Volt Lithium Announces Preliminary Economic Assessment at Rainbow Lake Project in Alberta, Highlighted by 45% IRR and US$1.5 Billion Before-Tax NPV8

You have opened a direct link to the current edition PDF

Open PDF Close
Uncategorized

Share this news article

Volt Lithium Announces Preliminary Economic Assessment at Rainbow Lake Project in Alberta, Highlighted by 45% IRR and US$1.5 Billion Before-Tax NPV8

 

 

 

 

 

  • Pre-tax US$1.5 Billion NPV8 and IRR of 45%
  • Rainbow Lake Area has a long history of resource extraction, well established infrastructure, and supportive government

 

Volt Lithium Corp. (TSX-V: VLT) is pleased to announce the summary results from the Company’s Preliminary Economic Assessment for the Rainbow Lake Lithium Project  a lithium brine project in northwest Alberta, Canada, where the Company owns lithium rights across 430,000 acres of land. The PEA outlines the estimated production scaling from 1,000 to over 23,000 metric tonnes per year of battery-grade lithium hydroxide monohydrate over a 19-year period. Volt’s completed NI 43-101 PEA Technical Report is expected to be filed on SEDAR+ within 45 days.

 

All dollar values in this press release are stated in US dollars unless otherwise noted.

 

“We are very pleased with the results of the PEA” commented Alex Wylie, President & CEO of Volt. “Volt’s focus on extracting lithium from oilfield brines allows for significant project returns and economics that will allow Volt to grow its lithium production in a measured and responsible way.”

 

Rainbow Lake PEA Highlights1

  • Production growing from 1,000 to over 23,000 metric tonnes per year (average over years 5 to 19) of battery grade LHM2 spanning a 19-year period;
  • Pre-tax $1.5 Billion NPV at 8% discount rate and IRR of 45%;
  • After-tax $1.1 Billion NPV8 and IRR of 35%;
  • Volt has entered into a capital expenditure recovery program and cost sharing arrangement with a private oil and gas company, which is expected to allow Volt to significantly enhance overall project economics3;
  • OPEX of approximately $3,276/tonne LHM in the Muskeg formation, with an average grade of 92 mg/L and approximately $4,545/tonne in the Keg River formation with an average grade of 49 mg/L; and
  • Project economics assumed $25,000/tonne LHM and provides strong leverage to higher lithium prices.

 

_________________
1 Readers are cautioned that reliance on information in this announcement without reference to the Technical Report may not be appropriate. The forthcoming Technical Report is meant to be read as a whole, and sections should not be read or relied upon out of context
2 23,000 metric tonnes lithium hydroxide monohydrate (“LHM”) is equivalent to 20,240 metric tonnes lithium carbonate equivalent (“LCE”)
3 Volt’s cost sharing arrangement with the E&PCo treated as Other Revenue in the cash flow statement for the IRR Analysis

 

Rainbow Lake PEA

 

Introduction

 

The Rainbow Lake PEA was compiled by Sproule Associates Limited integrating the work of Sproule and other consultants each having the qualifications necessary to author their respective sections of the PEA.

 

Volt is a lithium brine exploration and development company focused on advancing its Rainbow Lake Project in northern Alberta, Canada. The Rainbow Lake Project is based on a LHM plant with an assumed 19-year production life.

 

Volt will target production growth in three phases:

  • Phase 1: Production is targeted at 1,000 tonnes per annum focused on the Muskeg formation with an average lithium grade of 92 mg/L.
  • Phase 2: Volt intends to expand production to 5,000 tpa of LHM primarily focused on the Muskeg formation.
  • Phase 3: Volt intends to expand production to an average of approximately 23,000 tpa of LHM focused on the Muskeg and Keg River formations.

 

During the production ramp-up, Volt will maintain an ongoing exploration program to further its understanding of the reservoirs in the Rainbow Lake Area with the goal of targeting lithium production from brines in the Muskeg and Keg River formations offering the highest lithium concentrations.

 

The PEA contemplates brines will be treated using the Company’s proprietary direct lithium extraction technology that has been proven to selectively extract lithium from brine. This IES-300 technology was successfully tested during the Company’s Pilot Program conducted during the second quarter of 2023 and was used as the basis for the PEA. After passing through the extraction process, the concentrated lithium brine stream will undergo further processing steps including purification, concentration and conversion in order to produce commercial battery grade LHM.

 

Economic Analysis

 

The base case analysis assumes a long-term LHM price of $25,000/tonne. Using this price assumption, the Rainbow Lake Project generates a positive NPV8 of $1.5 billion pre-tax and $1.1 billion after-tax.

 

Key indicators and PEA Highlights are shown below in Table 1.

 

Table 1 – PEA Highlights

 

 

Initial Annual Production LHM tpa(1) 1,020(2)
Average Production Yrs 3-4 LHM tpa 5,028
Average Production Yrs 5 – 19 LHM tpa 23,031
Average Annual Production LHM tpa 18,906
Plant Operating Life years 19(3)
Total Capital Expenditures $ millions 1,549(4)(5)
Annual Operating Cost – Muskeg $/t 3,276(6)
Annual Operating Cost – Keg River $/t 4,545(6)
Selling Price $/t 25,000
Net Present Value – Pre-Tax $ millions 1,469
Net Present Value – After-Tax $ millions 1,063
Internal Rate of Return (IRR) Pre Tax % 45
Internal Rate of Return (IRR) After Tax % 35

Notes:

 

All model outputs are expressed on a 100% project ownership basis with adjustments for project financing assumptions.

 

  1. Tonnes (1,000 kg) per annum.
  2. Initial annual production figure represents Year 2 production, following a ramp-up period in Year 1.
  3. Plant design and financial modelling based on 19-year economic life.
  4. Capital Expenditures include 15% contingency for facility capital and 10% contingency for total development capital.
  5. No inflation or escalation has been carried for the economic modelling.
  6. Includes operating expenditures and sustaining capital.
  7. Selling price of battery-quality LHM based on a flatline price of $25,000/t over total project lifetime.
  8. Assumes a corporate tax rate of 23% and Royalty Tax rate of 1%, prior to project payout and 12% post project payout.
  9. Any discrepancies in the totals are due to rounding effects.

 

Capital Expenditures and Operating Costs

 

The capital expenditure estimate was prepared in accordance with the Association for the Advancement of Cost Engineering Class 5 Study standards, and has an approximate accuracy of +50% / -30%.

 

Assuming average production over 19 years of 18,906 tpa of LHM, the direct capital costs are estimated at $1.4 billion, with indirect costs of $95 million. A contingency of 10% was applied to total development program costs and 15% was applied to the facilities and indirect costs, yielding an estimated all-in capital cost of $1.55 billion.

 

The total estimated CAPEX for the project is presented in Table 2 below, inclusive of contingency.

 

Table 2 – CAPEX

 

    CAPEX ($ million)
Area Operations – Phase 1    
DLE Facilities   21
Drilling and Pipeline Costs   33
Indirect Costs   5
Admin and Power Generation   1
Subtotal   60
Area Operations – Phase 2    
DLE Facilities   60
Drilling and Pipeline Costs   152
Indirect Costs   24
Admin and Power Generation   6
Subtotal   242
Area Operations – Phase 3    
DLE Facilities   398
Drilling and Pipeline Costs   465
Indirect Costs   66
Admin and Power Generation   17
Subtotal   946
Central Processing Facility    
Lithium Processing Plant   165
Administrative Plan   3
Onsite Infrastructure   15
Subtotal   183
Total Direct Costs   1,431
Contingency – Facility Contingency   118
Total Project Costs   1,549

 

The operating expenditure estimate for the project was also prepared in accordance with the AACE Class 5 Study standard. The total OPEX is presented in Table 3 below.

 

Table 3 – OPEX

 

  Average Annual Cost ($/t)(1)
  Muskeg Keg River
Reagents 1,769 2,597
Consumables 272 513
Power 244 444
Labour(2) 250 250
Maintenance Materials and Services(3) 300 300
Transport and Logistics 115 115
General and Administrative 326 326
Total Annual OPEX 3,276 4,545


Notes:

  1. Operating costs are calculated based on average annual production of 19,299 tonnes of LHM.
  2. Approximately 65 full time equivalent positions.
  3. Includes contract maintenance, solids waste disposal, and external lab services.

 

Processing Overview & Cost Arrangements

 

As outlined above, Volt will deploy a three-phase strategy to grow its operations at Rainbow Lake. This is expected to facilitate a measured roll-out that allows for continued exploration of the reservoir, which ensures the Company is focused on area operations with the highest lithium grades, while minimizing dilution to shareholders as Volt anticipates using debt and other financing strategies to support growth while in commercial operations.

 

The capital cost arrangement with the E&PCo is structured to allow Volt to recover all capital expenditures it incurs for the recompletion and drilling of production wells to a total payout up to 200% of the original capital cost of the Wells. For the disposal wells, Volt’s capital cost arrangement is as follows: a) In Phase 1 Volt will pay 50% of the capital costs associated with the disposal wells and will receive a total payout of up to 200% of the capital costs paid by Volt for the disposal wells; and (b) In Phases 2 and 3, Volt will pay 100% of the capital costs associated with the disposal wells and will receive a total payout of up to 200% of the capital costs of the disposal wells. The Company has also entered into an operating agreement with the E&PCo whereby the E&PCo will pay Volt operating costs to manage shared wells and facilities on behalf of both the E&PCo and the Company. The Cost Arrangement and the OPEX Agreement significantly improve overall project economics for Volt at Rainbow Lake.

 

Volt’s proprietary IES-300 process produces a high-quality lithium chloride solution which will be further purified and concentrated by means of reverse osmosis, chemical softening and ion exchange. After purification and concentration of the raw lithium chloride, a conventional, two-stage, lithium carbonate crystallization process will be deployed for final conversion of the polished lithium chloride to battery-quality LHM.

 

Project Economics

 

The financial results described above are derived from inputs based on the annual production schedule as set forth in the PEA and summarized in Table 1 above. Sensitivity analysis on the economic results over a 19-year operating life are summarized in Table 4 below.

 

Table 4: Sensitivity Analysis

 

  After Tax NPV Discounted
at 8% (MM$US)
After Tax IRR (%)
LHM Price    
-20% 616 23.1
0% 1,063 34.9
+20% 1,506 48.9
Production    
-5% 952 31.8
0% 1,063 34.9
+5% 1,175 38.2
Capital Costs    
+20% 901 26.3
0% 1,063 34.9
-20% 1,221 50.4
Operating Costs    
+20% 980 32.8
0% 1,063 34.9
-20% 1,145 37.1

About Volt

 

Volt is a lithium development and technology company aiming to be North America’s first commercial producer of lithium hydroxide and lithium carbonates from oilfield brine. Our strategy is to generate value for shareholders by leveraging management’s hydrocarbon experience and existing infrastructure to extract lithium deposits from existing wells, thereby reducing capital costs, lowering risks and supporting the world’s clean energy transition. With four differentiating pillars, and a proprietary Direct Lithium Extraction technology and process, Volt’s innovative approach to development is focused on allowing the highest lithium recoveries with lowest costs, positioning us well for future commercialization. We are committed to operating efficiently and with transparency across all areas of the business staying sharply focused on creating long-term, sustainable shareholder value.

 

Posted December 14, 2023

Share this news article

MORE or "UNCATEGORIZED"


Ascot Announces Closing of C$34 Million Bought Deal Financing

Ascot Resources Ltd. (TSX: AOT) (OTCQX: AOTVF) is pleased to anno... READ MORE

July 25, 2024

RUA GOLD Closes C$8 Million Brokered Offering and Announces Commencement of Trading on the TSX Venture Exchange

Highlights Closing the fully subscribed brokered offering for C$8... READ MORE

July 25, 2024

Mosaic Acquires 100% of the Amanda Project

Mosaic Minerals Corporation (CSE: MOC) announces that it has sign... READ MORE

July 25, 2024

First Phosphate Confirms Significant High-Quality Igneous Phosphate Deposit at Its Bégin-Lamarche Project in the Saguenay-Lac-St-Jean Region, Quebec au Canada

First Phosphate Corp. (CSE: PHOS) (OTC: FRSPF) (FSE: KD0) is ple... READ MORE

July 25, 2024

PROSPECT RIDGE ANNOUNCES FINAL CLOSING OF ITS OVERSUBSCRIBED PRIVATE PLACEMENT

Prospect Ridge Resources Corp.  (CSE: PRR) (OTC: PRRSF) (FRA: OE... READ MORE

July 25, 2024

Copyright 2024 The Prospector News