Inventus Mining Corp. (TSX-V: IVS) is pleased to report positive metallurgical heap leach test results completed on material from the Company’s 100%-owned Pardo “River of Gold” Project, located 65 km northeast of Sudbury, Ontario.
The program evaluated gold recovery across multiple crush sizes and leach durations and provides a technical basis for detailed testing and potential integration as a future processing strategy.
HIGHLIGHTS
Wesley Whymark, CEO & Director, comments: “These results are very encouraging, demonstrating that Pardo mineralization is responsive to cyanide leaching and, importantly, that recovery is front-loaded. At a -1/4 inch crush, 72% of the gold was recovered in 48 days. This gives us a clear starting point to optimize cycle time, crush size and reagent consumption.
The most compelling opportunity is how leaching could fit into a broader and flexible processing strategy at Pardo. We are evaluating ore sorting to produce a smaller-volume, higher-grade product for transport to an existing mill. The lower-grade fraction could potentially remain on site for lower-cost heap leaching rather than being hauled and conventionally milled. Our next step is to directly test different lower-grade mineralization and sorter products and use those results to guide future economic studies.”
HEAP LEACH TEST RESULTS
Process Mineralogical Consulting Ltd. a mineral processing and metallurgical testing laboratory, tested a 310 kg composite of Trench 1 bulk sample material. Three columns containing approximately 59 to 65 kg of material were prepared at crush sizes of -1/4 inch, -3/8 inch and -1/2 inch. The columns were leached for 78 days using a 0.5 g/L sodium cyanide solution applied at a standard laboratory flow rate. The calculated head grades ranged from 1.51 to 2.69 g/t gold with results presented in Table 1 below.
Table 1. Column Leach Recovery Results
| Test | Crush Size | Calculated Head (g/t Au) | Gold Recovery 27 Days | Gold Recovery 48 Days | Gold Recovery 78 Days |
| Column A | -1/4 inch | 2.694 | 64.3% | 72.0% | 74.5% |
| Column B | -3/8 inch | 1.514 | 53.1% | 60.0% | 66.9% |
| Column C | -1/2 inch | 1.910 | 61.1% | 65.1% | 69.5% |
The -1/4 inch column demonstrated the clearest indication of a potential optimized heap leach cycle. Recovery increased to 64.3% by day 27 and 72.0% by day 48, then increased more gradually to 74.5% by day 78. Based on the current laboratory data, a 27 to 48 day cycle is an initial target for optimization.
Results showed that 86% to 92% of the unrecovered gold in the column residues was contained in the coarse fraction, indicating that gold liberation and solution access are important controls. PMC concluded that heap leaching may not be the preferred route for the tested higher-grade composite where maximum recovery is the objective. PMC also noted that the performance of this higher-grade composite cannot be used to predict the response of a lower-grade feed, which must be tested directly.
POTENTIAL INTEGRATED PROCESSING CONCEPT
Inventus believes the results support evaluating a flexible two-product processing approach rather than applying a single recovery method to all material. Under the concept being evaluated, crushed material would be ore sorted to produce a smaller-volume, higher-grade product for transport to an existing mill. A lower-grade fraction could be retained at site and processed by heap leaching if direct testwork demonstrates acceptable recovery, permeability and reagent consumption.
The concept could reduce the tonnes transported and conventionally milled while preserving the potential value of lower-grade material. This conceptual flowsheet has not yet been supported by an economic study and remains subject to metallurgical testing, engineering, permitting and economic analysis.
NEXT STEPS
About Inventus Mining Corp.
Inventus is a mineral exploration and development company focused on the world-class mining district of Sudbury, Ontario. We have a 100% interest in our principal assets, the Pardo Paleoplacer Gold Project and the Sudbury 2.0 Critical Mineral Project, located northeast of Sudbury. The Pardo Gold Project is the first important paleoplacer gold discovery in North America. Inventus has approximately 221 million common shares outstanding.
Qualified Person
The Qualified Person responsible for the technical content of this news release is Wesley Whymark, P.Geo., CEO and Director of Inventus, who has reviewed and approved this release. Mr. Whymark is not independent of the Company.
Appia Rare Earths & Uranium Corp. (CSE: API) (OTCQB: APAAF) ... READ MORE
Sorrento Resources Ltd. (CSE: SRS) (OTCQB: SRSLF), a Canadian exp... READ MORE
Study confirms Adanac as a large-scale, long-life primary molybde... READ MORE
Oroco Resource Corp. (TSX-V: OCO) (OTCQB: ORRCF) is pleased to re... READ MORE
High-Grade Mineralization Extended Downdip at the South Zone and ... READ MORE