within 45 days under the Company’s issuer profile on SEDAR+ at www.sedarplus.ca and on i-80 Gold’s profile. An Initial Assessment for the Cove Project (“S-K 1300 Report”) was also prepared in accordance with Subpart 1300 (“S-K 1300”) and Item 601 of the Regulation S-K and the S-K 1300 Report will be filed on EDGAR at www.sec.gov. Both reports will be available on the Company’s website at www.i80gold.com. The mineral estimates and project economics are the same under the 2025 PEA and the S-K 1300 Report.

 

The technical information contained in this press release has been prepared under the supervision of, and has been reviewed and approved by Dagny Odell, P.E., (SME No. 2402150) Practical Mining LLC, and Tyler Hill CPG., Vice President Geology for the Company, who are all qualified persons within the meaning of NI 43-101 and S-K 1300.

 

For a description of the data verification, assay procedures and the quality assurance program and quality control measures applied by the Company, please see the Company’s Annual Information

Form dated March 12, 2024 filed under the Company’s profile on SEDAR+ at www.sedarplus.ca and filed with the Company’s Form 40-F under the Company’s profile on EDGAR at www.sec.gov. Further information about the 2025 PEA referenced in this news release, including information in respect of data verification, key assumptions, parameters, risks and other factors, will be contained in the 2025 PEA.

 

The Study is preliminary in nature and includes an economic analysis that is based, in part, on inferred mineral resources. Inferred mineral resources that are considered too speculative geologically to have for the application of economic considerations applied to them that would enable them to be categorized as mineral reserves, and there is no certainty that the results of the Study will be realized. Mineral resources do not have demonstrated economic viability and are not mineral reserves.

 

Endnotes

(1) This is a non-IFRS/non-GAAP measure. Please see both sections titled “Non-IFRS Performance Measures/Non-GAAP Financial Performance Measures” below.
(2) Cash flow and NPV are calculated as of the start of construction, which is anticipated to commence in January 2028.
(3) Total Capital Cost in Table 4 excludes $7.2 million of contingent payments related to the acquisition of the property in 2012.  These amounts are anticipated to be incurred in 2033 and 2034 and are based on reaching production milestones of 250,000 and 500,000 gold ounces, respectively.

 

About i-80 Gold Corp.

 

i-80 Gold Corp. is a Nevada-focused mining company with the fourth largest gold mineral resources in the state of Nevada. The recapitalization plan underway is designed to unlock the value of the Company’s high-grade gold deposits to create a Nevada mid-tier gold producer. i-80 Gold’s common shares are listed on the TSX and the NYSE American under the trading symbol IAU:TSX and IAUX:NYSE. Further information about i-80 Gold’s portfolio of assets and long-term growth strategy is available at www.i80gold.com or by email at info@i80gold.com.

 

 

APPENDIX

 

Cove Project Detailed Cash Flow Model

 

All amounts are in United States dollars, unless otherwise stated.

Cove Underground UNITS TOTAL LOM 2025E 2026E 2027E 2028E 2029E 2030E 2031E 2032E 2033E 2034E 2035E 2036E 2037E 2038E 2039E 2040+1
Y -3 Y -2 Y -1 Y 1 Y 2 Y 3 Y 4 Y 5 Y 6 Y 7 Y 8 Y 9 Y 10 Y 11 Y 12 Y 13
+1
MINING
Mine Life Years 8
Mineralized Material Mined k tonnes 2,676 150.3 156.8 444.3 429.9 452.3 383.7 397.2 261.0
Waste Moved k tonnes 226 33.7 12.2 41.9 41.0 24.5 29.1 31.2 12.5
Total Moved k tonnes 2,902 184.1 169.0 486.1 471.0 476.8 412.9 428.4 273.4
Mineralized Material Moved Daily tpd 916 411.9 429.7 1,217.2 1,177.9 1,239.3 1,051.3 1,088.2 715.0
Backfill Placed k tonnes 1,756 98.7 102.9 291.5 282.2 296.8 251.8 260.7 171.3
Capitalized Mining k tonnes 467 3.2 190.8 86.3 39.1 97.7 4.4 45.2
PROCESSING
Total Material for Processing k tonnes 2,676 150 157 245 272 594 600 397 261
Au Average Grade g/t Au 10.4 8.83 10.06 11.06 11.71 11.32 9.44 9.64 10.78
Contained Gold ‘000 oz Au 894 37.73 42.73 69.32 80.83 177.59 151.09 102.88 77.39
Autoclave Processing
Total Tonnes Processed k tonnes 1,518 81 85 86 312 342 351 261
Gold Grade g/t Au 10.02 9.37 10.06 12.26 10.94 9.20 9.02 10.78
Silver Grade g/t Au 8.40 3.45 3.50 4.58 13.98 9.43 7.15 6.42
Contained Gold ‘000 oz Au 489 24.3 27.3 34.1 109.8 101.1 101.9 90.4
Contained Silver ‘000 oz Ag 410 9.0 9.5 12.7 140.4 103.6 80.7 53.9
Gold Average Recovery % 86 % 85.6 % 85.6 % 85.6 % 85.6 % 85.6 % 85.6 % 85.6 %
Silver Average Recovery % 25 % 25.0 % 25.0 % 25.0 % 25.0 % 25.0 % 25.0 % 25.0 %
Recovered Gold ‘000 oz Au 418 20.8 23.4 29.1 94.0 86.5 87.2 77.4
Recovered Silver ‘000 oz Ag 102 2.2 2.4 3.2 35.1 25.9 20.2 13.5
Roaster Processing
Total Tonnes Processed k tonnes 1,158 70 72 245 185 282 258 46
Gold Grade g/t Au 10.89 8.20 10.07 11.06 11.45 11.74 9.76 14.37
Silver Grade g/t Ag 3.23 3.49 4.20 2.69 3.26 3.69 2.66 4.47
Contained Gold ‘000 oz Au 406 18.4 23.4 87.1 68.2 106.3 81.0 21.2
Contained Silver ‘000 oz Ag 120 7.8 9.8 21.2 19.4 33.4 22.1 6.6
Gold Average Recovery % 79 % 79.2 % 79.2 % 79.2 % 79.2 % 79.2 % 79.2 % 79.2 %
Silver Average Recovery % 10 % 10.0 % 10.0 % 10.0 % 10.0 % 10.0 % 10.0 % 10.0 %
Recovered Gold ‘000 oz Au 321 16.9 19.3 69.3 51.7 83.6 64.6 15.7
Recovered Silver ‘000 oz Au 12 0.8 1.0 2.1 1.9 3.3 2.2 0.7
Total Tonnes Processed k tonnes 2,675.6 150.3 156.8 244.9 271.6 593.9 599.9 397.2 261.0
Total Gold Production ‘000 oz Au 739.6 37.7 42.7 69.3 80.8 177.6 151.1 102.9 77.4
Total Silver Production ‘000 oz Ag 114.5 3.0 3.4 2.1 5.1 38.4 28.1 20.8 13.5
Total Gold Equivalent Production ‘000 oz Au 741.0 37.8 42.8 69.3 80.9 178.1 151.4 103.1 77.6
REVENUE
Gold Price $/oz Au $2,175 $2,175 $2,175 $2,175 $2,175 $2,175 $2,175 $2,175 $2,175 $2,175 $2,175 $2,175 $2,175 $2,175 $2,175 $2,175 $2,175
Silver Price $/oz Ag $27 $27.25 $27.25 $27.25 $27.25 $27.25 $27.25 $27.25 $27.25 $27.25 $27.25 $27.25 $27.25 $27.25 $27.25 $27.25 $27.25
Revenues $M $1,612 $82 $93 $151 $176 $387 $329 $224 $169
OPERATING COSTS
Mining Costs (incl. backfill) $M $381 $21.6 $22.4 $62.4 $61.9 $64.2 $54.7 $57.1 $36.2
Mining Costs (waste) $M $27 $4.1 $1.5 $5.1 $5.0 $3.0 $3.6 $3.7 $1.5
Autoclave Processing $M $118 $6.3 $6.6 $6.7 $24.4 $26.7 $27.4 $20.4
Roaster Processing $M $96 $5.8 $6.0 $20.3 $15.3 $23.3 $21.3 $3.8
Transportation $M $56 $3.2 $3.3 $6.6 $6.4 $12.6 $12.5 $6.9 $4.2
Electrical Power $M $71 $7.9 $9.0 $9.1 $8.0 $9.5 $9.1 $8.8 $8.3 $0.8 $0.2
G&A $M $58 $7.2 $7.2 $7.2 $7.2 $7.2 $7.2 $7.2 $7.2
Total Operating Cost $M $806 $56.1 $56.0 $110.6 $110.5 $144.1 $135.0 $114.9 $77.8 $0.8 $0.2
Refining & Sales $M $1 $0.1 $0.1 $0.1 $0.2 $0.3 $0.3 $0.2 $0.1
Royalties & State Taxes $M $79 $3.3 $4.2 $4.2 $8.1 $21.8 $17.0 $11.7 $8.4
Mining Costs
(mineralized material)
$/t mined $142.2 $144 $143 $140 $144 $142 $143 $144 $139
Mining Costs (waste) $/t mined $121.4 $122 $122 $121 $121 $122 $122 $120 $122
Autoclave Processing $/t milled $78.1 $78 $78 $78 $78 $78 $78 $78
Roaster Processing $/t milled $82.7 $83 $83 $83 $83 $83 $83 $83
Transportation $/t milled $20.8 $21 $21 $27 $23 $21 $21 $17 $16
Electrical Power $/t milled $26.5 $52 $57 $37 $30 $16 $15 $22 $32
G&A $/t milled $21.5 $48 $46 $29 $26 $12 $12 $18 $28
Total $/t milled $301.3 $266 $266 $168 $247 $231 $231 $238 $244
CAPITAL EXPENDITURES
Contingent Payments $M $7 $3.6 $3.6
Pre-Development Capital $M $17 $9.4 $4.6 $3.3
Capitalized Development & Construction $M $69 $35.3 $34.2
Dewatering $M $88 $69.9 $18.0
Sustaining Capital $M $49 $15.2 $6.8 $14.4 $0.7 $12.0
Total Capital $M $231 $9.4 $4.6 $3.3 $105.2 $52.2 $15.2 $6.8 $14.4 $4.3 $15.6
Reclamation $M $31 $0.2 $0.2 $0.2 $0.8 $0.8 $0.8 $0.8 $0.8 $0.8 $0.8 $0.8 $4.6 $4.6 $4.6 $4.6 $5.8
CASH COSTS & AISC
Total Cash Costs
(Inc. Royalty)
$/oz $1,194 $1,573 $1,408 $1,658 $1,467 $930 $1,003 $1,227 $1,112
AISC(1) $/oz $1,303 $1,595 $1,782 $1,768 $1,656 $938 $1,088 $1,235 $1,171
CASH FLOW ANALYSIS
Revenue $M $1,612 $82 $93 $151 $176 $387 $329 $224 $169
Operating Costs Gold & Royalties $M ($886) ($59) ($60) ($115) ($119) ($166) ($152) ($127) ($86) ($1) ($0)
Reclamation Accrual $M ($31) ($2) ($2) ($3) ($3) ($8) ($6) ($4) ($3)
Depreciation $M ($295) ($13) ($16) ($25) ($32) ($70) ($64) ($44) ($30)
Net Operating Income
(Pre-Tax)
$M $400 $8 $15 $8 $22 $143 $107 $50 $49 ($1) ($0)
Income Taxes $M ($84) ($3) ($5) ($2) ($6) ($33) ($23) ($11) ($7) $1 $1 $1 $1
Net Income $M $315 $5 $10 $6 $16 $111 $84 $39 $42 $0 $1 $1 $1
Depreciation $M $295 $13.3 $16.0 $25.2 $32.1 $70.2 $63.8 $43.5 $30.3
Reclamation $M ($0.2) ($0.2) ($0.2) ($0.8) $0.9 $1.1 $2.1 $2.7 $6.8 $5.5 $3.5 ($1.6) ($4.6) ($4.6) ($4.6) ($5.8)
Working Capital $M $0 ($6.9) ($0.1) ($6.3) ($0.4) ($5.5) $1.6 $2.9 $4.7 $9.9 $0.1 $0.0
Operating Cash Flow $M $610 ($0) ($0) ($0) ($1) $12 $27 $27 $50 $182 $155 $89 $75 $6 ($4) ($4) ($5)
Capital Expenditures $M ($231) ($9) ($5) ($3) ($105) ($52) ($15) ($7) ($14) ($4) ($16)
NET CASH FLOW $M $379 ($10) ($5) ($3) ($106) ($40) $12 $20 $36 $178 $139 $89 $75 $6 ($4) ($4) ($5)
PROJECT ECONOMICS As of Q1/2025 As of Q1/2028
After-tax NPV 5% discounting $M $214 $271
Notes to table above:
(1) AISC annual calculations include reclamation costs on a cash basis rather than on an accrual basis. As such, the weighted average of the annual AISC amounts will not agree to the life of mine AISC.

 

 


Figure 1: Cove Longitudinal Section of Mineralized Bodies and Drill Holes (Looking Northeast) (CNW Group/i-80 Gold Corp)

 

 

 


Figure 2: Cove Project Gold Price Sensitivity Cost Analysis (CNW Group/i-80 Gold Corp)

 

 

 


Figure 3: Cove Regional Map (CNW Group/i-80 Gold Corp)

 

 

 


Figure 4: LOM Processing Schedule (CNW Group/i-80 Gold Corp)

 

 

 


Figure 5: LOM Annual Cash Flow (CNW Group/i-80 Gold Corp)

 

 

 


Figure 6: LOM Gold Production Profile vs Cost per Ounce (CNW Group/i-80 Gold Corp)

 

Posted February 13, 2025

Share this news article

MORE or "UNCATEGORIZED"


NEVADA KING INTERCEPTS 2.44 G/T AU OVER 90.0M AND 3.17 G/T AU OVER 60.1M AT PIT BOTTOM, AS WELL AS 4.97 G/T AU & 163 G/T AG OVER 27.4M AT ATLANTA

Nevada King Gold Corp. (TSX-V: NKG) (OTCQB: NKGFF)  is pleased t... READ MORE

March 13, 2025

Goliath Resources Updated Modelling Confirms Its Large Gold Rich Layered System Is Directly Associated To Motherlode Intrusive Source (RIRG) And Multiple Gold Rich Feeder Dykes That Assayed Up To 12 g/t AuEq Over 10 Meters That Remain Open For Expansion, Surebet Discovery, Golden Triangle, B.C.

Dyke Highlights: 17 feeder dykes have been intersected in drill h... READ MORE

March 13, 2025

NGEx Drills 51.50m at 4.37% Cu and 10.42 g/t Au (12.26% CuEq), including 21.50m at 8.71% Cu and 23.81 g/t Au (26.68% CuEq), and 27.40m at 7.80% Cu and 23.17 g/t Au (25.19% CuEq) at Lunahuasi

NGEx Minerals Ltd. (TSX: NGEX) (OTCQX: NGXXF) is pleased to prov... READ MORE

March 13, 2025

Fortuna intersects 7.2 g/t Au over 31.5 meters at Kingfisher, Séguéla Mine, Côte d’Ivoire

Fortuna Mining Corp. (NYSE: FSM) (TSX: FVI) is pleased to provide... READ MORE

March 13, 2025

ARIS MINING REPORTS RECORD Q4 2024 FINANCIAL RESULTS WITH STRONG EBITDA GROWTH AND ANNOUNCES 25% CAPACITY EXPANSION AT MARMATO

Aris Mining Corporation (TSX: ARIS) (NYSE-A: ARMN) announces its... READ MORE

March 13, 2025

Copyright 2025 The Prospector News