The Prospector News

McEwen Mining: Q3 Production

You have opened a direct link to the current edition PDF

Open PDF Close
Uncategorized

Share this news article

McEwen Mining: Q3 Production

 

 

 

 

 

McEwen Mining Inc. (NYSE: MUX) (TSX: MUX) is pleased to report production for Q3 2023 was 38,600 gold equivalent ounces and 104,800 GEOs for the nine months ended September 30th, 2023. Our consolidated production guidance for 2023 is maintained, despite the Gold Bar Mine’s production forecast being 13% below its guidance range. Our forecast for the full year 2023 (see Table 1) reflects actual productions to September 30th and management’s current estimates for Q4 2023

 

Table 1: Consolidated Production Summary

 

Q3 9M Full Year 2023 Forecast 2023
Guidance
2022 2023 2022 2023
Consolidated Production
Gold (oz) 26,200 31,500 74,650 86,100 124,300(3) 123,000-139,000
Silver (oz) 853,000 580,200 1,894,100 1,531,200 2,300,000 2.3M-2.6M
GEOs(1) 35,700 38,600 97,000 104,800 152,300 150,000-170,000
Gold Bar Mine, Nevada
GEOs 7,200 9,500 18,600 23,900 36,500 42,000-48,000
Fox Complex, Canada
GEOs 9,000 11,200 27,900 34,200 45,500 42,000-48,000
San José Mine, Argentina (49%)(2)
Gold Production 9,900 10,800 27,400 28,000 40,000 39,000-43,000
Silver Production 852,200 580,200 1,892,400 1,531,200 2,300,000 2.3M-2.6M
GEOs 19,300 17,900 49,700 46,700 68,000 66,000-74,000

 

Notes:

(1)   ‘Gold Equivalent Ounces’ are calculated based on a gold-to-silver price ratio of 90:1 for Q3 2022, 82:1 for Q1 2023, 82:1 for Q2, 2023, and 81:1 for Q3 2023. 2023 production guidance is calculated based on an 85:1 gold-to-silver price ratio.
(2)   The San José Mine is 49% owned by McEwen Mining Inc. and 51% owned and operated by Hochschild Mining plc. Production is shown on a 49% basis.
(3)   El Gallo Mine (on care and maintenance) is expected to recover 2,300 gold oz in 2023 from plant and pond cleanout.

Gold Bar Mine, Nevada

Good progress has been made at Gold Bar recovering from a challenging first half of the year, as demonstrated by steadily increasing production quarter after quarter. Gold Bar has also maintained an excellent safety record with 1,313 days without a lost time injury as of September 30th. Crushing and stacking of ore on the heap leach pad reached a rate of 9,300 tonnes per day (tpd) in September, a major improvement over the average in the prior eight months of 6,150 tpd. Year-to-date, ore containing 41,600 ounces of gold has been loaded onto the heap leach pad with an average expected recovery rate of 68%. Due to the gold inventory on the heap leach pad, we are confident in a reasonably strong Q4 continuing into the start of 2024. The 2023 production forecast is 13% below the guidance established in December 2022, due to a combination of factors including flooding and extreme weather in the Spring and a slower leach recovery rate of Gold Bar South ore.

 

Fox Complex, Timmins District

Fox performed well during Q3 and it is on track to slightly exceed the mid-point of our guidance range. Fox has achieved 738 days without a lost time injury as of September 30th. Mining at Froome is on track and the Stock mill continues to increase average throughput. We are pleased with the good exploration drilling results seen at our Stock Complex including the ‘Ramp Portal Zone’, which may represent an early mining horizon for our upcoming Stock West project (see news release dated October 3rd, 2023).

 

San José, Argentina

San José, which is operated by our joint venture partner Hochschild Mining, delivered Q3 production in line with our expectations for the quarter and guidance for the year. San José reported one lost time injury in August 2023, the worker has since recovered and returned to regular duty.

 

McEwen Copper

On October 11th our McEwen Copper subsidiary announced additional investments by Stellantis and Nuton of ARS$42 billion and US$10 million, respectively. Since the creation of McEwen Copper, shareholders have invested $397 million (including investments by Stellantis in Argentine Pesos at official exchange rates at the time of each transaction) to acquire shares even though that the Company has remained private. The recent transactions occurred at $26.00 per share of McEwen Copper, giving it a market value of approximately $800 million. McEwen Mining retains 47.7% ownership of McEwen Copper, with an implied market value of $380 million, this represents a value accretion for McEwen Mining shareholders of $98 million or two (2) dollars per share since March 2023.

 

McEwen Copper is now well financed for the remainder of 2023 and well into 2024. The funds raised will be used to advance the feasibility study on the Los Azules project and for other corporate purposes. McEwen Mining also received proceeds of $6 million to augment its balance sheet.

 

Currently, we have fourteen drill rigs on site at Los Azules, scaling up to 18 drill rigs for our drilling campaign targeting more than 45,000 meters. This program will generate all the remaining data required to complete the planned feasibility study by Q1 2025.

 

Technical Information

The technical content of this news release related to financial results, mining and development projects has been reviewed and approved by William (Bill) Shaver, P.Eng., COO of McEwen Mining and a Qualified Person as defined by SEC S-K 1300 and the Canadian Securities Administrators National Instrument 43-101 “Standards of Disclosure for Mineral Projects.”

 

Reliability of Information Regarding San José

Minera Santa Cruz S.A., the owner of the San José Mine, is responsible for and has supplied to the Company all reported results from the San José Mine. McEwen Mining’s joint venture partner, a subsidiary of Hochschild Mining plc, and its affiliates other than MSC do not accept responsibility for the use of project data or the adequacy or accuracy of this release.

 

 

ABOUT MCEWEN MINING

 

McEwen Mining is a gold and silver producer with operations in Nevada, Canada, Mexico and Argentina. In addition, it owns approximately 47.7% of McEwen Copper which owns the large, advanced stage Los Azules copper project in Argentina. The Company’s goal is to improve the productivity and life of its assets with the objective of increasing its share price and providing a yield. Its Chairman and Chief Owner has personally provided the company with $220 million and takes an annual salary of $1.

 

Posted October 30, 2023

Share this news article

MORE or "UNCATEGORIZED"


New Found Intersects 455 G/T Au Over 4.1m, 148 G/T Au Over 7.0m And 58.6 G/T Au Over 11.6m At Keats With Phase II Trench Channel Samples

  New Found Gold Corp. (TSX-V: NFG) (NYSE-A: NFGC) is pleased to announce the results of the seco... READ MORE

December 2, 2024

TRX Gold Reports Year-End 2024 Results

  TRX Gold Corporation (TSX: TRX) (NYSE American: TRX) today reported its results for the year end ... READ MORE

December 2, 2024

Arizona Metals Intersects 20.1 m @ 3.6 g/t AuEq in Kay2 Zone at Kay Deposit

Arizona Metals Corp. (TSX: AMC) (OTCQX: AZMCF) is pleased to announce new drill results from the Ka... READ MORE

December 2, 2024

American Pacific Closes Transaction to Gain USD$10M and 100% Interest in the Palmer VMS Project in Alaska

American Pacific Mining Corp. (CSE: USGD) (OTCQX: USGDF) (FWB: 1QC) announced today that it has clos... READ MORE

December 2, 2024

Aya Gold & Silver Announces First Silver Pour at Expanded Zgounder Mine

Aya Gold & Silver Inc. (TSX: AYA) (OTCQX: AYASF) is pleased to announce the first silver pour f... READ MORE

December 2, 2024

Copyright 2024 The Prospector News