Oroco Resource Corporation. (TSX-V: OCO) (OTCQB: ORRCF) (BF: OR6) is pleased to announce a revised Preliminary Economic Assessment and updated Mineral Resource Estimate) for the North Zone and South Zone of its Santo Tomas Porphyry Copper Project in Sinaloa State, Mexico. The PEA is based on a staged open pit mine and processing plant achieving 60,000 tonnes per day production in year 1 and expanding to 120,000 t/d in year 8 over a 22.6-year Life of Mine. Production is preceded by two years of construction and one concurrent year of pre-stripping. The PEA has been prepared by Ausenco Engineering USA South Inc. The updated MRE and geologic model were prepared by SRK Consulting (U.S.), Inc. of Denver, Colorado and SRK Consulting (Canada) Inc., Vancouver, BC. SRK (Canada) was responsible for geotechnical modeling. The mine planning and mine costs components of the PEA were prepared by SRK (U.S.).
Highlights of the revised PEA include:
Commenting on the updated PEA, CEO Richard Lock:
“When we completed the initial PEA in December 2023 it was clear there was additional value to be unlocked at Santo Tomas. Upon careful analysis, a staged approach to the mine expansion and a focus on exploiting the higher-grade near surface material in the early years of mining has unlocked a considerable increase in value. We have established a plan that invokes a very efficient use of capital and establishes a rapid post-tax payback of 3.8 years. The plan starts with the use of smaller equipment to provide rapid entry to the mineralized material and maintains a higher-grade feed profile to delay the requirement of an expansion until year 8. Copper Equivalent production in the first 7 years is forecast at 1.34 billion pounds at a Mill Feed average grade of 0.51% Cu Eq.
Quite significantly, this work establishes Santo Tomas as one of the most capital efficient large-scale, low-cost copper projects in the world as illustrated in Figure 1 below.
Figure 1: Santo Tomas Displays Strong Economics Compared to its Peers
Source/Notes:
FactSet. Technical reports (1) Copper equivalent production calculated using stated metal prices from each project’s latest technical report (After-Tax NPV 8% / Total Capex (US$M). Bubble size based on annual production). The above chart is for illustration purposes only and presents an abstract and simplified view of the NPV based on published data. The other projects presented may not take into account individual risk profiles of each deposit depicted and may not be contemporaneous with the current NPV of the Santo Tomas update. See important metal price and study date information for projects depicted above on Oroco’s website.
PEA Overview
The Santo Tomas property comprises 9,034 ha of mineral concessions encompassing significant porphyry copper mineralization in northern Sinaloa and southwest Chihuahua, Mexico. The Project is located in the Santo Tomas Porphyry District, which extends from Santo Tomas northward to the Jinchuan Group’s Bahuerachi Project located approximately 14 km to the north-northeast. The PEA was conducted using data (including 27,382 Cu assays) from 68 diamond drill holes (43,063 m) drilled by the Company and 90 legacy reverse circulation and diamond drill holes (21,075 m, for a total of 64,138 m in 158 drill holes) in the Project’s North Zone and South Zone. The data from the seven exploration diamond drill holes in Brasiles Zone and the single geotechnical hole (GT001) drilled by the Company were excluded from consideration in the MRE and PEA. Oroco’s entire updated drill hole database (including PEA excluded holes) contains 166 new and legacy drill holes totaling 69,556 m with lithological logging data and 29,992 Cu assays.
The commodity price assumptions for the Discounted Cash Flow analysis are presented in Table 1. Key results from the DCF analysis prepared by Ausenco are presented in Tables 2 & 3.
Table 1: DCF Price Assumptions
Commodity | Unit | Price* |
Cu | US $ / lb | 4.00 |
Mo | US $ / lb | 15.00 |
Au | US $ / t.oz | 1,900 |
Ag | US $ / t.oz | 24.00 |
*Cash flow model assumptions only.
Cautionary Note to Investors
The reader is cautioned that the PEA is preliminary in nature, and that it includes inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves, and there is no certainty that the preliminary economic assessment will be realized.
Table 2: Mining and Production – Key Results
Key Assumptions | Unit | LOM |
Exchange Rate | MXN / US$ | 19.76 |
Fuel Price | MXN / L | 20.41 (US$1.03) |
Production Profile | Unit | LOM |
Total Open Pit Tonnage | Mt | 1,964.9 |
Total Open Pit Mineralized Material Mined | Mt | 825.5 |
Open Pit Strip Ratio | Waste : mill feed | 1.38 |
Daily Throughput (Year 1 // Year 8 on) | kt/d | 60 // 120 |
LOM (concentrate production) | Years | 22.6 |
Copper in Mill Feed | M lb | 5,916 |
Molybdenum in Mill Feed | M lb | 138.7 |
Gold in Mill Feed | koz | 753.4 |
Silver in Mill Feed | koz | 55,200 |
LOM mill feed (Indicated // Inferred) | Mt | 388 // 460 |
Average Cu payable / year – LOM | M lb | 207.5 |
Average Cu payable / year – First 5 Years (1) | M lb | 167.5 |
Payable (2) Copper LOM (in concentrate) | M lb | 4,774 |
Payable Molybdenum LOM (in concentrate) | M lb | 80.8 |
Payable Silver LOM (min 30 g/t payable in Cu Concentrate) | koz | 26,673 |
Payable Gold LOM (min 1 g/t payable in Cu Concentrate) | koz | 300.2 |
Operating Costs (US$/lb.) | Unit | LOM |
C1 Cash Costs Copper (By-Product Basis) (3) | US$/lb | 1.54 |
C3 Cash Costs Copper (By-Product Basis) (4) | US$/lb | 2.00 |
Capital Expenditures (5) | Unit | LOM |
Initial Capital (6) | US$M | 1,103.5 |
Sustaining and Expansion Capital (6, 7) | US$M | 1,734.1 |
Closure Costs (5 years, year 22 – 27) | US$M | 209.2 |
Estimated Salvage Value | US$M | 0 |
Notes: (1) First 5 Years at full production, starting year 2. (2) Payable metals consider mining dilution, concentrator recoveries and Treatment Charges/Refining Charges (TC/RC). (3) C1 Cash Costs consist of mining costs, processing costs, mine-level G&A and transportation costs net of by-product credits. (4) C3 Cash Costs includes C1 Cash Costs plus sustaining and expansion capital, royalties, and closure costs. (5) All capital expenditures are inclusive of contingency provisions to allow for uncertain cost elements, which are predicted to occur but are not included in the cost estimate. (6) Net of leasing capital deferment and leasing costs. (7) Sum of expansion and sustaining capital.
Table 3: Key Financial Results and Costs
Economics | Unit | LOM |
IRR (pre-tax // post-tax) | % | 30.3 // 22.2 |
Payback (pre-tax // post-tax) | Years | 2.9 // 3.8 |
Revenue over LOM | US$M | 21,517 |
Initial Capital | ||
Mining Pre-Stripping (Capitalized OPEX) | US$M | 75.5 |
Mining Capital Equipment (1) | US$M | 89.4 |
Total Mining (1) | US$M | 164.9 |
Processing | US$M | 938.7 |
Total Initial Capital (1) | US$M | 1,103.6 |
Sustaining Capital | ||
Mining Equipment | US$M | 952.4 |
Processing | US$M | 94.6 |
Total Sustaining Capital | US$M | 1,047.0 |
Expansion Capital – Processing (year 7) | US$M | 687.2 |
Average LOM Operating Costs | ||
Mining Cost per tonne mined (2) | US$ / t | 2.04 |
Mining Cost per tonne milled (2) | US$ / t | 4.78 |
Mining Equipment Leasing Cost per tonne milled | US$ / t | 0.06 |
Processing Cost per tonne milled | US$ / t | 4.04 |
G&A Cost per tonne milled | US$ / t | 0.65 |
Total Operating Cost per tonne milled (2) | US$ / t | 9.53 |
Notes: (1) Includes leasing costs and deferral of capital associated with lease payments. Supplier-sourced leasing terms from October 2023 are used in the mine fleet cost calculations that include a 5-year lease period with 10.3% interest, 0.5% upfront fee, and no residual payment. (2) Excludes leasing costs.
Economic Sensitivities
Project economics and cash flows are most sensitive to changes in the price of copper (Figure 2) providing the highest potential for change in economics. However, mined grade and recovery sensitivity are also high and future studies will seek to optimize these parameters.
Figure 2: Post-Tax NPV and IRR Sensitivity Plots
Source: Ausenco 2024
Mineral Resource Estimate
The MRE was prepared in accordance with the Canadian Institute of Mining, Metallurgy, and Petroleum Definition Standards incorporated by reference in National Instrument 43-101, with an effective date of July 23, 2024. The Technical Report will be released by the Company and available at www.orocoresourcecorp.com and on SEDAR (www.sedarplus.ca) under the Company’s profile shortly.
The MRE includes the two primary mineralization zones identified at Santo Tomas: North Zone and South Zone. These zones display similar mineralization styles but are physically separated by localized post-mineralization faults and material currently defined as waste due to a lack of drilling. Consistent with the previous study, the MRE is not constrained by the location of the Huites Reservoir. Mineral resources are reported above an effective cut-off grade (CoG) of 0.15% Cu and constrained by an economic pit shell (see Table 4).
Table 4: Mineral Resource Statement for the Santo Tomas Project, effective July 23, 2024.
Category | Zone | Tonnes Mt | Average Grade | In-situ Metal3 | ||||||||||
CuEq10 | Cu | Mo | Au | Ag | CuEq10 | Cu 11 | Mo 11 | Au 11 | Ag 11 | |||||
% | % | % | g/t | g/t | M lb | M lb | M lb | koz | koz | |||||
Indicated | North Zone pit – sulphide | 540.6 | 0.37 | 0.33 | 0.008 | 0.028 | 2.1 | 4,465 | 3,976 | 95.4 | 483.4 | 36,524 | ||
Total Indicated | 540.6 | 0.37 | 0.33 | 0.008 | 0.028 | 2.1 | 4,465 | 3,976 | 95.4 | 483.4 | 36,524 | |||
Inferred | North Zone pit – sulphide | 90.0 | 0.34 | 0.31 | 0.005 | 0.021 | 1.7 | 679 | 620 | 10.2 | 61.4 | 4,949 | ||
North Zone pit – oxide | 4.4 | 0.31 | 0.31 | 0.002 | 0.053 | 1.6 | 29 | 29 | 0.2 | 7.4 | 228 | |||
South Zone pit – sulphide | 399.2 | 0.36 | 0.32 | 0.008 | 0.023 | 2.0 | 3,132 | 2,789 | 71.2 | 294.4 | 26,200 | |||
South Zone pit – oxide | 36.7 | 0.27 | 0.27 | 0.004 | 0.020 | 1.6 | 218 | 218 | 2.8 | 23.8 | 1,851 | |||
Total Inferred | 530.3 | 0.35 | 0.31 | 0.007 | 0.023 | 1.9 | 4,058 | 3,657 | 84.4 | 387.1 | 33,229 |
Notes:
The mineral resource estimation process includes updated structural, lithologic, and mineralization models not materially changed from the previous study, effective April 27, 2023. No additional drilling has been added and the estimation methodology remains unchanged from the methodology used in the. Differences in the MRE shown in Table 4 from the previous MRE are due to: 1) inclusion of oxidized mineralization in the North Zone pit and South Zone pit; and 2) updated economic and pit slope assumptions based on the updated PEA study. The resource estimation methodology involved the following procedures:
SRK undertook the geological modeling and mineral resource estimate using Seequent Leapfrog Geo and Leapfrog Edge, respectively. The procedure involved construction of wireframe models for structural geology controls, key geological and mineralization domains, data conditioning (compositing and capping) for statistical analysis, variography, block modeling and grade interpolation followed by block model validation. Grade was estimated using a combination of ordinary kriging and inverse distance weighting cubed estimates for copper, molybdenum, gold, and silver. Sulfur grades are estimated using inverse distance weighting squared and bulk density is estimated using a combination of simple kriging and IDW2. Grade estimation was based on block dimensions of 50 m x 50 m x 10 m for the PEA model (unchanged from previous studies). The block size reflects current data spacing across the Project while considering a likely open pit mining method. Classification of mineral resources considers the geological complexity (structure, lithology, alteration, and mineralization), spatial continuity of mineralization, data quality, and spatial distribution of drilling conducted at the Project.
The MRE is supported by 64,138 m of drilling in 158 holes. The drilling data represents a combination of holes completed by Oroco from 2021 to 2023 and historical drill holes but excludes drilling at Brasiles Zone (outside current project scope) and one geotechnical hole (due to lack of assay data).
Mineralization has been identified outside the current economic pit shell. The PEA highlights the potential to define additional mineral resources on the property. There is identified exploration potential for additional mineralization in the southeastern and southwestern portions of the South Zone based on observations from drilling and surface outcrops in the area.
Mine Design
The mine design re-worked previous phase designs to increase the number of pit phases from 4 to 20. Initial phases are smaller to reduce waste stripping and allow for faster access to higher grade mill feed, resulting in an average 0.51% CuEq ore grade for the first 7 years of production. These smaller phases have narrower access roads that require the use of small-scale haul trucks (72 t capacity). Later in the mine life, the pit phases are typically larger and will allow for the use of large-scale haul trucks (240 t capacity). Over the life of the project, including the pre-production waste mining year, 80% of the tonnes mined will be with the large-scale equipment fleet.
The final pit design ensures no incursion upon the Huites Reservoir, remaining outside of CONAGUA’s (Mexican water authority) jurisdiction boundary (the “CONAGUA limit”). Slope constraints derived from geotechnical domains were defined from Phase 1 drilling on the Project.
Table 5 shows mineral inventory within the ultimate pit design for this PEA.
Table 5: Pit Constrained Resource
Mill Feed | Waste Material | Strip Ratio | Total Material | |||||
Tonnes (Mt) |
Cu (%) |
Mo (%) |
Au (g/t) |
Ag (g/t) |
CuEq (%) |
Tonnes (Mt) |
Waste/Mill | Tonnes (Mt) |
825.5 | 0.325 | 0.008 | 0.028 | 2.080 | 0.365 | 1,139.4 | 1.38 | 1,964.9 |
The proposed mining method is conventional open pit truck and shovel operation with 10-meter bench intervals. Haul trucks will be used for hauling mineralized material to the crushing plant, long-term stockpile facilities, and waste to the waste rock storage facilities.
The mine production plan contains 825.5 M tonnes of mineralized sulfide material with an average grade of 0.37% CuEq, and 1,139.4 M tonnes of waste material (including mineralized oxide), resulting in a strip ratio of 1.38 over the LOM. CuEq is calculated using the methodology described in the footnotes to Table 4.
Mining operations will be carried out on a 24-hour per day, 365 days per year schedule. Total mined tonnes will start at 27.2M tonnes mined during the pre-stripping year and eventually ramp up to a maximum of 116M tonnes per annum (Mt/a) in Year 13. The Project has a total life of 23.5 years, which includes 1 year of pre-stripping and one final year of stockpile rehandling to the mill. Project expansion (Phase II) starts in Year 8 of operation.
The mining sequence consists of 20 phases (10 in the North Pit and 10 in the South Pit), which vary in minimum mining width according to the type of equipment to be used. Early years focus on mining the North Pit, while transitioning to larger equipment to be used once the South Pit has opened up to wider benches.
Mined tonnes, Mill Feed tonnes and Mineral Inventory classification are shown in Figures 3, 4 and 5.
Figure 3: Mine Production Schedule – Mineralized Material/Waste
Figure 4: Mill Production Schedule
Figure 5: Classification of Mineral Inventory
Process Design & Plant Infrastructure
Recent metallurgical test work results for composite and variability drill core samples from the North and South Zones demonstrated amenability to conventional flotation recovery to produce a marketable copper and molybdenum concentrates (given molybdenum levels observed in the bulk concentrate generated during locked cycle tests). The following key metallurgical parameters applied to develop the process design were:
Mine haul trucks will transport plant feed material to the dump pockets at the semi-mobile primary crushing station which directly feeds into a large gyratory crusher. From the primary crusher, plant feed material will be conveyed through a tunnel to a live stockpile ahead of a processing plant containing a secondary cone and tertiary HPGR crushing circuit. Tertiary crushed product will feed into two twin ball mills in closed circuit with cyclones to produce flotation feed at 80% minus 150 µm. The flotation circuit will produce a bulk rougher concentrate that is subsequently reground to 23 µm P80 prior to cleaner flotation stages to produce a bulk copper-molybdenum concentrate. The bulk cleaner concentrate advances to copper-molybdenum separation to recover a molybdenum concentrate. Gold and silver report to the copper concentrate. Copper and molybdenum concentrates are dewatered prior to shipment in sealed containers to a concentrate storage facility at the Port of Topolobampo for shipment to overseas smelters.
The tailings are dewatered and pumped to a cyclone sands station where coarse tailings report to build the tailings storage facility embankment and fines are deposited within the facility. Water off the TSF is reclaimed and recycled back through the process plant.
Figure 6 is an overall layout of the current project site.
Tailings and Waste Rock Storage Facilities
The storage of waste rock has been optimized and offers the following benefits:
Both the WRSFs and the TSF are designed with ditches and berms to divert stormwater around rather than through these facilities to minimize the volume of contact water requiring additional processing. Contact water filtered through these facilities will be captured and recycled back to the process plant.
Power Infrastructure and Water Supply
The re-designed electrical supply is from a built-for-purpose LNG combustion power plant located adjacent to the El Encino-Topolobampo natural gas pipeline some 33 km from site. This low carbon footprint power source option offers a cost for power lower than the going state rate. A 115 kVA overhead power line replaces the 230 kVA power line providing additional cost savings.
Make-up process water supply is now sourced from groundwater wells situated along the northern boundary of the North Pit. This arrangement offers two key benefits not realized in the October PEA:
Geology and Mineralization
Porphyry Cu (Mo‐Au‐Ag) mineralization on the Santo Tomas property is closely associated with intrusives linked to the Late Cretaceous to Paleocene (90 to 40 Ma) Laramide orogeny. Santo Tomas and most of the known porphyry copper deposits in Mexico lie along a 1,500 km‐long, NNW trending belt sub-parallel to the west coast, extending from the southwestern United States through to the state of Guerrero in Mexico.
In the Santo Tomas area, Mesozoic‐aged country rocks comprising limestone, minor sandstones, conglomerates, shales, and a thick succession of andesitic volcanics were intruded by a range of Laramide age intrusions related to the Late Cretaceous Sinaloa‐Sonora Batholith. Multiple phases are recognized ranging from dioritic to monzonitic in composition.
Mineralization is strongly structurally controlled associated with the Santo Tomas fault and fracture zone, which provided a pathway to quartz monzonite dikes, associated hydrothermal alteration, hydrothermal breccias, and sulfide mineralization. Sulfide minerals are dominated by chalcopyrite, pyrite and molybdenite with minor bornite, covellite, and chalcocite. Sulfides occur as fracture fillings, veinlets, and fine disseminations together with potassium feldspar, quartz, calcite, chlorite, and locally, tourmaline. Chalcopyrite is the main copper mineral with minor copper oxides near surface.
Community & Environmental
Oroco continues to engage with the local community on education, ongoing employment and other opportunities as they present themselves. Oroco strives to maintain transparent communications with local communities and public authorities at all levels to ensure that key stakeholders are aware of the project status and plans including responding to community concerns and requests in a timely and genuine manner. Oroco maintains its exploration permits and approvals in good standing.
Further environmental baseline studies and other socio-economic, cultural, and community engagements are planned for future EIS preparation and permitting.
Project Enhancement Opportunities
Several further opportunities to improve the Project have been identified during the revised PEA Study. These include but are not limited to:
A geological-geochemical conceptual model will inform the ongoing development and refinement of geochemical and mine rock management plan for the site. The predicted occurrence of large volumes of net neutralizing mine waste materials to be mined in early years will be confirmed, as the buffering characteristics of these waste materials can be effectively utilized as part of the overall waste rock management strategy. Additional geochemical assessment of the acid rock drainage / metal leaching risk for the Project will be implemented to provide additional test work and sampling coverage, and to confirm preliminary study findings.
Cautionary Notes to Investors
PEA
The reader is cautioned that the PEA is preliminary in nature, and that it includes inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves, and there is no certainty that the preliminary economic assessment will be realized.
Mineral Resource and Reserve Estimates
In accordance with applicable Canadian securities laws, all Mineral Resource estimates of the Company disclosed or referenced in this news release have been prepared in accordance with the disclosure standards of NI 43-101 and have been classified in accordance with the CIM Standards. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. No Mineral Reserves have been estimated for the Project. The estimate of mineral resources may be materially affected by environmental, permitting, legal, title, socio-political, marketing, or other relevant issues. In particular, the quantity and grade of reported inferred mineral resources are uncertain in nature and there has been insufficient exploration to define these inferred mineral resources as an indicated or measured mineral resource. It is uncertain in all cases whether further exploration will result in upgrading the inferred mineral resources to an indicated or measured mineral resource category.
Qualified Persons
The updated PEA for the Project summarized in this news release was prepared by Ausenco with input from SRK and has been incorporated in a technical report prepared in accordance with NI 43-101 which will be available under the Company’s SEDAR profile at www.sedarplus.ca and on the Company’s website. The affiliation and areas of responsibility for each of the Qualified Persons involved in preparing the PEA, upon which the technical report will be based, are as follows:
Table 6: Qualified Persons for PEA
Qualified Persons | Qualification | Company (location) | Position / Oversight |
James Arthur Norine | P.E. | Ausenco Engineering USA South Inc. | Vice President, Southwest USA |
Peter Mehrfert | P. Eng. | Ausenco Engineering Canada ULC | Principal Process Engineer |
James Millard | M. Sc., P. Geo. | Ausenco Sustainability ULC | Director, Strategic Projects |
Scott C. Elfen | P.E. | Ausenco Sustainability ULC | Global Lead Geotechnical Services |
Andy Thomas | M. Eng., P.Eng. | SRK Consulting (Canada), Inc. | Principal Rock Mechanics Engineer |
Fernando Rodrigues | BS Mining, MBA, MMSAQP | SRK Consulting (U.S.), Inc. | Practice Leader, Principal Consultant (Mine Plan, Mining CAPEX + OPEX) |
Ron Uken | PhD, PrSciNat |
SRK Consulting (Canada), Inc. | Principal Structural Geologist |
Scott Burkett | RM-SME B.Sc. Geology | SRK Consulting (U.S.), Inc. | Principal Consultant (Resource Geology) |
Each QP listed in Table 6 has reviewed and verified the content of this news release.
Andrew Ware, RM SME and QP for Oroco has reviewed and verified the contents of this news release and has approved the document for public release.
About OROCO
The Company holds a net 85.5% interest in those central concessions that comprise 1,173 hectares “the Core Concessions” of The Santo Tomas Project, located in northwestern Mexico. The Company also holds an 80% interest in an additional 7,861 hectares of mineral concessions surrounding and adjacent to the Core Concessions (for a total Project area of 9,034 hectares, or 22,324 acres). The Project is situated within the Santo Tomas District, which extends up to the Jinchuan Group’s Bahuerachi Project, approximately 14 km to the northeast. The Project hosts significant copper porphyry mineralization defined by prior exploration spanning the period from 1968 to 1994. During that time, the Project area was tested by over 100 diamond and reverse circulation drill holes, totalling approximately 30,000 meters. Commencing in 2021, Oroco conducted a drill program (Phase 1) at Santo Tomas, with a resulting total of 48,481 meters drilled in 76 diamond drill holes.
The drilling and subsequent resource estimates and engineering studies led to an initial MRE publication (May 2023) with a PEA (including an updated MRE) being published and filed in late 2023, with the current update work being undertaken in 2024. The MRE released with the initial PEA in late 2023 included an Updated Mineral Resource for the North and South Zones of the Santo Tomas Project, identifying Indicated and Inferred resources of 561 Mt @ 0.37% CuEq and 549 Mt @ 0.34% CuEq, respectively. The revised PEA includes a further Updated Mineral Resource for the North and South Zones of the Santo Tomas Project, identifying Indicated and Inferred resources of 540.6 Mt @ 0.37% CuEq and 530.3 Mt @ 0.35% CuEq, respectively.
The Project is located within 170 km of the Pacific deep-water port at Topolobampo and is serviced via highway and proximal rail (and parallel corridors of trunk grid power lines and natural gas) through the city of Los Mochis to the northern city of Choix. The property is reached, in part, by a 32 km access road originally built to service Goldcorp’s El Sauzal Mine in Chihuahua State.
Red Pine Exploration Inc. (TSX-V: RPX) (OTCQB: RDEXF) is pleased ... READ MORE
F3 Uranium Corp. (TSX-V: FUU) (OTC Pink: FUUFF) is pleased to ann... READ MORE
Collective Mining Ltd. (NYSE: CNL) (TSX: CNL) is pleased to ann... READ MORE
Aris Mining Corporation (TSX: ARIS) (NYSE-A: ARMN) announces t... READ MORE
Staffing in place and operations shakedown underway Rare E... READ MORE