Orezone Gold Corporation (TSX: ORE) (OTCQX: ORZCF) reported its operational and financial results for the first quarter of 2024.
All dollar amounts are in USD unless otherwise stated and abbreviation “M” means million.
Patrick Downey, President and CEO, commented “Our Bomboré mine had another quarter of consistent performance, delivering 30,139 ounces of gold production, mine earnings of $27 million, and positive free cashflow. In addition, we successfully commissioned the powerline connection to the national grid and substantially completed the construction of the MV3 resettlement site which will open mining access to the Siga East deposit in the third quarter of 2024.
Importantly, we continue to reinvest in the Bomboré mine and, after a careful review of available financing alternatives, the Company has decided to pursue its Phase II Hard Rock Expansion in two stages to better align capital requirements with funding sources. We have now received a debt proposal for the first stage of the expansion from our senior lender, Coris Bank, which we expect to finalize in the very near future.”
2024 FIRST QUARTER HIGHLIGHTS
(All mine site figures on a 100% basis) | Q1-2024 | Q1-2023 | |
Operating Performance | |||
Gold production | oz | 30,139 | 41,301 |
Gold sales | oz | 31,229 | 43,139 |
Average realized gold price | $/oz | 2,066 | 1,892 |
Cash costs per gold ounce sold1 | $/oz | 1,127 | 799 |
All-in sustaining costs1 (“AISC”) per gold ounce sold | $/oz | 1,324 | 926 |
Financial Performance | |||
Revenue | $000s | 64,685 | 81,712 |
Earnings from mine operations | $000s | 26,882 | 39,670 |
Net income attributable to shareholders of Orezone1 | $000s | 11,697 | 22,560 |
Net income per common share attributable to shareholders of Orezone1 Basic Diluted |
$ |
0.03 |
0.07 |
Adjusted EBITDA1 | $000s | 25,928 | 42,645 |
Adjusted earnings attributable to shareholders of Orezone1 | $000s | 7,736 | 24,574 |
Adjusted earnings per share attributable to shareholders of Orezone1 | $ | 0.02 | 0.07 |
Cash and Cash Flow Data | |||
Operating cash flow before changes in working capital | $000s | 20,357 | 41,137 |
Operating cash flow | $000s | 13,637 | 38,926 |
Free cash flow1 | $000s | 2,013 | 31,498 |
Cash, end of period | $000s | 15,597 | 45,172 |
1 Cash costs, AISC, Adjusted EBITDA, Adjusted earnings, Adjusted earnings per share, and Free cash flow are non-IFRS measures. See “Non-IFRS Measures” section below for additional information.
The Phase II Hard Rock Expansion
A hard rock plant, to complement the existing Phase I oxide plant, is required to process the fresh rock and lower transition mineral reserves of the Bomboré orebody.
The Company originally contemplated constructing a 4.4 million tonnes per annum hard rock plant in a single stage as outlined in its 2023 feasibility study. Following a recent review of available financing sources, the Company has decided to complete this brownfield expansion in two stages to better manage its capital requirements. Stage 1 will consist of an initial 2.5Mtpa hard rock plant, with a future Stage 2 expansion increasing hard rock plant throughput to 5.0Mtpa – 7.0Mtpa.
A preliminary capital cost for this initial 2.5Mtpa hard rock plant is estimated at $80 million, significantly less than the $167.5 million estimated for the 4.4Mtpa hard rock plant. The Company expects to finance the construction costs of this Stage 1 hard rock plant (rescoped “Phase II Hard Rock Expansion”) primarily through senior debt and cash flow generated from its Phase I oxide operations during the construction period.
The Company has significantly advanced discussions with Coris Bank for additional project debt and anticipates concluding a binding debt commitment in June 2024. Based on forecasted construction and key equipment timelines, the Company expects first gold from the Phase II Hard Rock Expansion to be achieved in late 2025.
The Company intends to provide more detailed guidance for its Phase II Hard Rock Expansion later this year after the Company has secured a binding debt commitment and Board approval to proceed with the expansion.
BOMBORÉ GOLD MINE (100% BASIS) – OPERATING HIGHLIGHTS
Q1-2024 | Q1-2023 | ||
Safety | |||
Lost-time injuries frequency rate (LTIFR) | per 1M hours | 0.00 | 0.00 |
Personnel-hours worked | 000s hours | 1,410 | 928 |
Mining Physicals | |||
Ore tonnes mined | tonnes | 2,402,533 | 2,205,056 |
Waste tonnes mined | tonnes | 3,123,099 | 2,382,135 |
Total tonnes mined | tonnes | 5,525,631 | 4,587,191 |
Strip ratio | waste:ore | 1.3 | 1.1 |
Processing Physicals | |||
Ore tonnes milled | tonnes | 1,355,619 | 1,445,693 |
Head grade milled | Au g/t | 0.78 | 0.96 |
Recovery rate | % | 89.0 | 92.2 |
Gold produced | Au oz | 30,139 | 41,301 |
Unit Cash Cost | |||
Mining cost per tonne | $/tonne | 3.48 | 2.91 |
Mining cost per ore tonne processed | $/tonne | 8.02 | 6.51 |
Processing cost | $/tonne | 9.24 | 9.21 |
Site general and admin (“G&A”) cost | $/tonne | 3.79 | 3.23 |
Cash cost per ore tonne processed | $/tonne | 21.05 | 18.96 |
Cash Costs and AISC Details | |||
Mining cost (net of stockpile movements) | $000s | 10,867 | 9,417 |
Processing cost | $000s | 12,520 | 13,322 |
Site G&A cost | $000s | 5,134 | 4,667 |
Refining and transport cost | $000s | 117 | 148 |
Government royalty cost | $000s | 5,132 | 4,912 |
Gold inventory movements | $000s | 1,416 | 2,019 |
Cash costs1 on a sales basis | $000s | 35,186 | 34,485 |
Sustaining capital | $000s | 4,018 | 3,530 |
Sustaining leases | $000s | 73 | 187 |
Corporate G&A cost | $000s | 2,069 | 1,731 |
All-In Sustaining Costs1 on a sales basis | $000s | 41,346 | 39,933 |
Gold sold | Au oz | 31,229 | 43,139 |
Cash costs per gold ounce sold1 | $/oz | 1,127 | 799 |
All-In Sustaining Costs per gold ounce sold1 | $/oz | 1,324 | 926 |
1 Non-IFRS measure. See “Non-IFRS Measures” section for additional details.
Bomboré Production Results
Gold production in Q1-2024 was 30,139 ounces, a decline of 27% from the 41,301 ounces produced in Q1-2023. The lower gold production is attributable to an 18% decrease in head grades, a 6% decline in plant throughput, and a 3% decrease in plant recoveries. The better head grade achieved in Q1-2023 was primarily the result of processing of high-grade stockpiles accumulated during the Phase I construction which have now been fully depleted. Mill availability in Q1-2024 was impacted by the commissioning of grid power to site and from the shortage of power from the national grid towards the end of the quarter. In addition, as mining deepens in the certain pits, the quantity of transition ore has started to increase. The presence of transition ore results in slightly lower metallurgical recoveries, lower plant throughput, and additional plant maintenance due to the harder nature of the ore.
Plant throughput, head grades, and recoveries are expected to improve from a greater blend of oxide ore once mining commences at Siga East in Q3-2024.
Bomboré Operating Costs
AISC per gold ounce sold in Q1-2024 was $1,324, a 43% increase from the $926 per ounce sold in Q1-2023. The higher AISC is primarily the result of: (a) lower Q1-2024 gold production and sales as explained above; (b) greater per ounce royalty costs from new royalty rates that took effect in October 2023 and from a higher realized selling price; and (c) increased mining costs.
Cash cost per ore tonne processed in Q1-2024 was $21.05 per tonne, an increase of 11% from the $18.96 per tonne in Q1-2023. The higher cash cost in Q1-2024 was predominantly due to increased mining and site G&A costs, and from fewer ore tonnes processed. Mining costs have increased as lower benches are mined resulting in longer hauls and more transition material that requires drill-and-blast prior to excavation. In addition, unit mining costs have increased from a higher strip ratio and more management fees from the mobilization of a second mining contractor in July 2023 to supplement material movement of the main mining contractor. Site G&A costs reflect greater spending for security as the Company expands its operations into the southern portion of the mining permit.
Processing costs per ore tonne has remained relatively stable from $9.21 per tonne in Q1-2023 to $9.24 per tonne in Q1-2024. Unit processing costs were expected to decline in Q1-2024 from 2023 levels upon the introduction of grid power to the Bomboré mine at the end of January 2024; however, the power costs savings from using grid power has been offset by greater blend of transition ore requiring higher per tonne consumption of power, grinding media, and main reagents; more plant maintenance to address higher equipment wear; and from lower plant throughput resulting in fixed processing costs being absorbed over fewer tonnes in Q1-2024. Furthermore, the mine relied on more self generated power beginning in March 2024 from lower-than-expected availability of grid power as the dry season impacted the contributions of hydropower to the national grid.
Bomboré Growth Capital Projects
Grid Power Connection
The commissioning of the powerline to connect Bomboré to Burkina Faso’s national energy grid commenced in January 2024 and was successfully energized by the end of the same month. As of March 31, 2024, the Company has incurred costs of $19.3M for the grid power connection, of which $1.1M was incurred in Q1-2024.
Resettlement Action Plan Phases II and III
RAP Phases II and III involve the construction of three new resettlement communities (MV3, MV2, and BV2) in order to relocate households currently residing within the southern half of the Bomboré mining permit. The Company has sequenced MV3 first in order to gain access to mining areas that are currently contemplated in the 2024 mine plan.
Construction of MV3 was substantially completed in April 2024 with the Company now organizing with local leaders and residents to relocate families into their new resettlement homes later in Q2-2024. In parallel, the Company has commenced earthworks for the next resettlement site (MV2) and awarded contracts to local companies to begin construction shortly.
As of March 31, 2024, the Company has incurred project-to-date costs of $13.5M for RAP Phases II and III, of which $3.1M was incurred in Q1-2024.
NON-IFRS MEASURES
The Company has included certain terms or performance measures commonly used in the mining industry that is not defined under IFRS, including “cash costs”, “AISC”, “EBITDA”, “adjusted EBITDA”, “adjusted earnings”, “adjusted earnings per share”, and “free cash flow”. Non-IFRS measures do not have any standardized meaning prescribed under IFRS, and therefore, they may not be comparable to similar measures presented by other companies. The Company uses such measures to provide additional information and they should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. For a complete description of how the Company calculates such measures and reconciliation of certain measures to IFRS terms, refer to “Non-IFRS Measures” in the Management’s Discussion and Analysis for the three months ended March 31, 2024 which is incorporated by reference herein.
QUALIFIED PERSONS
The scientific and technical information in this news release was reviewed and approved by Dr. Pascal Marquis, Geo., Senior Vice President of Exploration and Mr. Rob Henderson, P. Eng, Vice President of Technical Services, both of whom are Qualified Persons as defined under NI 43-101 Standards of Disclosure for Mineral Projects.
About Orezone Gold Corporation
Orezone Gold Corporation is a West African gold producer engaged in mining, developing, and exploring its 90%-owned flagship Bomboré Gold Mine in Burkina Faso. The Bomboré mine achieved commercial production on its oxide operations on December 1, 2022, and is now focussed on its staged hard rock expansion that is expected to materially increase annual and life-of-mine gold production from the processing of hard rock mineral reserves. Orezone is led by an experienced team focused on social responsibility and sustainability with a proven track record in project construction and operations, financings, capital markets, and M&A.
Falco Resources Ltd. (TSX-V: FPC) is pleased to announce the closing of ... READ MORE
Arizona Metals Corp. (TSX: AMC) (OTCQX: AZMCF) is pleased to announce th... READ MORE
Skyharbour Resources Ltd. (TSX-V: SYH) (OTCQX: SYHBF) (Frankfurt... READ MORE
Brunswick Exploration Inc. (TSX-V: BRW) (OTCQB: BRWXF) (FRANKFURT:1XQ) i... READ MORE
Blue Moon Metals Inc. (TSX-V: MOON), Nussir ASA and Nye Sulitjel... READ MORE