On Track for Strong Year
Aya Gold & Silver Inc. (TSX: AYA) (OTCQX: AYASF) is pleased to announce interim financial and operational results for the third quarter ended September 30, 2023. All amounts are in US dollars unless otherwise stated.
Q3-2023 Highlights
Operational and Financial:
Exploration and Development:
Zgounder Expansion:
(1) | The Corporation reports non-GAAP measures, which include cash costs per silver ounce and free cash flow, which are widely used in the mining industry as a benchmark for performance, but do not have a standardized meaning and the methods used by the Corporation to calculate such measures may differ from methods used by other companies with similar descriptions. See “Non-GAAP Measures” on pages 16-17 of the Corporation’s Q3-2023 MD&A for a reconciliation of non-GAAP to GAAP measures. |
(2) | Non-GAAP Measures, consisting of cash and cash equivalents of $50,609,505 and restricted cash of $20,562,506. |
Environmental, Social and Governance:
“The third quarter was an exceptional quarter from an operational perspective that sets us up for another record year. Zgounder delivered one of its best silver production quarters at industry-low cash costs and generated record cash flow,” said Benoit La Salle, President and CEO. “Based on our performance to date, we are well-positioned to exceed our 2023 guidance, notably our production guidance for a third consecutive year.
We continue to develop and grow our project pipeline and to execute on our expansion plan, which is now about 66% complete and on budget. Drilling at Zgounder reconfirmed continuity of high-grade mineralization both at surface and underground. Further, high-grade drill results at Boumadine extended the strike of the main trend which remains open in all directions. These results will be included in our Q1-2024 resource estimate and underpin our focus to grow ounces on a per share basis.
These excellent quarterly results highlight the dedication and commitment of our local teams, particularly in the context of the devastating Al Haouz earthquake.”
Q3-2023 Operational and Financial Highlights
Key Performance Metrics* | Q3-2023 | Q3-2022 | Variation | |
Operational | ||||
Ore Mined (tonnes) | 132,998 | 74,009 | 80 % | |
Ore Processed (tonnes) | 70,258 | 69,697 | 1 % | |
Average Processed Grade (g/t Ag) | 261 | 232 | 13 % | |
Mill Recovery (%) | 86.6 % | 86.2 % | (0.4 %) | |
Silver Ingots Produced (oz) | 195,913 | 184,629 | 6 % | |
Silver in Concentrate Produced (oz) | 323,172 | 267,052 | 21 % | |
Total Silver Produced (oz) | 519,085 | 451,681 | 15 % | |
Silver Ingots Sold (oz) | 205,043 | 174,243 | 18 % | |
Silver in Concentrate Sold (oz) | 338,940 | 245,517 | 38 % | |
Total Silver Sales (oz) | 543,983 | 419,760 | 30 % | |
Avg. Net Realized Silver ($/oz) | 21.53 | 17.12 | 26 % | |
Cash Costs per Silver Ounce Sold (¹ ) | 10.73 | 14.03 | (24 %) | |
Financial (in ‘000s of US dollars) | ||||
Revenue | 11,714 | 7,187 | 63 % | |
Cost of sales | 5,531 | 6,413 | (14 %) | |
Gross Margin | 6,183 | 774 | 699 % | |
Operating (loss) | 3,652 | (1,329) | (375 %) | |
Net Earnings (loss) | 1,206 | 672 | 79 % | |
Operating Cash Flow | 7,724 | 5,701 | 35 % | |
Cash and Restricted Cash (2) | 71,173 | 58,059 | 23 % | |
Shareholders | ||||
Earnings (Loss) per Share – basic | 0.01 | 0.01 | NM | |
Earnings (Loss) per Share – diluted | (0.00) | 0.01 | NM | |
(1,2) See footnotes (1, 2) on first page. |
Third Quarter 2023 Financial & Operational Highlights
Q3-2023 Operations Review
In Q3-2023, the Zgounder operations team focused on the ramp-up of the open pit, which reached 409 tpd of ore in September 2023. Underground production was steady, and mining production for the quarter averaged 1,446 tpd, for a total of 132,998t of ore.
The 1,950m underground level is now fully operational, and access to the 1,925m level was completed during the quarter. The open pit is now in full production and will be further ramped up after the mill is operational.
In Q3-2023, 70,258t of ore were processed, adding over 63kt of ore to inventory, in line with the 2024 commissioning plan. Steady throughput, recovery and availability of both plants resulted in total silver production of 519,085 oz. Combined silver recovery was 86.6%, while combined mill availability reached 93.7%. The mill feed grade averaged 261 g/t Ag in the quarter.
The quarter also saw commencement of an intensive training program for the mine rescue and emergency response team. By Q1-2024, Zgounder is expected to have a significantly improved response capacity and to be fully operational by Q3-2024. Year to date, the training hours at Zgounder, which have more than doubled every year since 2021, totaled over 7,800 as of quarter-end.
Zgounder Development
On February 22, 2022, the Corporation completed a feasibility study to expand the Zgounder Silver Mine from 700 tpd to 2,700 tpd capacity. At the end of Q3-2023, construction of the plant and surface infrastructure continued to track budget. Overall, the expansion project was 60% complete, compared to 45% at last quarter-end.
At the end of Q3-2023, construction of the processing plant was halfway through, with detailed engineering near-complete and procurement well advanced. Several long-lead items were delivered on site in Q3-2023, including the ball mill, thickener steel structures, the intensive leach reactors, and the crusher circuit equipment. Installation of the leach reactors also commenced.
Underground development progressed to plan in Q3-2023. Over 7,145m of lateral and ramp accesses have now been completed since January 2022, representing 76% of the planned lateral infrastructure. Most levels between 1,925m and 2,100m are now connected to the underground ramp. The main ventilation was also commissioned. To date, two of the three ore chutes have been completed, and the second ventilation shaft has begun. In June 2023, the open pit contractor was mobilized, open pit operations commenced, and ore was mined as planned. Overall, open pit and underground mine development were 65% completed.
At quarter-end, construction of the tailing storage facility was progressing well and was 86% complete. The two water storage basins were 100% completed. Other infrastructures, such as the camp, roads, workshops, and warehouses, were 55% completed. Furthermore, the powerline and electrical substations progressed to 48% completion.
At the end of Q3-2023, $138 million had been committed across all capital cost categories, and $91 million had been incurred. The Aya project team continues to remain confident of completing the project within the original budget of $159 million including contingency.
The table below presents construction progress by main project area:
Area | Progress |
Process Plant | 50 % |
Underground and Open-Pit Mines | 65 % |
Tailings | 86 % |
Water Management | 91 % |
Electrical Infrastructure | 48 % |
On-site Infrastructure | 60 % |
Q3-2023 Exploration
Zgounder
A total of 4,675m of DDH was completed on the near-mine permits in Q3-2023, of which 2,219m were completed by two rigs from surface. Two underground drill rigs were also mobilized in the quarter, conducting a total of 2,456m of DDH laterally and at depth. The underground program has been designed to explore the down-plunge potential of the Zgounder mineralized system toward the granite, to extend known mineralization, and to expand mineral resources.
The open-pit area near the east continued to return high-grade results in the quarter including ZG-RC-23-2230-212, which intercepted 2,812 g/t Ag over 8m; ZG-RC-CT7-P63-23-63, which intercepted 2,227 g/t Ag over 7.0m; and ZG-RC-C3-23-25 which intercepted 480 g/t Ag over 17m.
In the quarter, the 2023 drill program on Zgounder was expanded by 3,000m to 29,000m. The additional program will follow up early 2023 surface results east of the deposit and the reverse-circulation (“RC”) results in the southern part of the open pit.
Zgounder Regional
In Q3-2023, 1,923m of DDH were drilled on Zgounder Regional, including 830m on the Tourchkal area. One drill rig is currently active at Zgounder Regional as part of its 2023 expanded drill program, which now totals 14,000m.
The additional 7,300m in the 2023 regional program will be used to test the potential continuation of the Zgounder deposit east of the granophyre; to test the southern contact of the rhyolite; and to test a new target in the Tourchkal area showing silver grab samples and stream anomalies
Four new permits located about 25km east of Zgounder were acquired during the period as part of a reallocation of exploration permits by the Moroccan Directorate of Mines. As a result, the total Zgounder land package now totals 425 km².
Boumadine
Following successful completion of the initial program in July, the 2023 drill program on Boumadine was more than doubled to total 76,000m DDH.
As a result, six drill rigs were mobilized on the Boumadine property through Q3-2023 with the aim of conducting infill and exploring along strike including on new targets. In mid-September, drilling results were released, extending the main trend mineralization by 400m to 4.2km to the south with BOU-DD23-143, BOU-DD23-161 and BOU-DD23-168 demonstrating continuity.
The north area returned high-grade intersections, which expand the mineralization both at depth and to the north, with section 5400N to the south also extending Boumadine Main trend. At quarter-end, the drilling program was 69% complete and on track for completion in December 2023.
In parallel, the Corporation announced acquisition of a 16 km² exploration permit east of Boumadine as part of a reallocation of exploration permits by the Moroccan Directorate of Mines.
The technical information relating to Zgounder, Zgounder Regional and Boumadine properties was reviewed and approved by David Lalonde, B. Sc, Head of Exploration, designated as a Qualified Person under National Instrument 43-101.
About Aya Gold & Silver Inc.
Aya Gold & Silver Inc. is a rapidly growing, Canada-based silver producer with operations in the Kingdom of Morocco.
The only TSX-listed pure silver mining company, Aya operates the high-grade Zgounder Silver Mine and is exploring its properties along the prospective South-Atlas Fault, several of which have hosted past-producing mines and historical resources. Aya’s Moroccan mining assets are complemented by its Tijirit Gold Project in Mauritania, which is being advanced to feasibility.
Aya’s management team is focused on maximising shareholder value by anchoring sustainability at the heart of its operations, governance, and financial growth plans.
Figure 1 – Erection of the leach tank structural steel at the new Zgounder processing plant (CNW Group/Aya Gold & Silver Inc)
First Phosphate Corp. (CSE: PHOS) (OTCQB: FRSPF) (FSE: KD0) is pl... READ MORE
Further to its news release of December 18, 2024, Canadian Gold R... READ MORE
West Red Lake Gold Mines Ltd. (TSX-V: WRLG) (OTCQB: WRLGF) is ple... READ MORE
i-80 GOLD CORP. (TSX: IAU) (NYSE American: IAUX) announces that p... READ MORE
Orion Mine Finance announced today that OMF Fund IV SPV G LLC, a ... READ MORE