
Argonaut Gold Inc. (TSX: AR) announces the Company’s 2024 guidance including production, cost per ounce as well as capital and exploration expenditure forecasts.
Consolidated gold production for 2024, including the Mexican operations, is expected to be in the range of 225,000 and 250,000 gold equivalent ounces an increase of 13% to 25% over 2023 production. Cost of sales and cash costs per ounce of gold sold are expected to be similar to 2023, while all-in-sustaining costs per ounce sold are expected to be higher than 2023 due to the increase in sustaining capital at Magino and Florida Canyon. Higher sustaining costs at Magino are related to the completion of the tailings management facility. At Florida Canyon, higher sustaining costs are due to the construction of the third heap leach pad.
In 2023, Argonaut achieved a significant milestone with the commissioning of its flagship asset, the Magino mine. Ramp up continues into 2024 and the mining and milling rates are expected to be in line with Magino’s NI 43-101 Technical Report 2022 in the second half of 2024. Analysis to-date shows that total contained gold is projected to be within 1% of the reserve model compared to grade control polygons. While we believe the block model properly estimates the grade of the ore, the mine site is experiencing higher dilution rates than anticipated in the Technical Report due to challenges with selectively mining the high-grade parts of the ore body. As a result of the higher dilution than previously modeled in the high-grade areas of the deposit, the average grade to the mill is expected to be approximately 5 to 10% lower than in the Technical Report over the next 2 to 3 years; however, life-of-mine grades and ounces are not expected to be impacted. The Company expects to have an updated technical report with the latest findings filed in the second half of 2024.
“Over the last few months, we have analyzed our mining practices and grade and tonnes modeled and delivered to the process plant, in great detail. We have learned that selectively mining the high-grade portion of the deposit to the extent predicted in the Technical Report, in the initial three years, may not be achievable. In 2024, lower grades due to pit sequencing coupled with lower mining and processing rates in the first half of the year are expected to be offset by higher mill throughput in the second half of the year following the completion of optimization work underway in the first half of the year and improvements in mill availability,” stated Marc Leduc, Chief Operating Officer of Argonaut Gold. “Notably, gold recoveries are on plan, while unit costs are expected to be higher in 2024 relative to the Technical Report but decline over the following 12 to 18 months as we continue to work through the ramp up process.”
“Operationally, our near-term focus continues to be the ramp up of the Magino mine. The medium-term goal is to expand the reserve base and mill throughput in order to increase production to the 200,000 to 250,000 ounce per year range, while reducing the cost structure. Given the grade of the deposit, scale is important to drive strong free cash flows. We anticipate completing a re-financing of our current debt package by the end of the first quarter to provide sufficient liquidity during this ramp-up phase and for our future growth objectives,” stated Richard Young, President and Chief Executive Officer.
2024 OUTLOOK
The following table outlines the Company’s 2024 outlook for key operating and financial statistics:
Magino
Mine |
Florida Canyon Mine |
La Colorada
Mine |
San Agustin
Mine |
El Castillo
Mine |
Consolidated Guidance |
||
Operating Results | |||||||
Ore Mined | (‘000t) | 5,200 – 6,000 | 9,800 – 10,800 | – | 6,800 – 7,100 | – | |
Waste Mined | (‘000t) | 15,300 – 17,500 | 10,900 – 11,900 | – | 5,800 – 6,100 | – | |
Total Mined | (‘000t) | 20,500 – 23,500 | 20,700 – 22,700 | – | 12,600 – 13,200 | – | |
Grade mined | (g/t) | 0.95 – 1.00 | 0.27 – 0.29 | – | 0.45 – 0.50 | – | |
Contained oz mined | (oz) | 160,000 – 195,000 | 85,000 – 100,000 | – | 100,000 – 115,000 | – | |
Strip ratio | w/o | 2.92 – 2.94 | 1.10 – 1.11 | – | 0.85 – 0.86 | – | |
Crushed tonnes | (‘000t) | – | 5,600 – 6,500 | – | 6,800 – 7,100 | – | |
ROM tonnes | (‘000t) | – | 3,800 – 4,400 | – | – | – | |
Total Placed/milled | (‘000t) | 3,500 – 3,600 | 9,400 – 10,900 | – | 6,800 – 7,100 | – | |
Crushed grade | (g/t) | – | 0.30 – 0.36 | – | 0.45 – 0.50 | – | |
ROM grade | (g/t) | – | 0.13 – 0.18 | – | – | – | |
Processed grade | (g/t) | 1.10 – 1.20 | 0.27 – 0.29 | – | 0.45 – 0.50 | – | |
Recovery rate | % | 90% – 92% | 59 – 61% | – | 37% – 39% | – | |
Recoverable Placed | (oz) | – | 50,000 – 62,000 | – | 35,000 – 40,000 | – | |
GEO’s produced | (oz) | 120,000 – 130,000 | 63,000 – 70,000 | 5,000 – 6,000 | 35,000 – 40,000 | 2,000 – 4,000 | 225,000 – 250,000 |
Cost of sales | $/oz sold | 1,400 – 1,550 | 1,850 – 1,950 | 1,950 – 2,050 | 1,950 – 2,050 | 1,100 – 1,200 | 1,650 – 1,750 |
Cash cost | $/oz sold | 1,050 – 1,200 | 1,575 – 1,675 | 1,600 – 1,700 | 1,650 – 1,750 | 1,100 – 1,200 | 1,350 – 1,450 |
All-in sustaining cost | $/oz sold | 1,650 – 1,800 | 2,350 – 2,450 | 1,600 – 1,700 | 1,800 – 1,900 | 1,100 – 1,200 | 1,950 – 2,050 |
Production cost | $000s | 140,000 – 145,000 | 110,000 – 113,000 | 9,000 – 10,000 | 65,000 – 72,000 | 2,200 – 4,600 | 326,200 – 344,600 |
Cost Per Tonne | |||||||
Mining | $/t | 3.55 – 3.85 | 2.05 – 2.35 | – | 2.20 – 2.50 | – | |
Mining (ore tonne) | $/t | 13.95 – 14.25 | 4.35 – 4.65 | – | 4.10 – 4.40 | – | |
Crushing | $/t | 2.25 – 2.55 | – | 1.15 – 1.45 | – | ||
Processing | $/t | 13.20 – 13.50 | 1.65 – 1.95 | – | 3.35 – 3.65 | – | |
G&A | $/t | 7.65 – 7.85 | 1.80 – 2.00 | – | 1.20 – 1.40 | – | |
Capital Expenditures | |||||||
Sustaining Capital (including leases) | $ million | 61,000 – 63,000 | 39,000 – 40,000 | – | 6,500 – 7,000 | – | 106,500 – 110,000 |
Construction Capital | $ million | 2,900 – 3,000 | 10,000 – 11,000 | – | – | – | 12,900 – 14,000 |
Capital Stripping | $ million | – | 15,000 – 16,000 | – | – | – | 15,000 – 16,000 |
Reclamation & Other | $ million | – | 7,000 – 7,500 | – | – | 3,500 – 3,800 | 10,500 – 11,300 |
Capitalized Exploration | $ million | 14,000 – 15,000 | – | – | – | 14,000 – 15,000 |
Magino:
Florida Canyon
Mexico Operations
Qualified Person, Technical Information
The technical information contained in this press release has been prepared under the supervision of, and has been reviewed and approved by Mr. Marc Leduc, P.Eng. Chief Operating Officer; a Qualified Person as defined by National Instrument 43-101 – Standards of Disclosure for Mineral Projects. For further information on the Magino Mine, please see the technical report titled Magino Gold Project, Ontario, Canada, NI 43-101 Technical Report, Mineral Resource and Mineral Reserve Update dated March 3, 2022 (effective date of February 14, 2022) on the Company’s website www.argonautgold.com or on www.sedarplus.ca.
About Argonaut Gold
Argonaut Gold is a Canadian-based gold producer with a portfolio of operations in North America. Focused on becoming a low-cost, mid-tier gold producer, the Company’s flagship asset, Magino Mine, is expected to become Argonaut’s largest and lowest cost mine. The Company is pursuing potential for re-development and additional growth at the Florida Canyon Mine in Nevada, USA. Together, the Magino and Florida Canyon mines are the Company’s cornerstone assets that will drive Argonaut through this pivotal growth stage. The Company also has one additional operating mine in Mexico, the San Agustin Mine in Durango.
Commerce Resources Corp. (TSX-V: CCE) (FSE: D7H0) is pleased to... READ MORE
North Bay Resources, Inc. (OTC: NBRI) is pleased to announce a re... READ MORE
NevGold Corp. (TSX-V:NAU) (OTCQX:NAUFF) (Frankfurt:5E50) is pleas... READ MORE
G2 Goldfields Inc. (TSX: GTWO) (OTCQX: GUYGF) is pleased to annou... READ MORE
Aya Gold & Silver Inc. (TSX: AYA) (OTCQX: AYASF) announced fi... READ MORE