Osisko Metals Incorporated (TSX: OM) (OTCQX: OMZNF) (FRANKFURT: 0B51) is pleased to announce an updated Mineral Resource Estimate for the Gaspé Copper Project, located in the Gaspé peninsula of Eastern Quebec.
The updated MRE (Table 1) includes base-case, pit-constrained resources comprising 2,147 million tonnes averaging 0.25% Cu and 0.015% Mo (0.30% CuEq) of Measured and Indicated categories, and 971 million tonnes averaging 0.45% Cu and 0.044% Mo (0.60% CuEq) of Inferred category. This updated MRE includes 265 million tonnes averaging 0.38% Cu and 0.015% Mo (0.43% CuEq) that are pit-constrained and 706 million tonnes averaging 0.48% Cu and 0.055% Mo (0.66% CuEq) from underground resources at Porphyry Mountain. It also comprises a revision of the open pit base-case resource from the Spring 2026 MRE (see April 14, 2026 news release), justified by using a lower cut-off of 0.12% CuEq as a result of using higher long-term copper pricing (US$5.00/lb), as well as the addition of inferred underground resources from the Porphyry Mountain deposit.
The overall resource outlines one of the largest undeveloped copper-molybdenum deposits in North America: 11.6 billion pounds (5.26 million tonnes) of contained copper and 712 million pounds of contained molybdenum in the M&I category, as well as potential for an additional 9.6 billion pounds (4.37 million tonnes) of contained copper and 943 million pounds of contained molybdenum in the Inferred category.
Osisko Metals Chief Executive Officer Robert Wares commented: “This updated mineral resource estimate brings significant growth to the Gaspé Copper system through our preliminary estimate of the underground Porphyry Mountain deposit and re-evaluation of the base-case Spring 2026 open-pit MRE. Importantly, this MRE does not include results from the current 70,000 metre drill program, which we believe will significantly extend the open-pit resource to the south and southwest towards Needle Mountain. The 2026 core assaying is expected to be completed by mid-January 2027, which will be included in the next MRE update, anticipated for April 2027.”
Wares continued: “An additional 50,000 metre drill program will commence in Q2 2027, with the objective of upgrading significant Inferred Resources to the Indicated category, expanding the Deep Porphyry Exploration Program beyond the current limits of the Porphyry Mountain MRE model, and further expanding the boundaries of the Gaspé Copper system to the south, beyond Needle Mountain and Needle East.”
Table 1: MRE Base Case at CuEq = 0.12% cut-off for open pit and CuEq = 0.24% cut-off for underground. See Table 2 for broader range of sensitivities.
| Category | Cut-off | Cut-off | Tonnes | CuEq | Cu | Mo | Ag | Cu | Cu | Mo | Mo | Ag |
| CuEq %1 | NSR2 | Mt | % | % | % | g/t | M lbs | kt | M lbs | kt | Moz | |
| Measured | 0.12 | $9.36 | 144 | 0.41 | 0.36 | 0.013 | 1.92 | 1,148 | 521 | 42 | 19 | 9 |
| Indicated | 0.12 | $9.36 | 2,003 | 0.29 | 0.24 | 0.015 | 1.45 | 10,451 | 4,742 | 669 | 304 | 94 |
| M&I OP | 0.12 | $9.36 | 2,147 | 0.30 | 0.25 | 0.015 | 1.49 | 11,600 | 5,263 | 712 | 323 | 103 |
| Inferred OP | 0.12 | $9.36 | 265 | 0.43 | 0.38 | 0.015 | 1.77 | 2,222 | 1,008 | 88 | 40 | 15 |
| Inferred UG | 0.24 | 19.94 | 706 | 0.66 | 0.48 | 0.055 | 2.04 | 7,409 | 3,361 | 864 | 388 | 46 |
| Inferred total | Mixed | Mixed | 971 | 0.60 | 0.45 | 0.044 | 1.96 | 9,631 | 4,370 | 943 | 428 | 61 |
Copper equivalent grade is then calculated by substituting total NSR (Cu + Mo + Ag) for copper NSR in the regression equation, as follows: CuEq Grade (%) = (1.7643 + NSR_Cu + NSR_Mo + NSR_Ag) / 9271.9
Based on the NSR assumptions applied, this relationship simplifies to:
CuEq (%) = Cu (%) + 3.0229 × Mo (%) + 0.00008 × Ag (g/t)
The equivalent factors for molybdenum and silver are derived from the relative NSR contribution of each metal compared to copper under the assumptions described above.
General parameters of the updated pit-constrained MRE and Mineral Resource Sensitivity
This pit-constrained MRE uses a calculated lower cut-off of 0.088% CuEq for pit shell optimization and a reporting cut-off grade of 0.12% CuEq for base case in-pit resource estimation (see Table 2 below). The base case resource, emphasized to disregard lower-grade marginal material, reflects a conservative higher cut-off grade of 0.12% CuEq. The calculated lower cut-off grade of 0.088% CuEq is based on estimated production costs, NSRs and consensus long-term metal prices of US$4.50/lb copper, US$20 molybdenum and US$45/oz silver (see Table 3 for detailed parameters). The resource was estimated using data from historical drilling completed between the 1950s and 2019, and 160,000 metres of drilling completed by the Company from 2022 to 2025 and on additional 2025 metallurgical and comminution test results.
Table 2: Mineral Resource Estimates at Variable Cut-Off Grades for pit-constrained resource.
| Class | CuEq Cut-off (%) | NSR Cut-off (US$) |
Tonnage (Mt) | Strip Ratio | Grade | Copper Metal Resource | ||
| Cu (%) | Mo (%) | M lbs | kt | |||||
| M&I | 0.09 | 6.56 | 2,342 | 1.03 | 0.23 | 0.014 | 12,000 | 5,444 |
| Inferred | 0.09 | 6.58 | 287 | 0.36 | 0.014 | 2,264 | 1,027 | |
| M&I | 0.10 | 7.51 | 2,283 | 1.08 | 0.24 | 0.014 | 11,893 | 5,396 |
| Inferred | 0.10 | 7.51 | 280 | 0.36 | 0.015 | 2,252 | 1,022 | |
| M&I | 0.12 | 9.36 | 2,147 | 1.21 | 0.25 | 0.015 | 11,600 | 5,263 |
| Inferred | 0.12 | 9.36 | 265 | 0.38 | 0.015 | 2,222 | 1,008 | |
| M&I | 0.14 | 11.22 | 1,993 | 1.37 | 0.26 | 0.016 | 11,216 | 5,089 |
| Inferred | 0.14 | 11.22 | 253 | 0.39 | 0.015 | 2,194 | 995 | |
| M&I | 0.16 | 13.07 | 1,834 | 1.57 | 0.27 | 0.017 | 10,766 | 4,885 |
| Inferred | 0.16 | 13.07 | 239 | 0.41 | 0.016 | 2,158 | 979.3 | |
| M&I | 0.18 | 14.92 | 1,676 | 1.81 | 0.28 | 0.017 | 10,266 | 4,658 |
| Inferred | 0.18 | 14.92 | 224 | 0.43 | 0.016 | 2,116 | 960 | |
| M&I | 0.19 | 15.85 | 1,597 | 1.94 | 0.28 | 0.018 | 9,997 | 4,536 |
| Inferred | 0.19 | 15.85 | 217 | 0.44 | 0.016 | 2,094 | 950 | |
| M&I | 0.20 | 16.78 | 1,517 | 2.09 | 0.29 | 0.018 | 9,715 | 4,408 |
| Inferred | 0.20 | 16.78 | 208 | 0.45 | 0.016 | 2,068 | 938 | |
Same footnotes as Table 1 apply to this table.
Table 3: Whittle optimization parameters used for the pit-constrained Mineral Resource Estimate (all monetary values in US$ unless specified; based on average mill throughput of 160,000 tpd).
| Economic Parameters | ||
| US/Canada Exchange rate | 1.35 | |
| Discount rate | % | 8.0% |
| Cu Price | $/lb | $4.50 |
| Mo Price | $/lb | $20.00 |
| Ag Price | $/oz | $45.00 |
| Refining Cu ‘RC’ | $/lb | $0.08 |
| Refining Mo | $/lb | $0.00 |
| Refining Ag | $/oz | $0.00 |
| Royalty rate | % NSR | 2.40% |
| Concentrate Costs | ||
| Transport and loading costs (CAD$ 29.70) | $/wmt | $22.00 |
| Shipping cost (CAD$ 89.44) | $/wmt | $66.25 |
| Insurance and other costs (CAD$ 16.20) | $/wmt | $12.00 |
| Smelter Treatment Cost Cu ‘TC’ | $/dmt | $80.00 |
| Smelter Treatment Cost Cu ‘TC’ | $/lb | $0.34 |
| Smelter Treatment Cost Mo ‘TC’ | $/dmt | $1,690.00 |
| Smelter Treatment Cost Mo ‘TC’ | $/lb | $1.41 |
| Concentrate Feed | ||
| Concentrate Grade Cu | % | 25% |
| Concentrate Moisture Cont. | % | 8% |
| Concentrate Grade Mo | % | 58% |
| Concentrate Moisture Cont. | % | 8% |
| Payables | ||
| Payable Cu | % | 96.5% |
| Payable Mo | % | 98.0% |
| Payable Ag | % | 75.0% |
| Recovery and Dilution Factors | ||
| Avg. Cu Recovery* (variable with grade) | % | 91% |
| Avg. Mo Recovery | % | 72% |
| Avg. Ag Recovery | % | 65% |
| Mining Dilution (Whittle) | % | 0% |
| Mining Recovery (Whittle) | % | 100% |
| Mineralized Material Base Costs | ||
| Processing Cost | $/milled | $4.15 |
| % of rehandling | % | 10.00% |
| Stockpile Rehandle | $/milled | $0.16 |
| G&A | $/milled | $0.90 |
| Total | $/milled | $5.21 |
| Mining Costs | ||
| Mined rock centre of gravity cost | $/mined | $2.00 |
| Dump mining | $1.30 | |
| Incremental mining cost | $/mined/15m | $0.05 |
| NSR Calculations (before royalties) | ||
| NSR Cu | $/t | $21.42 |
| NSR Mo | $/t | $4.88 |
| NSR Ag | $/t | $1.14 |
| Total NSR | $/t | $27.44 |
| Copper Cut-Off grades | ||
| Mineralized material base cost | $/t | $5.21 |
| Mining cost | $/mined | $2.00 |
| Transport and Smelt cost | $/t | $1.87 |
| Royalties cost | $/t | $0.66 |
| Total cost | $/t | $9.74 |
| Cu Break-Even Cut-Off Grade | % Cu | 0.111% |
| Mill Cut-Off value | $/t | $7.74 |
| Cu Mill Cut-Off Grade | % Cu | 0.088% |
| Geotechnical Parameters | ||
| IRA slope in rock | degrees | 48 |
| Net Payability | ||
| Net payability Cu | % | 87.1% |
| Net payability Mo | % | 91.0% |
| Net payability Ag | % | 75.0% |
*The mill cut-off decreases to approximately $5.95/t at lower grades (e.g., 0.09% Cu and 0.008% Mo), as lower recoveries and payable metal reduce the effective transport and smelting costs per tonne, resulting in a lower cut-off value. Results presented above are with average grades of 0.27% Cu and 0.017% Mo.
General parameters of the underground inferred resources at Porphyry Mountain
The underground resource estimate (Porphyry Mountain) is based on the same coherent 3D geological model used for the Copper Mountain open-pit resources. Two additional stockwork mineralized zones were modeled that host underground mineralization: one in a vertically-oriented porphyry intrusion and a second in the surrounding gently-dipping porcellanite/skarn metasedimentary units.
This delineated underground portion of the mineral resource estimate uses a lower cut-off grade of 0.24% CuEq (equivalent to US$19.94 NSR) for the optimization of block-caving underground mining and a reporting cut-off grade of 0.00% CuEq within the bulk mining zone, as is appropriate for a block-caving mining approach (see Table 4 for detailed parameters). The lower cut-off grade of 0.24% CuEq is based on estimated production costs, undercut level development costs, NSRs, and long-term consensus metal prices of US$5.00/lb for copper, US$20/lb for molybdenum, and US$45/oz for silver. The underground resource was estimated using data from historical drilling conducted between 1994 and 2019 and partial re-assaying of available core.
Table 4: Optimization parameters used for the Porphyry Mountain underground MRE (all monetary values in US$; based on average site mill throughput of 160,000 tpd).
| Economic Parameters | ||
| US/Canada Exchange rate | 1.35 | |
| Discount rate | % | 8.0% |
| Cu Price | $/lb | $5.00 |
| Mo Price | $/lb | $20.00 |
| Ag Price | $/oz | $45.00 |
| Refining Cu ‘RC’ | $/lb | $0.08 |
| Refining Mo | $/lb | $0.00 |
| Refining Ag | $/oz | $0.00 |
| Royalty rate | % NSR | 5.00% |
| Concentrate Costs | ||
| Transport and loading costs (CAD$ 29.70) | $/wmt | $22.00 |
| Shipping cost (CAD$ 89.44) | $/wmt | $66.25 |
| Insurance and other costs (CAD$ 16.20) | $/wmt | $12.00 |
| Smelter Treatment Cost Cu ‘TC’ | $/dmt | $80.00 |
| Smelter Treatment Cost Cu ‘TC’ | $/lb | $0.34 |
| Smelter Treatment Cost Mo ‘TC’ | $/dmt | $1,690.00 |
| Smelter Treatment Cost Mo ‘TC’ | $/lb | $1.41 |
| Concentrate Feed | ||
| Concentrate Grade Cu | % | 25% |
| Concentrate Moisture Cont. | % | 8% |
| Concentrate Grade Mo | % | 58% |
| Concentrate Moisture Cont. | % | 8% |
| Payables | ||
| Payable Cu | % | 96.5% |
| Payable Mo | % | 98.0% |
| Payable Ag | % | 75.0% |
| Recovery and Dilution Factors | ||
| Avg. Cu Recovery* (variable with grade) | % | 91% |
| Avg. Mo Recovery | % | 72% |
| Avg. Ag Recovery | % | 65% |
| Mineralized Material Base Costs | ||
| Processing Cost | $/milled | $4.15 |
| G&A | $/milled | $0.90 |
| Total | $/milled | $5.05 |
| Mining Costs | ||
| Underground mining costs | $/mined | $8.52 |
| Design Parameters | ||
| Draw Column Width | m | 25 |
| Maximum Draw Column Height | m | 400 |
| NSR Calculations (before royalties) | ||
| NSR Cu | $/t | $43.08 |
| NSR Mo | $/t | $15.79 |
| NSR Ag | $/t | $1.44 |
| Total NSR | $/t | $60.31 |
| Copper Cut-Off grades | ||
| Mineralized material base cost | $/t | $5.05 |
| Mining cost | $/mined | $8.52 |
| Transport and Smelt cost | $/t | $3.35 |
| Royalties cost | $/t | $3.02 |
| Total cost | $/t | $19.94 |
| Cu Break-Even Cut-Off Grade | % Cu | 0.238% |
| Net Payability | ||
| Net payability Cu | % | 88.0% |
| Net payability Mo | % | 91.0% |
| Net payability Ag | % | 75.0% |
*Results presented above are with average grades of 0.48% Cu and 0.055% Mo.
Other parameters used for the Mineral Resource Estimate include:
Cautionary Statement Regarding Mineral Resources
The mineral resources disclosed in this news release conform to standards and guidelines in National Instrument 43-101 – Standards of Disclosure for Mineral Projects and were prepared by independent qualified persons for purposes of NI 43-101. The above-mentioned mineral resources are not mineral reserves as they do not have demonstrated economic viability. The quantity and grade of the reported Inferred Mineral Resources are conceptual in nature and are estimated based on limited geological evidence and sampling. Geological data is sufficient to imply but not verify geological grade and/or quality of continuity. An Inferred Mineral Resource has a lower level of confidence relative to a Measured or Indicated Mineral Resource and constitutes an insufficient level of confidence to allow conversion to a Mineral Reserve. It is reasonably expected, but not guaranteed, that the majority of Inferred Mineral Resources could be upgraded to Measured or Indicated Mineral Resources with additional drilling. The technical report prepared in accordance with NI 43-101, including the mineral resources for the Gaspé Copper Project contained in this news release, will be delivered and filed on SEDAR+ (www.sedarplus.ca) under Osisko Metals’ issuer profile within 45 days of the date of this news release.
Qualified Person
The Mineral Resource Estimate and other scientific and technical information in this news release has been prepared and approved by independent qualified persons for purposes of NI 43-101: Pierre-Luc Richard, P.Geo., of PLR Resources Inc. with contributions from Patrick Frenette, P.Eng., of Synectiq for cut-off grade estimates, pit shell optimization and underground block-caving parameters, and Christian Laroche, P.Eng., from Synectiq, for metallurgical parameters.
Quality Assurance / Quality Control
Osisko Metals adheres to a strict QA/QC program for core handling, sampling, sample transportation and analyses, including insertion of blanks and standards in the sample stream. Drill core is drilled in HQ or NQ diameter and securely transported to its core processing facility on site, where it is logged, cut and sampled. Samples selected for assay are sealed and shipped to ALS Canada Ltd.’s preparation facility in Sudbury. Sample preparation details (code PREP-31DH) are available on the ALS Canada website. Pulps are analyzed at the ALS Canada Ltd. facility in North Vancouver, BC. Allsamples are analyzed by four acid digestion followed by both ICP-AES and ICP-MS for Cu, Mo and Ag.
About Osisko Metals
Osisko Metals Incorporated is a Canadian exploration and development company creating value in the critical metals sector, with a focus on copper and zinc. The Company acquired a 100% interest in the past-producing Gaspé Copper mine from Glencore Canada Corporation in July 2023. The Gaspé Copper mine site is located near Murdochville in Québec’s Gaspé Peninsula. The Company is currently focused on resource expansion of the Gaspé Copper system, with current Measured and Indicated Mineral Resources of 2.15 Bt averaging 0.30% CuEq and Inferred Mineral Resources of 971 Mt averaging 0.60% CuEq (in compliance with NI 43-101). For more information, see this news release. Gaspé Copper hosts the largest undeveloped copper resource in eastern North America, strategically located near existing infrastructure in the mining-friendly province of Québec.
In addition to the Gaspé Copper project, the Company is working with Appian Capital Advisory LLP through the Pine Point Mining Limited joint venture to advance one of Canada’s largest past-producing zinc mining camps, the Pine Point project, located in the Northwest Territories. The current mineral resource estimate for the Pine Point project consists of Indicated Mineral Resources of 49.5 Mt averaging 5.52% ZnEq and Inferred Mineral Resources of 8.3 Mt averaging 5.64% ZnEq (in compliance with NI 43-101). For more information, see Osisko Metals’ June 25, 2024 news release entitled “Osisko Metals releases Pine Point mineral resource estimate: 49.5 million tonnes of indicated resources at 5.52% ZnEq”. The Pine Point project is located on the south shore of Great Slave Lake, NWT, close to infrastructure, with paved road access, an electrical substation and 100 kilometres of viable haul roads.
For further information on this news release, visit www.osiskometals.com or contact:
Don Njegovan, President
Email: info@osiskometals.com
Phone: (416) 500-4129
Forte Minerals Corp. (CSE: CUAU) (OTCQX: FOMNF) (Frankfurt: 2OA) is pleased to announce that it has ... READ MORE
Dakota Gold Corp. (NYSE American: DC) is pleased to report the results of its S-K 1300 Pre-Feasibili... READ MORE
Fury Gold Mines Limited (TSX: FURY) (NYSE American: FURY) is pleased to announce results from five ... READ MORE
CanAlaska Uranium Ltd. (TSX-V: CVV) (OTCQX: CVVUF) (FSE: DH7) is pleased to report that it has comp... READ MORE
Onyx Gold Corp. (TSX-V: ONYX) (OTCQX: ONXGF) is pleased to report assay results from 36 drill holes ... READ MORE