Eldorado Gold Corporation (TSX: ELD) (NYSE: EGO) is pleased to announce that first copper-gold concentrate has been produced at its wholly owned Skouries Project in northern Greece, marking a significant milestone in the transition of the project from construction to operations and a major step toward commercial production which is expected to be achieved in the fourth quarter of 2026.
First concentrate was produced on September 8 as part of the ongoing commissioning and ramp-up of the processing plant. This milestone follows the introduction of first ore to the crusher in July and reflects the successful commissioning of key process plant systems, including crushing, grinding, flotation and tailings thickening circuits. The ore stockpile currently exceeds 4.6 million tonnes above reserve grade, providing a strong foundation for ramp-up and underpinning more than seven months of processing throughput and concentrate production.
“This is a defining moment for Eldorado,” said George Burns, Chief Executive Officer. “First concentrate at Skouries represents the culmination of years of development, construction and partnership and marks the beginning of a new chapter for our Company. Skouries is not only a transformational asset for Eldorado, but also one of the most significant investments in Greece and one of Europe’s largest copper-gold projects. Together with McIlvenna Bay in Saskatchewan, Skouries is expected to transform Eldorado into a larger, more diversified precious metals and critical minerals producer with a stronger production base, meaningful copper and silver exposure and enhanced free cash flow generation. We are proud of what has been accomplished through our partnership with the Greek government and banks, local communities, our workforce and other stakeholders, and we look forward to creating long-term value and benefits for Greece and all stakeholders for decades to come.”
Key infrastructure commissioning has steadily progressed with crushing, grinding, flotation, tailings thickening, and concentrate thickening systems operating successfully. Temporary on-site power generation continues to support early operations and ramp-up until connection to the national power grid is achieved, which remains subject to final inspections, testing and installation of metering equipment by the Greek transmission authority and is expected in September 2026.

Stockpile dome and process plant

Semi-autonomous grinding mill (SAG) & Ball mill

Flotation cells and regrind mill (in the foreground)
Skouries is expected to produce on average 140,000 ounces of gold and 67 million pounds of copper annually over the life of mine.
Multimedia
https://eldoradogold.getbynder.com/web/18d252a9d9d595a6/september-2026-project-progress/
Qualified Person
Simon Hille, FAusIMM, Executive Vice President, Chief Operating Officer, is the Qualified Person under National Instrument 43-101 responsible for preparing and supervising the preparation of the scientific or technical information contained in this news release and for verifying the technical data disclosed in this document relating to Skouries.
About Eldorado Gold
Eldorado is a gold, copper and base metals producer with mining, development and exploration operations in Canada, Türkiye, and Greece. The Company has a highly skilled and dedicated workforce, safe and responsible operations, a portfolio of high-quality assets, and long-term partnerships with local communities.
K2 Gold Corporation (TSX-V: KTO) (OTCQX: KTGDF) (FSE: 23K) announ... READ MORE
Highlights Assay results reported for 15 drill holes comprising... READ MORE
Also reports 1,323.20 m of 0.50% CuEq1, including 555 m of 0.71... READ MORE
High-grade orogenic quartz-tourmaline veins encountered within a ... READ MORE
Resource-conversion and resource-addition drilling returned multi... READ MORE