The Prospector News

i-80 Gold Announces Positive Preliminary Economic Assessment on the Mineral Point Open Pit Project, Nevada; After-Tax NPV(5%) of $614 Million with an After-Tax IRR of 12% at US$2,175/oz Au

You have opened a direct link to the current edition PDF

Open PDF Close
Uncategorized

Share this news article

i-80 Gold Announces Positive Preliminary Economic Assessment on the Mineral Point Open Pit Project, Nevada; After-Tax NPV(5%) of $614 Million with an After-Tax IRR of 12% at US$2,175/oz Au

i-80 GOLD CORP. (TSX:IAU) (NYSE:IAUX) is pleased to announce the results of the preliminary economic assessment for the Mineral Point Project. Mineral Point is situated within the Company’s broader Ruby Hill Complex. The Complex is located along the southeastern end of the Battle Mountain-Eureka Trend in northern Nevada, United States. The PEA demonstrates that Mineral Point has the potential to become the flagship asset within the Company’s gold portfolio.

“We are pleased to release PEA results for our Mineral Point project as it marks another key step in our plan to establish i-80 Gold as a mid-tier gold producer with a robust pipeline of growth. A key driver of future growth, Mineral Point is the largest of our two planned oxide projects complementing our three high-grade underground mines in northern Nevada. With significant production scale, a long mine life, and low costs, Mineral Point is expected to be the flagship project within our portfolio,” stated Richard Young, Chief Executive Officer.

 

Mineral Point PEA Highlights

Mineral Estimates, Production and Mine Life

  • Large open pit heap leach gold mine with a life of mine of approximately 17 years.
  • Annual gold equivalent production(1) of approximately 280,000 ounces following ramp up.
  • Estimated LOM cash costs(2) of $1,270 per ounce and all-in-sustaining costs(2) of $1,400 per ounce.
  • Updated mineral resource estimate resulting in an indicated gold mineral resource of 3.4 million ounces at 0.48 grams per tonne and an indicated silver resource of 104.3 million ounces at 15.0 g/t.
  • Updated mineral resource estimate resulting in an inferred gold mineral resource of 2.1 million ounces at 0.34 g/t and an inferred silver resource of 91.5 million ounces at 14.6 g/t.

 

Project Economics

  • Based on a $2,175/oz gold price, the Project’s undiscounted after-tax cash flows(3)(4) total $1,470 million with an after-tax net present value(3)(4) of $614 million, assuming a 5% discount rate, generating an 12% internal rate of return.
  • Based on spot gold and silver prices of $2,900/oz and $32.75/oz respectively, the Project’s undiscounted after-tax cash flows(2)(3)total $3,665 million with an after-tax NPV(3)(4) of $2,092 million, assuming a 5% discount rate, generating an IRR of 27%.
  • Mine construction capital, including all pre-production facilities and equipment is estimated at $708 million. This includes $299 million in mobile equipment for the initial fleet. In addition, approximately 104 million tonnes of stripping is required in the first year of production to gain access to the body of mineralized material costing $287 million.
  • LOM sustaining capital is estimated at $388 million, primarily for a leach pad expansion and mobile equipment maintenance and replacements.
  • Total capital includes a contingency of 15%, or $63 million applied to LOM mobile equipment of $420 million. A 25% contingency of $122 million has also been applied to all other capital including earth works, infrastructure and heap leach expansion costs.
  • Project funding is expected to include a combination of cash flow from the Company’s existing operations and a corporate debt facility.

 

Mining and Processing

  • The primary mining method will be a conventional open pit truck (24 trucks) and shovel (4 shovels) operation, moving approximately 100 million tonnes per year during a steady state of production.
  • The LOM strip ratio is 2.9:1, excluding capitalized pre-stripping.
  • Material mined will be crushed, stacked and processed at the heap leach facility located on site at a rate of approximately 23 million tonnes per year during steady state.
  • All mineralized material will be placed on leach pads following two-stage crushing. Processing also includes a Merrill Crowecircuit for the recovery of silver.
  • Ultimate block recovery determined by mineral and rock alteration type.
  • Overall average gold grade processed of 0.39 g/t with an expected average gold recovery of 78% and an average silver grade processed of 15.37 g/t with an expected average silver recovery of 41%.

All amounts are in United States dollars, unless otherwise stated.

A summary of key valuation, cost, and operating metrics is presented in Table 1 below. For more detailed metrics presented on an annual basis, see Mineral Point Project Detailed Cash Flow Model in the Appendix.

Table 1: Summary of PEA Key Operating and Financial Metrics

Project Economics Unit
Gold Price $/oz $2,175
Silver Price $/oz $27.25
Pre-Tax NPV(5%)(3) $M $828
After-Tax NPV(5%)(3)(4) $M $614
After-Tax IRR(4) % 12 %
After-Tax Cash Flow(4) $M $1,470
Production Profile
Mine Life years 16.5
Mineralized Material Mined 000s
tonnes
358,741
Gold Grade of Mineralized Material Mined g/t Au 0.39
Silver Grade of Mineralized Material Mined g/t Ag 15.37
Waste Tonnes Mined 000s
tonnes
1,032,779
Capitalized Stripping Tonnes Mined 000s
tonnes
104,236
Total Tonnes Moved (incl. heap leach relocation) 000s
tonnes
1,519,756
Total Mineralized Material Processed 000s
tonnes
358,741
Gold Grade Processed g/t Au 0.39
Silver Grade Processed g/t Ag 15.37
Strip Ratio (excluding pre-strip) (waste:mineralized
material)
2.9:1
Average Gold Recovery % 78 %
Average Silver Recovery % 41 %
Total Gold Recovered 000s oz 3,529
Total Silver Recovered 000s oz 72,028
Total Gold Equivalent Recovered(1) 000’s oz 4,432
Average Annual Gold Equivalent
Production(1) (LOM)
000s oz 268
Average Annual Gold Equivalent Production(1)
(following production ramp up)
000s oz 282
Unit Operating Costs
LOM Operating Cost
Mineralized Material Mined $/t mined $2.76
Mineralized Waste Mined
(incl. heap leach pad movement)
$/t mined $2.73
Processed (heap leach) $/t processed $4.30
G&A $/t processed $0.83
LOM Total Cash Costs(2) (net of by-product credit) $/oz $1,270
LOM All-in Sustaining Costs(2) (net of by-product credit) $/oz $1,400
Total Capital Costs
Construction Capital $M $707.5
Capitalized Stripping $M $287.3
Sustaining Capital $M $388.4
Reclamation & Surety $M $69.8
Total Capital & Closure Costs $M $1,453.1

“As a cornerstone of our growth strategy, Mineral Point transforms our gold production profile and positions i-80 Gold as a significant silver producer. This project’s simple design and proven technology, combined with its location on a brownfield site, and our existing understanding of geology, hydrology and metallurgy, substantially reduces execution risks typically associated with projects of this scale. The Mineral Point PEA confirms its potential to become one of Nevada’s largest open-pit truck-and-shovel mining operations,” added Matthew Gili, President and Chief Operating Officer.

 

Mineral Resource Update

The PEA includes all drilling conducted by the previous owners up to 2021 when i-80 Gold acquired the property. The updated mineral resource estimate includes a total of 3,376,000 ounces of gold with an average grade of 0.48 g/t Au in the indicated category and 2,117,000 ounces of gold with average grade of 0.34 g/t Au in the inferred category of resources (see Table 2). Additionally, the resource hosts 104,332,000 ounces of silver at 15.0 g/t in the inferred category and 91,473,000 ounces of silver at 14.6 g/t in the indicated category. The reported mineral resource estimate is constrained to a selected optimized pit shell using Lerchs-Grossman (LG) mining software (see Figure 1).

The majority of the economic material is hosted within the Hamburg Dolomite constrained by the Dunderberg Shale hanging wall and the Secret Canyon Formation foot wall lithology units.

Grade estimation was carried out using a probability assigned constrained kriging (PACK) methodology in Vulcan software to define potentially mineralized high and low-grade domains using different grade threshold values (see Figure 2). Low and high-grade indicators were estimated, and an estimated indicator probability value was selected as the probability threshold to define blocks for the high-grade domain. A block size of 25 ft × 25 ft × 25 ft was selected based on a bench height of proposed mining operations, along with historical mining in the Archimedes pits and future open pit mining considerations. Soft boundaries for the low-grade and high-grade domains were used for selection of drill hole 10-foot composites to estimate grade values to blocks.

Updates to the mineral resource estimate include incorporating a current topographic surface, modified block model coding for certain fields, and refined specific gravity measurements and tonnage factor conversions.

In addition to advancing the project permitting, an updated mineral resource estimate is expected to be completed in 2029 for inclusion in the planned feasibility study. The updated resource is expected to include 50,000 meters of drilling targeting additional sample material for metallurgical test work, resource definition to upgrade current resource classification, and potential expansion. The timing of the anticipated feasibility study is planned to align with the expected completion of the permitting process. The objective is to have an up-to-date feasibility study at the time permits are received to support a planned corporate debt facility, which combined with expected cash flows from the Company’s existing operations, is expected to finance the construction of Mineral Point.

Table 2: Mineral Point Mineral Resource Estimate Statement as of December 31, 2024

Indicated Mineral Resources
Tonnes Au Ag Au Ag
(000) (g/t) (g/t) (000 oz) (000 oz)
Mineral Point 216,982 0.48 15.0 3,376 104,332
Total Indicated 216,982 0.48 15.0 3,376 104,332
Inferred Mineral Resources
Tonnes Au Ag Au Ag
(000) (g/t) (g/t) (000 oz) (000 oz)
Mineral Point 194,442 0.34 14.6 2,117 91,473
Total Inferred 194,442 0.34 14.6 2,117 91,473
Notes to table above:

I.    Mineral resources have an effective date of December 31, 2024

II.    Mineral resources are not mineral reserves and do not have demonstrated economic viability

III.    Mineral resources are the portion of Mineral Point that can be mined profitably by open pit mining
method and processed by heap leaching

IV.    Mineral resources are below an updated topographic surface

V.    Mineral resources are constrained to economic material inside a conceptual open pit shell.  The main
parameters for pit shell construction are a gold price of $2,175/oz Au, a silver price of $26.00/oz,
average gold recovery of 77%, average silver recovery of 40%, open pit mining costs of $3.31/tonne,
heap leach average processing costs of $3.47/tonne, general and administrative cost of $0.83/tonne
processed, gold refining cost of $1.85/oz, silver refining cost of $0.50, and a 3% royalty

VI.    Mineral resources are reported above a 0.1 g/t Au cutoff grade

VII.    Mineral resources are stated as in situ

VIII.    Mineral resources have not been adjusted for metallurgical recoveries

IX.    Reported units are metric tonnes

X.    Reported table numbers have been rounded as required by reporting guidelines and may result in
summation discrepancies

 

Economic Analysis

The Project’s NPV and IRR in relation to fluctuations in the long-term gold and silver price are outlined in Table 3.

Table 3: Mineral Point Gold Price Sensitivity After-tax Analysis

Note: Project NPV at 8% is $296 million.

 

Project Overview

Mineral Point is a component of the broader Ruby Hill Complex located along the southeastern end of the Battle Mountain/Eureka gold trend; a northwest-trending geological belt located in north-central Nevada (see Figure 3). The Project is an open pit heap leach project and is an extension of the historically mined Archimedes open pit, which was a major past-producing asset. Mineral Point contains a large oxide gold and silver deposit, as well as multiple base metal deposits, and has the potential to become the Company’s largest gold producing asset.

The Complex also includes the Archimedes Underground Project, comprised of the Ruby Deeps and 426 zone, which are located immediately northwest and below the historic Archimedes Pit.

Current processing infrastructure at the Complex includes a primary and secondary crushing plant, grinding mill, leach pad, and carbon-in-column circuit, which are designed to process oxide material. Some of these installations are applicable to Ruby Deeps within the Archimedes Underground, however, their capacity does not meet the requirements of Mineral Point, a larger deposit. The existing heap leach pad on the property will be moved in years 7 and 14 of operation as the open pit boundaries for Mineral Point expand.

The Mineral Point deposit is composed of oxide and transitional material, which is amenable to heap leaching after a two-stage crush. Appropriate facilities are planned to the west of the current facilities to minimize haulage distances and optimize facility layout for the approximately 17-year mine life.

 

Geology and Mineralization

The Mineral Point deposit is a large, disseminated gold-silver mineralized zone located immediately west of the Archimedes Pit and the Archimedes Underground. Mineral Point is hosted within a north trending and plunging fold hinge. Stratigraphically, most mineralization is contained within the Cambrian Hamburg dolomite with lesser quantities in the Dunderberg shale.

Locally the deposit contains high-grade gold and silver in what were formerly massive sulfide veins that are now oxidized. The deposit spans a length of over 2.5 kilometers with a width of nearly 1 kilometer at its widest.

 

Mining and Processing

The PEA demonstrates an initial mine life of approximately 17 years with an average annual gold equivalent production(1) of approximately 280,000 ounces of gold following production ramp up. The PEA represents a preliminary point-in-time estimate of the mine plan.

Open pit optimization produced a series of nested pit shells that prioritize early extraction of the most economically viable and robust material. The mine will be developed in consecutive phases to manage the stripping ratio and to provide consistent process feed.

The mine will be accessed by a set of ramps designed for 320-ton haul trucks on the west side of the pit. Mining will be conducted by rope and hydraulic shovels with an annual production rate of 23,000,000 processed tonnes.

The PEA incorporates a two-stage crush for the process material placed on the heap leach. Due to the silver in the deposit, a Merrill Crowe plant has been included in the process. A LOM processing schedule is illustrated in Figure 4.

 

Capital Cost Summary

Mine construction capital, which includes all pre-production facilities and equipment, is estimated to total $708 million. This includes $299 million in mobile equipment for the initial fleet. In addition, approximately 104 million tonnes of stripping is required in the first year of production to gain access to the body or mineralized material costing $287 million.

LOM sustaining capital is estimated at $388 million, primarily for leach pad expansion and mobile equipment maintenance and rebuilds.

Mineral Point is expected to generate an estimated $1,470 million in after-tax cash flow over the current mine life (see Figure 5).

Table 4: Capital Cost Estimates

Mine
Construction
Sustaining
($M) ($M)
Capitalized Waste $287.3
Construction Capital $290.9
Mining Equipment $298.7 $14.3
Sustaining Capital $306.5
Contingency
(15% Mobile Equipment; 25% Facilities)
$117.9 $67.6
Total Capital Cost $994.8 $388.4

 

Operating Cost Summary

The PEA estimates cash costs(2) of $1,270 per ounce of gold and all-in sustaining costs(2) of $1,400 per ounce of gold for the LOM (see Table 5).

Figure 6 illustrates these operating costs over the Project’s estimated production profile.

Table 5: Total and Unit Operating Costs

Total Costs Unit Cost Cost per Ounce
($M) ($/t ) ($/oz Au)
Mining $3,874.4 $10.80 $1,097.8
Processing $1,542.2 $4.30 $437
G&A $296.6 $0.83 $84
Refining, Royalties & Net Proceeds Tax $722.3 $2.01 $205
By-Product Credits ($1,953.0) ($5.4) ($553)
Total Operating Cost/Cash Costs(2) $4,482.6 $12.50 $1,270.1
Closure & Reclamation $69.8 $0.19 $19.8
Sustaining Capital $388.4 $1.08 $110.1
All-in Sustaining Costs(2) $4,940.8 $13.77 $1,399.9

 

Permitting

Base line work began in the fall of 2024 to allow for Mineral Point permitting to commence in the second half of 2027 following regulatory agency approvals of the Lower Archimedes Underground permitting actions. Baseline studies commenced in late 2024 to facilitate the permit application. Based on the anticipated disturbance footprint and associated dewatering, it is expected that National Environmental Policy Act related permitting activities will result in the need to complete an Environmental Impact Statement through the Bureau of Land Management.

Nevada Division of Environmental Protection permitting will also be required with modifications to the site Water Pollution Control Permits, a modification to the Reclamation Permit, and a revision to the Class II Air Quality Operating Permit.

Additionally, due to the sensitivity surrounding water in Diamond Valley, water rights will be a primary focus based on pumping and potential impacts, in addition to, the formation of a pit lake following cessation of mining. With the level of detail that is anticipated for the various permitting actions, the projected timeline for regulatory agency approvals is by the end of 2029.

 

Next Steps to Feasibility Study

A feasibility study in accordance with National Instrument 43-101 – Standards of Disclosure for Mineral Projects and Subpart 1300 of Regulation S-K with an updated mineral resource estimate is expected to be completed in 2029. The updated resource is expected to include 50,000 meters of drilling. Below is a summary of additional work to be conducted.

Resource Delineation and Exploration

  • Begin resource conversion drilling to upgrade inferred mineral resource and to better define the types or mineralized material and mining limits.
  • Include geotechnical drilling in the expansion program to better understand the pit slopes and operating safety factors.
  • Enhance the metallurgical testing with samples specifically collected to improve the understanding of Mineral Point in contrast to the other projects within the Ruby Hill Complex.

Permitting

  • Commence permitting process.
  • Complete hydrology and hydrological studies.

The Company expects to spend approximately $25 million to complete permitting, drilling and the feasibility studies through before construction commences.

 

Technical Disclosure and Qualified Persons

The PEA was prepared in accordance with NI 43-101. The PEA will be filed within 45 days of the Company’s related Archimedes press release issued on February 18, 2025 under the Company’s issuer profile on SEDAR+ at www.sedarplus.ca. An Initial Assessment for the Mineral Point Open Pit Project was also prepared in accordance with S-K 1300 and Item 601 of the Regulation S-K and the S-K 1300 Report will be filed on EDGAR at www.sec.gov. Both reports will be available on the Company’s website at www.i80gold.com. The mineral estimates and project economics are the same under the PEA and the S-K 1300 Report.

The technical information contained in this press release has been prepared under the supervision of, and has been reviewed and approved by Aaron Amoroso, MMSA QP (01548QP) and Jonathan Heiner, P.E., SME-RM (4143808) of Forte Dynamics, Inc, and Tyler Hill CPG., Vice President Geology for the Company, who are all qualified persons within the meaning of NI 43-101 and S-K 1300.

For a description of the data verification, assay procedures and the quality assurance program and quality control measures applied by the Company, please see the Company’s Annual Information Form dated March 12, 2024 filed under the Company’s profile on SEDAR+ at www.sedarplus.ca and filed with the Company’s Form 40-F under the Company’s profile on EDGAR at www.sec.gov. Further information about the PEA referenced in this news release, including information in respect of data verification, key assumptions, parameters, risks and other factors, will be contained in the PEA.

The PEA is preliminary in nature and includes an economic analysis that is based, in part, on inferred mineral resources. Inferred mineral resources that are considered too speculative geologically to have for the application of economic considerations applied to them that would enable them to be categorized as mineral reserves, and there is no certainty that the results of the PEA will be realized. Mineral resources do not have demonstrated economic viability and are not mineral reserves.

 

Endnotes

  1. Gold equivalent ounces (AuEq oz) defined as recovered Au oz plus recovered Ag oz times the price ratio of Ag to Au.  AuEq = Au recovered oz + [(Ag recovered oz) x ($27.25/$2,175)].  LOM overall recoveries for Au and Ag are 78% and 41% respectively. Production defined as process recovered ounces.
  2. This is a non-IFRS/non-GAAP measure. Please see the section titled “Non-IFRS Performance Measures/Non-GAAP Financial Performance Measures” below.
  3. Cash flow and NPV are calculated as of the start of construction, which is anticipated to commence in early 2030, subject to obtaining the necessary permits by December 31, 2029, as anticipated.
  4. After tax metrics assume the Company consumes existing net operating losses.

 

About i-80 Gold Corp.

i-80 Gold Corp. is a Nevada-focused mining company with the fourth largest gold mineral resources in the state of Nevada. The recapitalization plan underway is designed to unlock the value of the Company’s high-grade gold deposits to create a Nevada mid-tier gold producer. i-80 Gold’s common shares are listed on the TSX and the NYSE American under the trading symbol IAU:TSX and IAUX:NYSE. Further information about i-80 Gold’s portfolio of assets and long-term growth strategy is available at www.i80gold.com or by email at info@i80gold.com.

 

APPENDIX

Mineral Point Open Pit Project Detailed Cash Flow Model

Mineral Point UNITS TOTAL /
LOM
2030E 2031E 2032E 2033E 2034E 2035E 2036E 2037E 2038E 2039E 2040E 2041E 2042E 2043E 2044E 2045E 2046E 2047E 2048E 2049E 2050E 2051E
MINING
Mine Life Years 16.5
Mineralized Material
Mined
k tonnes 358,741 7,377 22,680 22,742 22,065 22,680 22,680 22,742 22,680 22,680 22,680 22,742 22,680 22,680 22,680 22,742 22,680 11,537
Expensed Waste
Moved
k tonnes 1,032,779 6,244 96,926 98,462 96,662 100,239 82,750 69,303 71,561 72,913 80,701 80,377 71,389 72,956 8,629 6,224 15,872 1,571
Existing Heap Leach
Relocation(1)
k tonnes 24,000 8,266 15,734
Total Moved k tonnes 1,415,520 13,621 119,605 121,204 118,727 122,919 105,430 100,311 94,241 95,593 103,381 103,118 94,068 95,635 47,042 28,966 38,552 13,107
Strip Ratio (waste:mineralized material) 2.9:1 0.8:1 4.3:1 4.3:1 4.4:1 4.4:1 3.6:1 3.0:1 3.2:1 3.2:1 3.6:1 3.5:1 3.1:1 3.2:1 0.4:1 0.3:1 0.7:1 0.1:1
Daily Mining Rate
(Mineralized Material)
tpd 57,815 20,210 62,136 62,306 60,452 62,136 62,136 62,306 62,136 62,136 62,136 62,306 62,136 62,136 62,136 62,306 62,136 31,607
Capitalized Mining k tonnes 104,236 104,236
PROCESSING
Heap Leach
Processing
Total Tonnes
Processed
k tonnes 358,741 7,377 22,680 22,742 22,065 22,680 22,680 22,742 22,680 22,680 22,680 22,742 22,680 22,680 22,680 22,742 22,680 11,537
Gold Grade g/t Au 0.39 0.26 0.35 0.38 0.61 0.34 0.34 0.40 0.41 0.39 0.48 0.50 0.37 0.47 0.41 0.24 0.28 0.32
Silver Grade g/t Au 15.37 16.00 14.06 14.77 25.60 10.23 9.28 10.82 11.54 8.57 10.90 18.97 36.11 22.29 17.99 13.03 9.20 10.05
Contained Gold ‘000 oz Au 4,525 60.7 253.3 277.0 433.3 246.2 249.8 294.5 300.7 280.7 348.9 364.4 269.1 344.7 301.2 175.3 206.0 118.7
Contained Silver ‘000 oz Ag 177,293 3,795 10,251 10,801 18,164 7,462 6,768 7,913 8,411 6,249 7,947 13,867 26,333 16,255 13,121 9,524 6,705 3,726
Gold Average
Recovery
% 78 % 78 % 78 % 78 % 78 % 78 % 78 % 78 % 78 % 78 % 78 % 78 % 78 % 78 % 78 % 78 % 78 % 78 %
Silver Average
Recovery
% 41 % 41 % 41 % 41 % 41 % 41 % 41 % 41 % 41 % 41 % 41 % 41 % 41 % 41 % 41 % 41 % 41 % 41 %
Recovered Gold ‘000 oz Au 3,529 50.5 210.9 223.7 348.3 200.1 204.0 243.4 244.0 215.9 275.1 274.8 209.8 207.1 210.4 143.9 168.9 98.5
Recovered Silver ‘000 oz Ag 72,028 1,601 4,250 4,456 7,318 3,125 2,783 3,284 3,471 2,578 3,273 5,579 10,533 6,507 5,248 3,809 2,717 1,495
Total Tonnes
Processed
k tonnes 358,741 7,377 22,680 22,742 22,065 22,680 22,680 22,742 22,680 22,680 22,680 22,742 22,680 22,680 22,680 22,742 22,680 11,537
Total Gold Production ‘000 oz Au 3,529 50 211 224 348 200 204 243 244 216 275 275 210 207 210 144 169 99
Total Silver
Production
‘000 oz Ag 72,028 1,601 4,250 4,456 7,318 3,125 2,783 3,284 3,471 2,578 3,273 5,579 10,533 6,507 5,248 3,809 2,717 1,495
Total Gold Equiv.
Production(5)
‘000 oz Au 4,432 70.5 264.2 279.5 440.0 239.2 238.9 284.5 287.5 248.2 316.1 344.7 341.8 288.6 276.2 191.7 203.0 117.3
Recoverable Ag
ounces remaining (BOP)
REVENUE
Gold Price US$/oz Au $2,175 $2,175 $2,175 $2,175 $2,175 $2,175 $2,175 $2,175 $2,175 $2,175 $2,175 $2,175 $2,175 $2,175 $2,175 $2,175 $2,175 $2,175 $2,175 $2,175 $2,175 $2,175
Silver Price US$/oz Ag $27.25 $27.25 $27.25 $27.25 $27.25 $27.25 $27.25 $27.25 $27.25 $27.25 $27.25 $27.25 $27.25 $27.25 $27.25 $27.25 $27.25 $27.25 $27.25 $27.25 $27.25 $27.25
Gold Revenues US$M $7,668.8 $110 $458 $486 $757 $435 $443 $529 $530 $469 $598 $597 $456 $450 $457 $313 $367 $214
Silver Revenue $1,953.0 $43 $115 $121 $198 $85 $75 $89 $94 $70 $89 $151 $286 $176 $142 $103 $74 $41
Total Revenue $9,621.7 $153 $      574 $     607 $     955 $     519 $     519 $     618 $     624 $     539 $     686 $     748 $     741 $     626 $     599 $     416 $     441 $     255
OPERATING COSTS
Mining Costs US$M $988.6 $20.3 $62.5 $62.7 $60.8 $62.5 $62.5 $62.7 $62.5 $62.5 $62.5 $62.7 $62.5 $62.5 $62.5 $62.7 $62.5 $31.8
Mining Costs (Waste &
Relocation )
US$M $2,885.8 $17.2 $267.1 $271.3 $266.4 $276.2 $228.0 $204.7 $197.2 $200.9 $222.4 $221.5 $196.7 $201.0 $49.8 $17.2 $43.7 $4.3
Heap Leach
Processing
US$M $1,542.2 $31.7 $97.5 $97.8 $94.9 $97.5 $97.5 $97.8 $97.5 $97.5 $97.5 $97.8 $97.5 $97.5 $97.5 $97.8 $97.5 $49.6
G&A US$M $296.6 $6.1 $18.7 $18.8 $18.2 $18.7 $18.7 $18.8 $18.7 $18.7 $18.7 $18.8 $18.7 $18.7 $18.7 $18.8 $18.7 $9.5
Total Operating
Cost
US$M $5,713.2 $75.3 $445.9 $450.6 $440.3 $455.0 $406.8 $383.9 $376.0 $379.7 $401.1 $400.7 $375.5 $379.8 $228.5 $196.4 $222.5 $95.3
Refining & Sales US$M $42.5 $0.9 $2.5 $2.6 $4.3 $1.9 $1.8 $2.1 $2.2 $1.7 $2.1 $3.3 $5.7 $3.6 $3.0 $2.2 $1.7 $0.9
Royalties & State
Taxes(2)
US$M $679.8 $16.2 $38.6 $41.1 $78.0 $32.7 $32.2 $40.5 $40.7 $32.0 $43.3 $51.6 $63.9 $44.9 $46.5 $30.7 $28.8 $18.1
Mining costs
(Mineralized Material)
US$/t mined $2.76 $2.76 $2.76 $2.76 $2.76 $2.76 $2.76 $2.76 $2.76 $2.76 $2.76 $2.76 $2.76 $2.76 $2.76 $2.76 $2.76 $2.76
Mining Costs
(Waste & Relocation)
US$/t mined $2.73 $2.76 $2.76 $2.76 $2.76 $2.76 $2.76 $2.64 $2.76 $2.76 $2.76 $2.76 $2.76 $2.76 $2.04 $2.76 $2.76 $2.76
Processing (Heap
leach)
US$/t process $4.30 $4.30 $4.30 $4.30 $4.30 $4.30 $4.30 $4.30 $4.30 $4.30 $4.30 $4.30 $4.30 $4.30 $4.30 $4.30 $4.30 $4.30
G&A US$/t process $0.83 $0.83 $0.83 $0.83 $0.83 $0.83 $0.83 $0.83 $0.83 $0.83 $0.83 $0.83 $0.83 $0.83 $0.83 $0.83 $0.83 $0.83
Total US$/t process $15.9 $10.21 $19.66 $19.81 $19.95 $20.06 $17.94 $16.88 $16.58 $16.74 $17.69 $17.62 $16.56 $16.75 $10.08 $8.64 $9.81 $8.26
CAPITAL
EXPENDITURES
Initial & Construction
Capital
US$M $707.5 $667.0 $40.6
Capitalized Stripping US$M $287.3 $287.3
Sustaining Capital US$M $388.4 $2.6 $21.4 $8.4 $71.0 $10.6 $9.2 $71.5 $9.0 $9.4 $71.8 $9.0 $9.4 $69.1 $4.7 $5.1 $4.0 $2.3
Total Capital US$M $1,383.2 $667.0 $330.5 $21.4 $8.4 $71.0 $10.6 $9.2 $71.5 $9.0 $9.4 $71.8 $9.0 $9.4 $69.1 $4.7 $5.1 $4.0 $2.3
Reclamation & Surety US$M $69.8 $0.5 $0.5 $0.5 $0.5 $0.5 $0.5 $0.5 $0.5 $0.5 $0.5 $0.5 $0.5 $0.5 $0.5 $0.5 $18.7 $12.5 $12.5 $12.5 $3.1 $3.1
CASH COSTS & AISC
Total Cash Costs
(Inc. Royalty) (net of by-
product credit)
US$/oz $1,270 $971 $1,762 $1,670 $931 $2,024 $1,791 $1,386 $1,331 $1,591 $1,301 $1,107 $760 $1,216 $645 $875 $1,061 $748
All-in Sustaining
Costs(3)
US$/oz $1,400 $1,033 $1,866 $1,710 $1,136 $2,079 $1,838 $1,682 $1,370 $1,637 $1,563 $1,142 $807 $1,553 $670 $1,040 $1,159 $898
CASH FLOW ANALYSIS
Revenue US$M $9,621.7 $153 $574 $607 $955 $519 $519 $618 $624 $539 $686 $748 $741 $626 $599 $416 $441 $255
Operating Costs Gold
& Royalties
US$M ($6,435.5) ($92) ($487) ($494) ($523) ($490) ($441) ($426) ($419) ($413) ($447) ($456) ($445) ($428) ($278) ($229) ($253) ($114)
Depreciation US$M ($1,383.2) ($28) ($279) ($79) ($73) ($47) ($49) ($60) ($68) ($62) ($80) ($95) ($74) ($76) ($100) ($70) ($86) ($56)
Net Operating
Income (Pre-Tax)
US$M $1,803.0 $33 ($192) $33 $359 ($18) $29 $132 $137 $64 $160 $198 $222 $122 $221 $117 $102 $84
Income Taxes US$M ($263.1) ($1) ($1) ($12) ($1) ($4) ($5) ($8) ($29) ($38) ($39) ($22) ($46) ($24) ($18) ($15)
Net Income US$M $1,539.9 $31 ($192) $32 $347 ($18) $28 $128 $132 $56 $131 $160 $183 $101 $175 $92 $85 $69
Depreciation &
Depletion
US$M $1,383.2 $27.9 $278.7 $79.2 $73.4 $47.4 $49.2 $59.7 $68.4 $61.6 $80.1 $95.0 $74.3 $75.7 $100.3 $70.3 $85.7 $56.3
Reclamation US$M ($69.8) ($0.5) ($0.5) ($0.5) ($0.5) ($0.5) ($0.5) ($0.5) ($0.5) ($0.5) ($0.5) ($0.5) ($0.5) ($0.5) ($0.5) ($0.5) ($18.7) ($12.5) ($12.5) ($12.5) ($3.1) ($3.1)
Working Capital US$M $8.7 $42.8 $0.5 ($1.2) $1.7 ($5.6) ($2.6) ($0.9) $0.4 $2.5 ($0.0) ($2.9) $0.5 ($17.5) ($3.7) $3.0 ($14.7) ($11.0)
Operating Cash
Flow
US$M $2,853.3 $68 $129 $111 $419 $31 $71 $184 $199 $118 $213 $254 $254 $176 $257 $158 $155 $98 ($23) ($12) ($3) ($3)
Capital Expenditures US$M ($1,383.2) ($667) ($330) ($21) ($8) ($71) ($11) ($9) ($72) ($9) ($9) ($72) ($9) ($9) ($69) ($5) ($5) ($4) ($2)
NET CASH FLOW US$M $1,470.0 ($667) ($263) $107 $103 $348 $20 $62 $113 $190 $108 $141 $245 $245 $107 $252 $153 $151 $96 ($23) ($12) ($3) ($3)
Cumulative CF
PROJECT ECONOMICS
(as of Jan. 1 2029)
After-tax NPV 5%
discounting
US$M $ 614.1
12.1 %
Notes to table above:
1) Relocation of existing heap leach material at Ruby Hill

2) Includes 3% royalty on Au & Ag, and 10% stream on Ag

3) AISC calculated on cash basis, not accrual basis

4) Project NPV at 8% is $296 million

5) Gold equivalent ounces (AuEq oz) defined as recovered Au oz plus recovered Ag oz times the price ratio of Ag to Au.  AuEq = Au recovered oz + [(Ag recovered oz) x ($27.25/$2,175)].
LOM overall recoveries for Au and Ag are 78% and 41% respectively. Production defined as process recovered ounces

Posted February 21, 2025

Share this news article

MORE or "UNCATEGORIZED"


K92 Mining Announces Latest Drilling Results From Arakompa Including Confirmation of Two Significant Thick High-Grade Veins (AR1 & AR2), Southern Strike Extension and Bulk Zone Expansion

K92 Mining Inc . (TSX:KNT) (OTCQX:KNTNF) is pleased to announce its fourth set of drilling results... READ MORE

February 21, 2025

Centerra Gold Announces 2024 Year-End Mineral Reserves and Resources, Including an Initial Resource at Goldfield; Provides Exploration Update

Centerra Gold Inc. (TSX: CG) (NYSE: CGAU) announces its 2024 year-end estimates for mineral reserves... READ MORE

February 21, 2025

Eldorado Gold Delivers Strong 2024 Full Year and Fourth Quarter Financial and Operational Results; Positive Free Cash Flow Realized in the Quarter and Full Year

Eldorado Gold Corporation (TSX: ELD) today reports the Company’s financial and operational results... READ MORE

February 21, 2025

Mandalay Resources Announces Record Financial Performance in 2024, Generating $69 Million in Free Cash Flow

Mandalay Resources Corporation (TSX: MND) (OTCQB: MNDJF) announced its financial results for the fou... READ MORE

February 21, 2025

Imperial Provides Update on Red Chris 2024 Production and Production Guidance for 2025

Imperial Metals Corporation (TSX:III) reports that 2024 metal production from Red Chris (100% basis... READ MORE

February 21, 2025

Copyright 2025 The Prospector News