Gunnison Copper Corp. (NYSE American: GUNN) (TSX: GCU) (OTCQB: GCUMF) (FSE: 3XS0), an American copper producer headquartered in Phoenix, Arizona, announces its financial and operational results for the three and nine months ended September 30, 2026. All dollar amounts are in U.S. dollars and prepared in accordance with IFRS Accounting Standards as issued by the International Accounting Standards Board.
Highlights Q3 2026
Subsequent to Quarter End
Upcoming Milestones
Financial and Operational Results
The following table summarizes selected financial and operational information for the Company for the third quarter ended September 30, 2026:
| Selected Quarterly Metrics | Units | Q1 2026 | Q2 2026 | Q3 2026 | YTD |
| Mineralized material mined | Short tons | 655,510 | 1,392,559 | 1,948,056 | 3,996,125 |
| Copper grade stacked | % | 0.356% | 0.558% | 0.617% | 0.536% |
| Copper cathode produced | lbs. | 2,106,583 | 2,006,315 | 3,423,948 | 7,536,846 |
| Revenue | US$ 000’s | 20,104 | 23,612 | 36,134 | 79,850 |
| Copper cathode sales revenue | US$ 000’s | 10,796 | 13,733 | 21,295 | 45,824 |
| Costs of production | US$ 000’s | (8,717) | (7,380) | (12,343) | (28,440) |
| Income from mine operations | US$ 000’s | 11,387 | 16,232 | 23,791 | 51,410 |
| Net income | US$ 000’s | 1,666 | 13,101 | 12,739 | 27,506 |
| EPS | US$/share | 0.004 | 0.03 | 0.03 | 0.06 |
Note: Financial information is presented in US dollars. Figures may be subject to rounding.
For the three months ended September 30, 2026, Gunnison generated US$36.1 million in revenue, compared with US$2.9 million in the corresponding period of 2025, reflecting increased copper production and sales following the restart and ramp-up of Johnson Camp. Revenue included US$21.3 million from copper cathode sales and US$14.7 million of deferred mining and processing demonstration service revenue.
The Company reported net income of US$12.7 million, or US$0.03 per share, compared with a net loss of US$22.9 million, or US$0.06 per share, in the third quarter of 2025.
Johnson Camp produced approximately 3.42 million pounds of copper cathode during Q3 2026, an increase of 71% compared with Q2 2026. Copper cathode sales totaled approximately 3.31 million pounds, at an average realized price of US$6.41 per pound, compared with 2.26 million pounds at US$6.07 per pound in the preceding quarter.
The Company continued to improve operating efficiencies as production increased. SX/EW unit costs decreased to US$0.56 per pound of copper produced, compared with US$0.76 per pound in Q2 2026, reflecting improved fixed-cost absorption as production volumes increased.
For the nine months ended September 30, 2026, the Company generated US$79.9 million in revenue and net income of US$27.5 million, or US$0.06 per share, compared with revenue of US$3.5 million and a net loss of US$46.8 million, or US$0.13 per share, in the corresponding period of 2025.
Reported net income included non-cash fair value adjustments associated with the Nuton Stage 2 payable and copper stream derivative liabilities.
At September 30, 2026, Gunnison had US$23.5 million in cash and cash equivalents, including US$16.1 million of non-Nuton cash and US$7.4 million of Nuton-related cash.
The financial information in this release was selected from the Company’s condensed consolidated interim financial statements and MD&A for the three and nine months ended September 30, 2026, which is available on SEDAR+, EDGAR and the Company’s website.
ABOUT GUNNISON COPPER
Gunnison Copper Corp. is a multi-asset pure-play copper developer and producer that controls the Cochise Mining District, containing 12 known deposits within an 8 km economic radius, in the Southern Arizona Copper Belt.
Its flagship asset, the Gunnison Copper Project, has a main pit Measured and Indicated Mineral Resource containing over 846 million tons with a total copper grade of 0.33% containing 5.19 billion pounds of copper (Measured Mineral Resource of 192 million tons at 0.37% containing 1.42 billion pounds of copper and Indicated Mineral Resource of 655 million tons at 0.31% containing 3.77 billion pounds of copper).
The Strong & Harris satellite deposit, located approximately 1.9 miles from the Gunnison processing facilities, is also included in the mine plan and hosts an Inferred Mineral Resource of 76 million tons grading 0.49% total copper (0.32% CuOx) at a 0.07% cutoff, 0.56% zinc and 0.12 oz/ton silver, containing approximately 740 million pounds of copper, including 483 million pounds of oxide copper, as well as zinc (856 million pounds) and silver (9.0 million ounces).
A preliminary economic assessment was completed in March 2026 for the Gunnison Project yielding robust economics including an NPV8% of $2 billion, IRR of 22.5%, and payback period of 3.9 years. It is being developed as a conventional operation with open pit mining, heap leach, and SX/EW refinery to produce finished copper cathode on-site with direct rail link. The PEA is preliminary in nature and includes Inferred Mineral Resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves. There is no certainty that the conclusions reached in the PEA will be realized. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.
In addition, Gunnison’s Johnson Camp Asset, which is now in production, is fully funded by Nuton LLC, a Rio Tinto Venture, with a production capacity of up to 25 million lbs of finished copper cathode annually.
Other significant deposits controlled by Gunnison in the district, with potential to be economic satellite feeder deposits for Gunnison Project infrastructure, include South Star, and eight other deposits.
For more information on the Company, please visit our website at www.GunnisonCopper.com.
For additional information on the Gunnison Project please refer to the technical report titled “Gunnison Project NI 43-101 Technical Report, Preliminary Economic Assessment, Cochise County, Arizona, USA” with an effective date of March 18, 2026 filed on SEDAR+ at www.sedarplus.ca.
For additional information on the Johnson Camp Mine please refer to the technical report titled “Johnson Camp Mine NI 43-101 Technical Report, Cochise County, Arizona, USA” with an effective date of March 18, 2026 filed on SEDAR+ at www.sedarplus.ca.
Dr. Roland Goodgame, Senior VP of Project Development of the Company is a Qualified Person as defined by NI 43-101. Dr. Goodgame has reviewed and approved the technical information contained in this news release.
For further information regarding this press release, please contact:
Gunnison Copper Corp.
Concord Place, Suite 300, 2999 North 44th Street, Phoenix, AZ, 85018
Melissa Mackie
T: 647.533.4536
E: info@GunnisonCopper.com
www.GunnisonCopper.com
The global silver market is forecast to record its sixth consecutive annual deficit in 2026, with de... READ MORE
First Canadian Graphite Inc. (TSX-V:FCI)(OTCQB:GRAPF) is pleased to announce that it has received su... READ MORE
Denarius Metals Corp. (Cboe CA: DMET) (OTCQX: DNRSF) announced today that it has filed its un... READ MORE
In this episode of the Prospector Podcast, host Michael Fox speaks with ... READ MORE