Marathon Gold Corporation (TSX: MOZ) announces its financial results for the first quarter ending March 31, 2022 and provides an update on the Company’s activities at the Valentine Gold Project in the central region of Newfoundland and Labrador.

 

First Quarter Highlights

  • At March 31, 2022 the Company had cash and cash equivalents of $72.4 million, leaving it well positioned to execute on its permitting, development, and exploration activities at the Project;
  • On March 31, 2022, the Company closed a US$185 million term loan credit facility with Sprott Private Resource Lending II (Collector-2) LP for the construction, development and working capital requirements of the Project;
  • On March 17, 2022, the Company was notified that the Newfoundland and Labrador Minister of Environment and Climate Change had completed its review of the Project’s Environmental Impact Statement and concurrently, that the Project had received approval by the Cabinet of the Government of NL. Marking completion of the provincial Environmental Assessment process;
  • On March 16, 2022, the Company was notified that the Impact Assessment Agency of Canada had completed its technical review of the Project’s EIS. The Federal EA is approaching a ministerial decision and site-specific permitting has commenced;
  • Purchased for cancellation a historical 7.5% net profit interest royalty that covers certain mineral resource areas at the Project;
  • Incurred capital expenditures of $13.4 million in the period, primarily related to pre-construction capital spending, including detailed engineering and consulting fees, milestone payments related to the procurement of a permanent camp, access road upgrades and initial deposits on drilling and mobile equipment;
  • Completed 12,530 metres of exploration drilling in 62 holes from a total full-year 50,000 metre exploration drilling program. 9,810 metres were drilled in the Berry Deposit and 2,720 metres in the Victory Deposit; and
  • Strengthened the Company’s management team with the appointment of Ms. Julie Robertson as Chief Financial Officer of the Company, bringing extensive experience in capital projects financial management, planning, and control.

 

Matt Manson, President, and CEO commented: “The first quarter of 2022 ended with important achievements for Marathon in the permitting and financing of the Valentine Gold Project. Over two days in mid-March we were very pleased to report the emphatic approval in of the Project at the Newfoundland and Labrador cabinet, marking the completion of our provincial EA process, and the completion of the technical and public review phase under our federal EA process. This has allowed us to guide to the commencement of early works in the third quarter and, subject to a formal board construction decision, full construction mobilization by year-end. Then, at the end of March, we announced the closing of our previously announced US$185 million term loan with Sprott Resource Lending, which will comprise the debt portion of our project financing.” Mr. Manson continued: “Alongside our project permitting and financing achievements, and the ongoing engineering and procurement work in support of our project-build, we will be updating the Project’s Mineral Resource estimate by mid-year, which will incorporate 100,000 metres of drilling at the Berry Deposit and the results of our 2021 Reverse Circulation drill program. This new estimate is expected to be both larger, with an expected increase in open-pit Measured and Indicated Resources, and more robust. We will then demonstrate the impact of this new estimate in an updated technical report, scheduled for the fourth quarter, which will reflect a new, longer-term vision for the Project’s mine plan, the current cost environment, a higher gold price environment, and our settled development schedule. Taken together, this work will present a major new gold mining project that is well conceived, well engineered, well financed, and fully permitted, with clear cost and schedule-to-complete objectives, and a mineral resource that is both tested and still growing. Our treasury at quarter-end was strong, at $72.4 million, and we continue to enjoy all the advantages of building a mining team and business located in the central region of Newfoundland and Labrador.”

 

Financial Performance

 

The results of operations for the first quarter 2022 are summarized below (all figures are in Canadian dollars unless otherwise noted):

(Stated in thousands of Canadian dollars)     For the Three Months Ended
March 31,
      2022   2021
EXPENSES                  
General and administrative expense     $ 2,325     $ 1,709  
Finance income, net       (100 )     (26 )
Other income       (42 )     (36 )
Loss before tax       2,183       1,647  
Deferred income tax expense       1,622       995  
Net Loss     $ 3,805     $ 2,642  
                   
Capital expenditures     $ 13,352     $ 5,595  

 

Factors affecting financial results for the three months ended March 31, 2022:

  • General and administrative expenses increased from $1.71 million to $2.33 million due to an increase in Project Financing advisory & professional fees and Share-based compensation expense, partially offset by a decrease in Salaries and wages expense, as pre-construction costs are being capitalize.
  • Deferred income tax (recovery)/expense increased from $1.00 million to $1.62 million, as the increase in the deferred tax liability of $3.90 million in the first quarter of 2022 was higher than the $1.10 million increase in the deferred tax liability in the comparable period in 2021. This was partially offset by a higher decrease in the flow-through share tax liability in the first quarter of 2022 of $2.28 million, compared to $0.10 million in the comparable period in 2021.
  • Capital expenditures excluding working capital movements, were $7.76 million higher in the first quarter of 2022 than the prior year primarily because of project pre-construction capital spending, which commenced in the third quarter of 2021 and continued into the first quarter of 2022. Pre-construction capital spending in the first quarter of 2022 included detailed engineering and consulting fees, milestone payments related to the procurement of a permanent camp, road maintenance and initial deposits on drilling equipment.

 

2022 Exploration Drilling Program

 

Marathon’s 2022 exploration drilling program commenced in January 2022 with a full-year plan of 50,000 metres of diamond drilling at a total budget of $12.0 million. The components of the 2022 exploration drilling program are as follows:

  • 38,000 – 40,000 metres of drilling in the Berry Deposit, designed to increase drill density over the 1.5 kilometres of mineralization previously delineated and for further resource expansion; and
  • 10,000 – 12,000 metres of drilling at the Victory Deposit, with a view to potential resource expansion.

 

The 2022 program will also include a significant prospecting program along the approximately 13 kilometres of geological contact at the Valentine Lake Shear Zone between the Victory Deposit and the eastern boundary of the property. The above noted drilling and prospecting programs will also be supported by additional structural geological and geophysical surveys, which will be utilized to better understand the setting of the five currently known Project mineral deposits.

 

At March 31, 2022, the Company had completed 12,530 metres of its total full-year plan of 50,000 metres. A total of 9,810 metres were drilled in the Berry Deposit and 2,720 metres in the Victory Deposit. All assay results from the 2022 exploration drill program remain outstanding. As of April 21, 2022 the Company had released results from a total of approximately 100,000 metres of drilling at the Berry Deposit and a total of approximately 19,000 metres of drilling at the Victory Deposit (see Marathon news release dated April 21, 2022). Results from the Berry Deposit continued to show multiple long intercepts of high-grade mineralization, and the recent drilling at the Victory Deposit has demonstrated its potential to host additional large-scale mineralization.

 

2022 Development Activity

 

Marathon’s project development activities for the remainder of 2022 will primarily be focused in the following key areas:

  • Completion of the 2022 Valentine Gold Project exploration program;
  • Release from the federal EA process;
  • Completion of ongoing detailed engineering, procurement and site-specific permitting;
  • Commencement of site early works, scheduled for the third quarter, supporting full site mobilization by the end of the year;
  • Completion of an update to the Project’s Mineral Resource estimate, inclusive of updates to the Marathon, Leprechaun, Berry and Victory Deposits;
  • Completion of a new NI 43-101 technical report for the Project, which will constitute an updated Feasibility Study;
  • Completion of a 24,000 metre RC drill program at the Leprechaun and Marathon Deposits, aimed at establishing a grade control dataset ahead of the commencement of pre-stripping activities;
  • Ongoing stakeholder engagement and consultation activity;
  • Continued capacity building and development of the project execution team; and
  • Ongoing support for project financing activities.

 

Qualified Persons

 

Disclosure of a scientific or technical nature in this news release has been approved by Mr. Tim Williams, FAusIMM, Chief Operating Officer of Marathon, Mr. Paolo Toscano, P.Eng. (Ont.), Vice President, Projects for Marathon, and Mr. James Powell, P.Eng. (NL), Vice President, Regulatory and Government Affairs for Marathon, and Mr. David Ross, P.Geo. (Ont), Director of Mineral Resources for Marathon Gold Corporation. Nicholas Capps, P.Geo. (NL), Exploration Manager of Marathon, is responsible for the design and operation of exploration programs at the Valentine Gold Project. Exploration data quality assurance and control for Marathon is under the supervision of Jessica Borysenko, P.Geo (NL), GIS Manager for Marathon. Mr. Williams, Mr. Toscano, Mr. Powell, Mr. Ross, Mr. Capps and Ms. Borysenko are Qualified Persons in accordance with National Instrument 43-101 – Standards of Disclosure for Mineral Projects (“NI 43-101”) and have approved the technical content of this news release. Marathon’s mineral resources and mineral reserves have been estimated in accordance with the standards of the Canadian Institute of Mining, Metallurgy and Petroleum (“CIM”) and in accordance with the requirements of NI 43-101. Mineral resources which are not mineral reserves do not have demonstrated economic viability. Mineral resources are reported inclusive of mineral reserves. Information on data verification performed on, and other scientific and technical information relating to, the Valentine Gold Project are contained in Marathon’s Annual Information Form (“AIF”) for the year ended December 31, 2021 and the current technical report for the Valentine Gold Project prepared in accordance with NI 43-101 titled “NI 43-101 Technical Report & Feasibility Study on the Valentine Gold Project, Newfoundland and Labrador, Canada” prepared by Ausenco Engineering Canada Inc. with an effective date of April 15, 2021 (the “2021 Valentine Technical Report”). The AIF and the 2021 Valentine Technical Report are available at www.sedar.com.

 

About Marathon

 

Marathon is a Toronto based gold company advancing its 100%-owned Valentine Gold Project located in the central region of Newfoundland and Labrador, one of the top mining jurisdictions in the world. The Project comprises a series of five mineralized deposits along a 20-kilometre system. An April 2021 Feasibility Study outlined an open pit mining and conventional milling operation over a thirteen-year mine life with a 31.5% after-tax rate of return. The Project has estimated Proven Mineral Reserves of 1.40 Moz (29.68 Mt at 1.46 g/t) and Probable Mineral Reserves of 0.65 Moz (17.38 Mt at 1.17 g/t). Total Measured Mineral Resources (inclusive of the Mineral Reserves) comprise 1.92 Moz (32.59 Mt at 1.83 g/t) with Indicated Mineral Resources (inclusive of the Mineral Reserves) of 1.22 Moz (24.07 Mt at 1.57 g/t). Additional Inferred Mineral Resources are 1.64 Moz (29.59 Mt at 1.72 g/t Au). Please see Marathon’s Annual Information Form for the year ended December 31, 2021 and other filings made with Canadian securities regulatory authorities and available at www.sedar.com for further details and assumptions relating to the Valentine Gold Project.

 

Posted May 13, 2022

Share this news article

MORE or "UNCATEGORIZED"


Silver Mountain Announces Closing of Prospectus Offering

Silver Mountain Resources Inc. (TSX-V: AGMR) (OTCQB: AGMRF) is ... READ MORE

April 24, 2024

Mandalay Extends the Storheden Gold Deposit Adjacent to the Operating Björkdal Mine

Mandalay Resources Corporation (TSX: MND) (OTCQB: MNDJF) announce... READ MORE

April 24, 2024

Collective Mining Intercepts 632.25 Metres at 1.10 g/t Gold Equivalent in a 200 Metre Step-Out Hole to the South at Trap

Collective Mining Ltd. (TSX: CNL) (OTCQX: CNLMF) (FSE: GG1) is pl... READ MORE

April 24, 2024

Koryx Copper Intersects 207 Meters at 0.49% and 116 Meters at 0.54% Copper Equivalent

Significant copper and molybdenum intersections include: HM19: 11... READ MORE

April 24, 2024

Red Pine Intercepts Significant Mineralization at the Wawa Gold Project, including 5.34 g/t over 13.39 metres including 16.50 g/t gold over 0.97 metre and 13.62 g/t gold over 2.13 metres

Red Pine Exploration Inc. (TSX-V: RPX) (OTCQB: RDEXF) is pleased ... READ MORE

April 24, 2024

Copyright 2024 The Prospector News