Goldsource Mines Inc. (TSX-V:GXS) (OTCBB:GXSFF) (FWB:G5M) today announced that throughput and production from the Eagle Mountain Gold Project in Guyana have been affected in July and August, primarily as a result of weather related issues, a delay in the shipment of a 40-tonne truck to site and the low grade of available material. Processing operations were suspended on July 23, 2016 to reduce consumable costs and focus on developing access to Pit #4 and preparing Pit #4 for open pit mining. Eagle Mountain is expected to begin processing higher-grade material from Pit #4 in early September 2016.
Since July 1, 2016, the Company has processed 13,922 tonnes over 19 days, with average throughput of 732 tonnes per day (“tpd”). During the same period, Goldsource poured 38 ounces of gold and sold 37 ounces of gold at an average price of US$1,336 per ounce. As a result, Eagle Mountain, during July and August, has performed below commercial production levels achieved June 20, 2016 (see news release dated June 21, 2016 and the Preliminary Economic Assessment report titled “Preliminary Economic Assessment of the Eagle Mountain Saprolite Gold Project, Guyana”, dated September 12, 2014 with an effective date of June 15, 2014.
In the first half of 2016, Management elected to shift focus from development of Pit #6 (with material designed to be transported by a gravity fed chute) to the higher grade and closer proximity Pit #4, which is at a lower elevation relative to the process plant, requiring the use of a truck to haul material. Management was originally expecting the delivery of a 40-tonne truck to site in late July to deliver higher-grade material from Pit #4 to the processing plant. A lack of tire availability and an error by the ground transportation freight forwarder resulted in a delay in the ground shipment, which significantly delayed the sea freight departure. The arrival of the truck in Guyana on August 23, 2016 has been confirmed, with an expected arrival on site in early September 2016.
During the commissioning phase of Eagle Mountain, the focus was on processing low-grade material during the optimization process. The plan was to continue to process lower-grade mineralization until higher-grade material could be exploited through the arrival of the 40-tonne truck to site. However, with the grade processed averaging just 0.43 grams per tonne (“g/t”) gold (below the 0.5 g/t cutoff grade for the Eagle Mountain resource) Management elected to stop processing material on July 23 to reduce the cost of onsite consumables and shift focus to developing access and mine preparation for the higher-grade material at Pit #4.
Unexpectedly heavier rainfall due to “La Nina” at Eagle Mountain has made road access challenging, which contributed to additional downtime in July and August. Fewer weather related issues are expected as we move into the drier months of September through March.
While Eagle Mountain has underperformed in July and August, the Company expects to return to commercial production levels in early September based on the following:
2016 Guidance
Weather and a delay in the delivery of the 40-tonne truck procured in Q2, 2016 have impacted operations in Q3, 2016. In addition, Management has also applied for a permit from the Government of Guyana to operate a low impact intensive cyanide leaching circuit at Eagle Mountain, which is expected to substantially improve gold recovery and production from the mine. While the permit was originally expected in July 2016, to allow the SLR unit to be operational by October 2016, the permit has not yet been granted and there is no firm date for its issuance. As a result, the Company has revised its targets and assumptions previously announced in its news release dated June 21, 2016 as follows:
Outlook
While the Company has reduced its 2016 production guidance, the phased expansion approach to Eagle Mountain remains intact. The throughput expansion plan and the contemplation of integrating an SLR unit into the process flow sheet warrants completion of a pre-feasibility study by H1 2017. Management’s expects the PFS to support the design, purchase and deployment of the Phase II plant, which should increase throughput capacity to approximately 4,000 tpd. The Company expects to achieve this expansion through the implementation of the following:
Night shift: A second (night) shift is to be phased in during the latter part of Q3, 2016.
The Company continues to evaluate opportunities to improve recoveries and the average head grade at Eagle Mountain to increase production prior to the Phase II expansion. Opportunities include:
With Eagle Mountain expected to begin processing the higher-grade material from Pit #4, a significant improvement in production is expected, with potential for a material improvement in production and operating margins should a permit for an SLR unit be granted.
ABOUT GOLDSOURCE MINES INC.
Goldsource Mines Inc. (www.goldsourcemines.com) is a Canadian resource company that has recently achieved commercial production for Phase I at it 100%-owned Eagle Mountain Gold Project, located in Guyana. Goldsource is led by an experienced management team, proven in making exploration discoveries and in project construction.
Significant copper and molybdenum intersections include: HM09: 13... READ MORE
Aya Gold & Silver Inc. (TSX: AYA) (OTCQX: AYASF) is pleased t... READ MORE
Key Highlights – Preliminary Economic Assessment Pre-Tax Net Pr... READ MORE
Aris Mining Corporation (TSX: ARIS) (NYSE-A: ARMN) announces its ... READ MORE
Orla Mining Ltd. (TSX: OLA) (NYSE: ORLA) announces the results fo... READ MORE