
Fortuna Mining Corp. (NYSE: FSM) (TSX: FVI) reports production results for the second quarter and first half of 2026 from its three operating mines in West Africa and Latin America, and provides updates on growth initiatives, capital allocation, safety, and key operating activities across its portfolio. All figures presented in this news release are expressed in U.S. dollars, unless otherwise indicated.
Q2 2026 highlights
Production
Growth initiatives
Return to shareholders
Safety
Q2 and H1 2026 consolidated GEO production
| GEO Production | ||||
| Q2 2026 | Q1 2026 | H1 2026 | 2026 Annual Guidance | |
| Ongoing Operations | ||||
| Séguéla, Côte d’Ivoire | 41,683 | 42,016 | 83,699 | 160,000 – 170,000 |
| Lindero, Argentina | 20,829 | 21,545 | 42,374 | 92,000 – 102,000 |
| Caylloma, Peru | 9,705 | 9,311 | 19,016 | 29,000 – 33,000 |
| Total | 72,217 | 72,872 | 145,089 | 281,000 – 305,000 |
Notes:
West Africa region
Séguéla Mine, Côte d’Ivoire: Advancing growth initiatives
| Q2 2026 | Q1 20261 | |
| Tonnes milled | 421,464 | 430,953 |
| Average tpd milled | 4,581 | 4,788 |
| Gold grade (g/t) | 3.46 | 3.21 |
| Gold recovery (%) | 92.1 | 93.4 |
| Gold production (oz)2 | 41,683 | 42,016 |
Notes:
Mining
Séguéla mined a total of 433,231 tonnes of ore, averaging 3.06 g/t Au and containing an estimated 42,555 ounces of gold from the Antenna, Ancien, Koula, and Sunbird pits. A total of 5,902,142 tonnes of waste was mined during the period, resulting in a strip ratio of 13.6:1. Additionally, 731,647 tonnes of waste was mined during the quarter at Sunbird South to gain access to the underground portal position.
Processing
Séguéla produced 41,683 ounces of gold during the quarter at an average head grade of 3.46 g/t Au, broadly in line with the previous quarter and slightly ahead of the mine plan. Tonnes milled were slightly lower than in the previous quarter, reflecting a planned mill reline during the period.
Project updates
Process plant expansion study
Process plant expansion studies were completed during the quarter by Lycopodium, including requirements for supporting infrastructure. The proposed expansion would increase processing capacity to approximately 2.3 million tonnes per annum and is designed to improve recoveries through increased residence time in the leach circuit.
The scope primarily includes the addition of a ball mill and increased thickener, leach, and gravity circuit capacity, with existing primary crushing capacity determined to be sufficient for the proposed throughput.
Estimated project capital is approximately $100 million, including additional backup power generation capacity and supporting infrastructure. The project is currently being evaluated for a construction decision.
Sunbird Underground Project
The Sunbird Underground Project continued to advance. During the quarter, Fortuna announced a 34% increase in estimated Mineral Reserve gold ounces and a 55% increase in Inferred Mineral Resource gold ounces for the Sunbird Underground deposit. Drilling continues to infill Inferred Mineral Resources and test down-dip and strike extensions.
In parallel, the Company approved a $48 million budget for underground equipment, infrastructure, and the establishment of an owner-operator team, with orders already placed for long-lead items.
The ESIA for the Sunbird Underground Project has been filed with the government of Côte d’Ivoire and is at an advanced stage of review, with the permit expected to be received in Q4 2026.
Solar power plant
The 6 MW photovoltaic solar power plant has been commissioned. In light of the expected advancement of the process plant expansion and Sunbird Underground Project, the Company is evaluating an expansion of the solar plant to 10 MW. No upfront capital investment by Fortuna would be required for this expansion, as the contractor would incorporate the related capital cost into its fee.
Exploration activities
During the quarter, two additional drill rigs were mobilized to Séguéla, increasing the total number of rigs on site to seven. Two rigs remain active at Sunbird, while the remaining five are focused on upgrading Kingfisher Inferred Mineral Resources to Indicated status and testing further extensions of the Kingfisher deposit.
Year-to-date production
Séguéla produced a total of 83,699 ounces of gold in the first half of 2026 and remains on track to achieve annual production guidance, while advancing key growth initiatives including the process plant expansion study and Sunbird Underground Project.
Diamba Sud Gold Project, Senegal: Advancing toward final investment decision
During the second quarter of 2026, the Diamba Sud Gold Project advanced toward a final investment decision following the receipt of the ESIA and publication of feasibility study results. The related NI 43-101 Technical Report is expected to be filed on SEDAR+ within the required 45-day period.
Early works and procurement activities continued to support project readiness, including construction of the new site access road and installation of additional temporary accommodation and office facilities for the owner’s project and pre-production teams. The contract for a new 320-person camp has been awarded, and tendering for other major construction packages is well advanced. Letters of award have been issued for the project’s critical path contracts, including the process plant and power station, securing the delivery schedule for the heavy fuel oil generators, the project’s longest-lead item, which are expected in mid-2027. In addition, tenders for all process plant long-lead equipment, including the SAG mill and jaw crusher, have been launched, with purchase orders expected early in the third quarter.
The project remains positioned for a final investment decision, supporting continued momentum toward first gold production in mid-2028.
Latin America region
Lindero Mine, Argentina: Positioned for stronger second-half production
| Q2 2026 | Q1 20261 | |
| Ore placed on pad (t) | 1,558,750 | 1,525,286 |
| Gold grade (g/t) | 0.64 | 0.62 |
| Gold production2 (oz) | 20,829 | 21,545 |
Notes:
Mining
During the first half of 2026, Lindero placed on the leach pad approximately 95% of the ounces planned for the period required to achieve the midpoint of its annual production guidance. With the completion in the second quarter of key capital projects aimed at improving comminution reliability and availability, the operation is well positioned to deliver stronger production and lower sustaining costs in the second half of the year.
During the second quarter, Lindero mined 1.38 million tonnes of ore at a strip ratio of 1.81:1. A total of 1.56 million tonnes was stacked on the leach pad at an average gold grade of 0.64 g/t, containing an estimated 32,008 ounces of gold. Gold ounces placed increased by 4.8% compared to the first quarter, in line with the planned mine sequence and supporting anticipated production growth in the remainder of 2026.
Processing
Lindero produced 20,829 ounces of gold during the second quarter of 2026, broadly consistent with production levels achieved in the first quarter.
Looking ahead, with all major plant capital projects now complete, Management expects improved mechanical availability across the processing circuit, supporting higher crushing and stacking rates. Combined with higher ore grades scheduled in the mine plan for the second half of the year, these improvements are expected to drive a significant increase in gold production and support the achievement of Lindero’s 2026 annual guidance.
Year-to-date production
Lindero produced a total of 42,374 ounces of gold in the first half of 2026 and remains on track to achieve annual production guidance.
Exploration activities
Brownfields exploration at Lindero continued during the quarter, with two drill rigs focused on testing Inferred Mineral Resources and open mineralization areas below the ultimate Mineral Reserve pit shell. The program is advancing as planned and is expected to be completed during the third quarter of 2026.
At the Cerro Lindo gold prospect, drilling is targeting approximately 7,000 metres, with the current campaign expected to be completed by year-end.
Caylloma Mine, Peru: Continued strong operating performance
| Q2 2026 | Q1 20261 | |
| Tonnes milled | 141,337 | 136,701 |
| Average tpd milled | 1,588 | 1,553 |
| Silver grade (g/t) | 62 | 72 |
| Silver recovery2 (%) | 82.26 | 81.89 |
| Silver production (oz) | 231,294 | 257,603 |
| Lead grade (%) | 2.76 | 2.99 |
| Lead recovery (%) | 90.89 | 90.59 |
| Lead production (lbs) | 7,815,387 | 8,174,740 |
| Zinc grade (%) | 4.26 | 4.21 |
| Zinc recovery (%) | 90.64 | 90.80 |
| Zinc production (lbs) | 12,037,240 | 11,525,766 |
| GEO production (oz) | 9,7053 | 9,3114 |
Notes:
Mining
Mine production totaled 133,940 tonnes of ore in the second quarter, predominantly from overhand cut-and-fill mining, which accounted for 75% of production, with 25% extracted through sub-level stoping.
Processing
Caylloma produced 231,294 ounces of silver during the second quarter at an average head grade of 62 g/t Ag, a 10% decrease compared to the previous quarter, in line with the planned mining sequence for the period. Zinc and lead production totaled 12.0 million pounds and 7.8 million pounds, respectively, at average head grades of 4.26% Zn and 2.76% Pb, reflecting consistent production when compared to the first quarter and in line with the mining sequence.
Project update
As of June 30, 2026, the project to expand the capacity of tailings storage facility No. 3 at the Caylloma Mine was 28% complete and progressing according to plan.
Year-to-date production
Caylloma produced 9,705 GEO in the second quarter and 19,016 GEO in the first half of 2026, positioning the mine to achieve its annual production guidance.
Qualified Person
Eric Chapman, Senior Vice President of Technical Services for Fortuna Mining Corp., is a Professional Geoscientist registered with Engineers and Geoscientists British Columbia (Registration No. 36328), and a Qualified Person as defined by National Instrument 43-101- Standards of Disclosure for Mineral Projects. Mr. Chapman has reviewed and approved the scientific and technical information contained in this news release and has verified the underlying data.
About Fortuna Mining Corp.
Fortuna Mining Corp. is a Canadian precious metals mining company with three operating mines and a portfolio of exploration projects in Argentina, Côte d’Ivoire, Guinea, Guyana, and Peru, as well as the Diamba Sud Gold Project in Senegal. Sustainability is at the core of our operations and stakeholder relationships. We produce gold and silver while creating long-term shared value through efficient production, environmental stewardship, and social responsibility.
Mogotes Metals Inc. (TSX-V: MOG) (FSE: OY4) (OTCQB: MOGMF) is ple... READ MORE
Roxmore Resources Inc. (TSX: RM) (OTCQX: GARLF) is pleased to rep... READ MORE
Equinox Gold Corp. (TSX: EQX) ( NYSE American: EQX) is pleased to... READ MORE
Equinox Gold transaction on track for Q3 closing Orla Mining L... READ MORE