Uranium Energy Corp (NYSE American: UEC) is pleased to report the filing of an initial assessment technical report summary that includes an economic analysis and mineral resource estimate for its 100% owned Roughrider Project, located in Northern Saskatchewan, Canada. All currency references are in United States dollars.

Amir Adnani, President, and CEO stated: “This Initial Economic Assessment marks a pivotal milestone for Roughrider, validating it as a top-tier, high-margin operation with a clear path to development into a world-class mine and mill. With a post-tax estimated net present value of $946 million, today’s results underscore the strength of our 2022 decision to acquire Roughrider from Rio Tinto for $150 million, consistent with our strategy to acquire accretive assets at opportune points in the uranium price cycle.

Key competitive advantages that position Roughrider as an elite underground development project include: 

  1. high grade operation with 2.36% U3O8 Life of Mine feed grade, 
  2. one of the lowest capex profiles in Canada and
  3. location in the Eastern Athabasca Basin, where future development will benefit from proximity to power, roads, and the Points North Landing airport and construction facility.

Additionally, we see significant potential for further value creation as we advance the project through the prefeasibility stage, supported by recent exploration drill results and the discovery of the Roughrider North Deposit.

Roughrider is poised to benefit from uranium and nuclear energy’s growing prominence to address North America’s rising electricity demand for safe, reliable, economic, and clean energy sources. Given UEC’s capabilities as an established uranium producer, we are uniquely positioned to leverage our operational expertise and financial strength to advance and de-risk Roughrider, maximizing value for our shareholders, stakeholders, and rightsholders.”

Key Highlights:

  • Estimated post-tax NPV8 of $946 million, IRR of 40%, post-tax payback period of 1.4 years based on a long-term uranium price of $85/lb U3O8 and utilizing an 8% discount rate (NPV 8%), Table 1.
  • Expected Life of Mine production of 61.2 million lbs U3O8 produced over nine years with an average annual production rate of 6.8 million lbs U3O8. Initial capex estimated at $545 million including mill and underground mine. See Table 2.
  • AISC of $20.48/lb U3O8. See Table 3.
  • Average Annual LOM earnings before interest, taxes, depreciation and amortization of $395 million. See Table 4.
  • The Roughrider Project is in the well-established infrastructure of eastern Athabasca Basin, with an adjacent high-voltage 138 kV transmission line, hydroelectric power generation, 7 km north of the commercial airport at Points North Landing, and highway system. See Figure 4.

The economic analysis is included in a technical report summary titled “S-K 1300 Initial Assessment Report – Roughrider Uranium Project, Saskatchewan, Canada” issued on November 5, 2024 and prepared for UEC by Tetra Tech Canada Inc., Understood Mineral Resources Ltd., Snowden Optiro, Terracon Geotechnique Ltd. and Clifton Engineering Group Inc.; in accordance with Item 1302 of SEC Regulation S-K 1300 a copy of which is available under UEC’s profile at www.sec.gov (the “Technical Report Summary”). The Technical Report Summary has now been filed through EDGAR on Form 8-K and is also available as a Material Document on SEDARplus. The economic analysis included therein and summarized in this news release is preliminary in nature and includes inferred mineral resources that are considered too speculative geologically to have modifying factors applied to them that would enable them to be categorized as mineral reserves, and there is no certainty that this economic assessment will be realized.

Table 1. Base Case Financial Highlights

Base Case Financials 
Pre-Tax Cash Flow (undiscounted) ($ millions) $3,366
Pre-Tax NPV8 ($ millions) $1,629
Pre-Tax IRR % 53 %
Pre-Tax Payback Period Years 1.2
Post-Tax Cash Flow ($ millions) $2,040
Post-Tax NPV8 ($ millions) $946
Post-Tax IRR % 40 %
Post-Tax Payback Period Years 1.4

The base case reflected in the analysis assumes, among other things, an $85/lb U3O8 uranium price, an exchange rate of 0.75 United States dollars to Canadian dollars, and that all costs are in Q4 2024 dollars with no inflation applied. For further information regarding the impact of excluding such inferred mineral resources from the analysis, please refer to the Technical Report Summary.

Table 2. Key Physical Highlights 

Initial Assessment Report Physical Highlights
Avg. LOM Annual Production M lbs U3O8 6.8
LOM Production M lbs U3O8 61.2
Mine Life Years 9
Mill Processing rate tonnes / day 400
Underground peak mining rate tonnes / day 818
LOM tonnes processed tonnes 1,205,000
LOM Avg. Head Grade %U3O8 2.36
Process Recovery % 97.5

 

Table 3. Cost Summary

Initial Assessment Report Financial Highlights*
Mining $ / lb U3O8 $3.25
Processing $ / lb U3O8 $4.30
Surface and G&A $ / lb U3O8 $2.18
Average LOM Operating Cost $ / lb U3O8 $9.72
Royalties $ / lb U3O8 $7.84
Offsite Charges $ / lb U3O8 $0.28
Sustaining Capital + Closure $ / lb U3O8 $2.64
All in Sustaining Costs (AISC) $ / lb U3O8 $20.48
*Note: totals may not add due to rounding.

 

Table 4. Sensitivity to Uranium Price 

Roughrider Project Financial Estimates based on Uranium Price
Uranium Price
($ / lb U3O8)
After-Tax NPV8 After-Tax IRR Annual Average
EBITDA ($)
$ 150 / lb U3O8  $ 2.1 Billion 64 %  $ 730 Million
$ 100 / lb U3O8  $ 1.2 Billion 46 %  $ 473 Million
$ 90 / lb U3O8  $ 1.0 Billion 42 %  $ 421 Million
$ 85 / lb U3O8  $ 0.9 Billion  40 %  $ 395 Million 
$ 50 / lb U3O8  $ 0.3 Billion 21 %  $ 215 Million

 

Mine Plan

The initial economic assessment envisions that the Roughrider deposit will be mined using the longhole stoping method utilizing retreat mining in a transverse stope orientation with various orientations between the three main mineralized zones. Various underground mining methods were considered; however, longhole stoping was ultimately selected to reduce cost. Development will be located to the south of the deposits and will be accessed using a ramp decline which will also be the primary source of fresh air ventilation. Exhaust shafts will be used to ventilate the mine.

Ground freezing will be used to control water inflows into the main decline to a depth below the unconformity as well as into the three mining zones. Freeze wells will be installed from surface around the perimeter of each zone with active freezing starting at least 12 months prior to mining. Figure 1 was generated by UEC as a conceptual image of the conventional underground mine. Further details of proposed mining and milling methods are set out in the Technical Report Summary.

Figure 1 Roughrider Project Conventional Mine Schematic (CNW Group/Uranium Energy Corp)

The initial construction focus is on the development of the decline, ventilation and secondary egress from surface (red to yellow). Once the decline reaches the deposit, initial focus will be on the Roughrider West deposit with the decline held while levels and ventilation are developed in this area (green). Mining then progresses to the Roughrider East deposit (cyan) and finally Roughrider Far East deposit (blue). See Figure 2.

Figure 2. Isometric View of the Mining Sequence (CNW Group/Uranium Energy Corp)

Mill, Processing and Tailings Design

The processing facility incorporated in the initial economic assessment is designed using established methods from other Athabascaoperations, such as Rabbit Lake, Key Lake and McClean Lake. It will operate at a nominal throughput of 400 t/d with an LOM average mill feed grade of 2.36% U3O8 and a recovery rate of 97.5%. LOM average annual production of yellowcake product is expected to be about 3.08 million kg (6.80 million lbs) at 95% U3O8. See Table 5 for the key processing parameters and Figure 3 for the recovered uranium LOM plan.

Table 5. Mill Processing Parameters

Key Processing Data
Mill Processing Rate tonnes / day 400
LOM tonnes Processed tonnes 1,205,000
LOM Average Head Grade %U3O8 2.36
LOM Feed M lbs U3O8 62.7
Process Recovery % 97.5
LOM Recovered M lbs U3O8 61.2

Figure 3. Roughrider Project Recovered Uranium and Head Grade (CNW Group/Uranium Energy Corp)

 

Based on prior metallurgical test work, the following conclusions can be made:

  • The comminution test work showed that Roughrider samples are soft in nature with an average Bond Ball Mill Work Index of 10.6 kWh/t.
  • Agitated tank leach test results showed that Roughrider mineralization is amenable for uranium extraction via atmospheric acid leaching. On average 98.5% of extraction can be achieved within 12 hours of leach retention time at 50°C with a grind size of 250 µm. Further, it was found that there was no significant difference in dissolution and extraction of uranium from the different deposits (RRW, RRE and RRFE).
  • Two different approaches (strong acid strip with uranyl peroxide precipitation and ammonia strip with ammonium diuranate precipitation) were examined for production of final yellowcake product. It was found that organic extraction followed by strong acid strip produced higher quality yellowcake meeting refinery specifications compared to the ammonium sulfate strip method.
  • Tailings neutralization and effluent treatment test work based on the standard approaches used in the Athabasca region indicated that effluent quality meeting the MDMER guidelines can be achieved.

The Technical Report Summary provides for the construction of a tailing management facility to store the uranium tailings produced from processing. The TMF will be located approximately one km northeast of the proposed processing plant on gently sloping terrain. Thickened slurry tailings will be deposited into three adjacent storage cells sequentially constructed over the LOM. The design incorporates a double liner seepage containment system and a ‘pervious surround’ rock filter. This approach will allow for staged TMF cell construction and progressive reclamation. Containment will be enhanced by construction of a filter rock drain system used successfully at other uranium operations and identified as the ‘pervious surround’ approach. The storage of tailings solids below grade will reduce risk and promote secure physical containment.

At closure, the water cover will be pumped out of the cell and a cover of soil and geomembrane layers will be placed over the tailings surface. With the multi-cell design, it will be possible to progressively reclaim the TMF storage cells during the operational phase.

 

Capital Expenditure

The capital and operating cost estimates are based on a 400 t/d processing throughput. The cost was estimated based on the mine plan and process flowsheet. All costs are reported in US dollars and the Association for the Advancement of Cost Engineering Class 5 initial capital cost estimate has been prepared in accordance with the standards of AACE International. The accuracy range of the initial capital cost estimate is ±50%. This estimate was prepared with a base date of the fourth quarter of 2024. See Table 6 for summary of total initial capital cost.

Table 6. Estimated Capital Cost Summary

Capital Cost Area Value ($ million)
Mining 96.8
Processing Plant 89.5
Infrastructure 80.1
Tailings and Waste Rock Management 19.0
Direct Cost 285.4
Indirect Cost* 99.9
Owner’s Cost 60.2
Contingency 99.9
Total Initial Capital Cost 545.5
Pre-production Cost 35.6
Total Initial Capital Cost (inc. pre-production) 581.1

Note: Totals may not add due to rounding.

*Includes EPCM cost of $34.0 million.

 

Next Steps, Licensing and Permitting

UEC continues to advance the Roughrider Project through technical and environmental studies, community engagement and assessing opportunities to further de-risk the project. The parallel processes of updating the environmental baseline work and Indigenous engagement will support a future Environmental Impact Assessment required for uranium production. UEC plans to follow-up encouraging exploration results in 2024 with an updated mineral resource estimate on or about the first quarter of 2025 to support the development of a pre-feasibility study in 2025.

Resource Update and Exploration

The 2024 mineral resource estimate that is set out in the Technical Report Summary has been prepared in accordance with the requirements of S-K 1300. To meet the requirement of reasonable prospects of eventual economic extraction, the mineral resource estimate is reported within a constrained mineable shape optimizer as informed by a breakeven cut-off grade of 0.30% U3O8. The mineral resource estimate is reported diluted, including waste and mineralization below cut-off.

The mineral resource estimate set forth in the Technical Report Summary is summarized in Table 7. No Mineral Reserves have been estimated at the project.

Table 7: Mineral Resource Statement for the Project (as of November 5, 2024)

Zone Classification Tonnage (kt)  Grade U3O8 (%)  Contained U3O8
Metal (M lb U3O8)
RRW Indicated 431 1.89 17.97
Inferred 152 2.80 9.39
RRE Indicated
Inferred 390 2.57 22.05
RRFE Indicated 268 1.67 9.89
Inferred 78 1.13 1.94
Total Indicated 699 1.81 27.86
Inferred 620 2.45 33.38

Notes

  1. Reported on a 100% ownership basis.
  2. To establish reasonable prospects of eventual economic extraction, a cut-off grade of 0.30% U3O8 was utilized. Such grade was calculated based on the following criteria and assumptions U3O8price of $85 / lb, transport cost of $0.26 / lb, mining cost of $163 /t, processing cost of $222 / t, G&A cost of $112 / t, royalties of 9.22% / t, and process recovery of 95.5%.
  3. The mineral resource estimate was prepared by Understood Mineral Resources Ltd., one of the independent qualified persons under the Technical Report Summary. The MSO shapes were estimated by Snowden Optiro, one of the independent qualified persons under the Technical Report Summary.
  4. The tonnage is presented in metric tonnes and contained metal is reported in both metric tonnes and imperial pounds. Estimates have been rounded and may not add up due to significant figure rounding.

Since November 2023, UEC has been continuously exploring the Roughrider Property, see January 31, 2024, August 20, 2024 and September 12, 2024 press releases. As of July 31, 2024, a total of 94 drill holes have been completed, for a total of 29,840 m drilled, with the best drill results so far being between the existing West, East and Far East Zones, down dip of the Far East Zone, and the Roughrider North deposit.

For further details of the initial economic assessment and the resource estimate for the Roughrider Project disclosed herein, including important information regarding their underlying assumptions and methodologies, readers should refer to the Technical Report Summary.

About Canada’s Athabasca Basin

The Athabasca Basin is a world-class uranium district in the northern portion of the provinces of Saskatchewan and Alberta in Canada, occupying an area of about 100,000 square kilometres. The unique geology of the Athabasca Basin often results in deposit grades that exceed the world average of uranium deposits of 0.2% U3O8 by up to 100 times.

All of Canada’s current uranium production occurs from the mines located in the Athabasca Basin. According to the World Nuclear Association, the Athabasca Basin was responsible for producing 15% of the world’s uranium production in 2022.

Uranium mineralization in the Athabasca Basin occurs in fault structures that penetrate the interface between the sandstone and underlying basement rocks. Uranium can be found at the interface, known as the unconformity, or up to several hundreds of metres below the unconformity surface in the underlying basement rock and fault structures.

 

About the Roughrider Uranium Project

The Roughrider Project is a uranium project located in the eastern Athabasca Basin of northern Saskatchewan, Canada; one of the world’s premier uranium mining jurisdictions. The project is located approximately 13 kilometres west of Orano’s McClean Lake Mill, near UEC’s existing Athabasca Basin properties, see Figure 4. The depth to mineralization at the project is approximately 200 m and hosted primarily in the basement rocks below the unconformity.

Figure 4 Roughrider Location Map (CNW Group/Uranium Energy Corp)

Qualified Person

The technical information in this news release has been reviewed and approved by James Hatley, P.Eng., UEC’s Vice President Production, Canada, who is a Qualified Person for the purposes of SEC Regulation S-K 1300.

About Uranium Energy Corp

Uranium Energy Corp is America’s largest and fastest growing supplier of uranium needed to produce safe, clean, reliable nuclear energy. UEC is advancing the next generation of low-cost, environmentally friendly ISR mining uranium projects in the United Statesand high-grade conventional projects in Canada. The Company has two production-ready ISR hub and spoke platforms in South Texas and Wyoming. These two production platforms are anchored by fully operational Central Processing Plants and served by seven U.S. ISR uranium projects with all their major permits in place. In August 2024, production began at the Christensen Ranch project in Wyoming, sending uranium loaded resin to the CPP at Irigaray (Wyoming hub). Additionally, the Company has diversified uranium holdings including: (1) one of the largest physical uranium portfolios of U.S. warehoused U3O8; (2) a major equity stake in Uranium Royalty Corp., the only royalty company in the sector; and (3) a Western Hemisphere pipeline of resource stage uranium projects. The Company’s operations are managed by professionals with decades of hands-on experience in the key facets of uranium exploration, development and mining.

Posted November 8, 2024

Share this news article

MORE or "UNCATEGORIZED"


White Gold Corp. Closes $5M First Tranche of Upsized Private Placement

White Gold Corp. (TSX-V: WGO) (OTCQX: WHGOF) (FRA: 29W) is please... READ MORE

December 23, 2024

Osisko Announces Acquisition of Additional Gibraltar Silver Stream Interest and Closing of the Dalgaranga Royalties Acquisition

Osisko Gold Royalties Ltd (TSX:OR) (NYSE:OR) is pleased to announ... READ MORE

December 23, 2024

Canada Nickel Announces Initial Resource at Reid Nickel Sulphide Project

Highlights: Initial Reid Indicated Resource of 0.59 billion tonne... READ MORE

December 23, 2024

NMG Announces the Closing of Aggregate US$50 Million Private Placement by Canada Growth Fund and Investissement Quebec

Nouveau Monde Graphite Inc. (NYSE: NMG) (TSX-V: NOU) confirms it ... READ MORE

December 23, 2024

FALCO ANNOUNCES CLOSING OF BROKERED PRIVATE PLACEMENT

Falco Resources Ltd. (TSX-V: FPC) is pleased to announce the closing of ... READ MORE

December 20, 2024

Copyright 2024 The Prospector News