The Prospector News

Updated PEA for Falchani Highlights Robust Economics After-tax NPV8% Triples to US$5.11 Billion, IRR 32.0% and Low Opex $5,093/t LCE

You have opened a direct link to the current edition PDF

Open PDF Close
Uncategorized

Share this news article

Updated PEA for Falchani Highlights Robust Economics After-tax NPV8% Triples to US$5.11 Billion, IRR 32.0% and Low Opex $5,093/t LCE

 

 

 

 

 

American Lithium Corp. (TSX-V:LI) (NASDAQ:AMLI) ( Frankfurt:5LA1) is pleased to announce the results of its updated Preliminary Economic Assessment for the Falchani Lithium project located in Puno, southwestern Peru. This independent, updated PEA was completed by DRA Global following the updated mineral resource estimate recently completed by Stantec Consulting Services Ltd. (“Stantec” – see news release dated December 15, 2023).

 

The updated PEA demonstrates that with low initial capex, the Falchani project has the potential to become a substantial, low-cost, long-life producer of high purity Lithium Carbonate (“LCE” or “Li2CO3”) with the potential to also produce Sulfate of Potash (“SOP”) and Cesium Sulfate (“CsS” or “Cs2SO4”) by-products alongside LCE. The PEA base case envisions 32 years of mining followed by 11 years of stockpile processing over the potential life of mine. The PEA alternative case is identical, but with added production of high purity SOP and Cesium sulfate as by-products from Years 6-43 alongside the initial expansion. All dollar figures are in US currency.

 

Falchani PEA Highlights (Base Case – LCE only production):

  • Pre-tax Net Present Value8% $8.41 billion at $22,500/tonne LCE
  • After-tax NPV8% $5.11 billion at $22,500/t LCE
    • NPV has tripled versus 2019 PEA After-tax NPV8% $1.5 billion at $12,000/t LCE
  • Pre-tax Internal Rate of Return of 40.7%
  • After-tax IRR of 32.0%
  • Pre-tax initial capital payback period 2.5 years; after-tax payback 3.0 years
  • Average LOM annual pre-tax cash flow: $1,019 million; annual after-tax cash flow: $ 644 million
  • Initial Capital Costs estimated at $681 million
  • Total Capex LOM estimated at $2,565 million; Sustaining Capital estimated at $236 million
  • Operating cost estimated at $5,092/t LCE
  • PEA mine and processing plan produces 2.64 Mt LCE LOM over 43 years
    • Steady-state Ave. of 23,145 tpa LCE Phase 1; 45,084 tpa Phase 2; and 72,624 tpa Phase 3

 

Simon Clarke, CEO of American Lithium states, “The very large increase in NPV combined with a low initial capex and robust economics in the updated PEA for Falchani are the culmination of successful work programs at site and flow sheet optimization over the last couple of years combined with an improved lithium pricing environment. We are also extremely pleased to now include the compelling strategic and economic value proposition of adding SOP fertilizer and cesium sulfate by-products to the robust economic potential of core, high purity lithium production at Falchani. This PEA update is a major step towards completion of pre-feasibility work.

 

In this PEA, we showcase the existing potential for high annual production and long mine-life at Falchani, yet the deposit resource currently remains open to the north and west with the potential for further resource / mine-life expansion. The low operating cost potential at Falchani with costs of less than $5,100/t LC, puts it among the lowest cost next-tier lithium projects under development globally. With the potential to also supply significant amounts of SOP to the Peruvian agricultural sector, the project has the unique characteristic of having major positive strategic implications for two key sectors of the Peruvian economy.”

 

Falchani PEA Highlights Alternate Case – LCE-only in Phase 1; SOP + Cs2SO4 added from Phase 2:

  • Identical LCE production scenario, but with added average production of 81,556 tpa of SOP and 3,796 tpa of Cs2SO4 from Years 6-43
  • Pre-tax NPV8% $9.25 billion at $22,500/t LCE, $1,000/t SOP & $58,000/t Cs2SO4
  • After-tax NPV8% $5.58 billion at $22,500/t LCE, $1,000/t SOP & $58,000/t Cs2SO4
  • Pre-tax Internal Rate of Return of 38.5%
  • After-tax IRR of 29.9%
  • Pre-tax initial capital payback period 2.5 years; after-tax payback 3.0 years
  • Average LOM pre-tax annual cash flow (excluding initial capital): $1,227 million; annual after-tax cash flow: $ 774 million
  • Initial Capital Costs estimated at $681 million
  • Total Capex estimated at $3,466 million; Sustaining Capital estimated at $260 million
  • Opex estimated at $5,705/t LCE (for all products)
  • Opex estimated at $1,361/t LCE, inclusive of SOP & Cs2SO4 credits
  • PEA mine plan produces 2.64 Mt LCE and 3.10 Mt SOP and 144,247 t Cs2SO4 LOM over 43 years

 

Mine Life & Production

  • Simple drill, blast, truck and shovel open pit mining of the near-surface, high-grade (>2,700 ppm Li) resource the scalable, long-life, lithium project producing approximately 23 ktpa LCE over Years 1-5, expanding to 45 ktpa LCE production for Years 6-10 years followed by Phase 3 expansion producing ~84 ktpa for Years 11-32 when mining ceases. Rehandling of the <2,700 ppm Li stockpile allows production to continue for Years 33-43, averaging 44.8 ktpa over this period.
  • Average LOM Production of approximately 61,400 tpa of 99.5% LCE for 43 years.
  • Targeted >2,700 ppm Li grade pit-constrained resource supports mining for 32 years and processing <2,700 ppm Li stockpile for an additional 11 years.
  • LOM Strip Ratio (Waste:Ore) of 0.60:1 after accounting for processed stockpile material
  • Sulfuric acid leaching using industry standard techniques and flowsheet produces high purity lithium carbonate to enable the production of battery grade LC.
  • Sulfate of Potash is an important fertilizer product for specialty crops, especially those grown in Peru (ex. avocado, blueberries, grapes & coffee) with a growing global market. SOP production from Falchani has the potential to satisfy Peru’s domestic needs with additional export possibility.
  • Cesium is used in high-pressure, high-temperature offshore oil and gas drilling and is used in infrared detectors, optics, photoelectrical cells, scintillation counters and spectrometers. Isotopes of cesium are atomic clocks necessary for aircraft guidance systems, global positioning satellites, and internet and cell phone applications. Cesium sulfate produced at Falchani can be further refined by third parties into desired end-products.

 

Table 1 – Falchani Project PEA Key Highlights

 

Description Units Base Case Alternate Case
LCE Selling Price $/tonne $22,500 $22,500
Life of Mine years 43 43
Processing Rate P1 / P2 / P31 ROM Mtpa 1.5/3.0/6.0 1.5/3.0/6.0
Average Throughput (LOM) tpa 4,946,898 4,946,898
LCE Produced (average LOM)1 tpa 61,386 61,386
P1 LCE Production (Yr 1-5 steady state) tpa 23,000 23,000
P2 LCE Production (Yr 6-10 steady state) tpa 45,000 45,000
P3 LCE Production (Yr 11-32 steady state) tpa 84,000 84,000
P3 LCE Production (Yr 33-43 stockpile) tpa 44,800 44,800
LCE Produced (total LOM)1 tonnes 2,639,610 2,639,610
Unit Operating Cost (OPEX) LOM2 $/LCE tonne 5,092 1,361
SOP Produced (average LOM)1 tpa n/a 81,556
SOP Selling Price $/tonne n/a 1,000
Cs2SO4 Produced (average LOM)1 tpa n/a 3,796
Cs2SO4 Selling Price $/tonne n/a 58,000
Capital Cost (CAPEX)3 P1 $ M 681 681
Capital Cost (CAPEX)3 LOM $ M 2,565 3,466
Sustaining Capital Costs (undiscounted) $ M 236 260
Project Economics
Pre-tax:
Net Present Value (NPV) (8%) U$ M 8,411 9,251
Internal Rate of Return (IRR) % 40.7 38.5
Initial Payback Period (undiscounted) years 2.5 2.5
Average Annual Cash Flow (LOM) $ M 1,019 1,227
Cumulative Cash Flow (undiscounted) $ M 43,150 52,072
After-tax:4
Net Present Value (NPV)8%) Post-Tax $ M 5,109 5,585
Internal Rate of Return (IRR) Post-Tax % 32.0 29.9
Payback Period (undiscounted) years 3.0 3.0
Average Annual Cash Flow (LOM) $ M 644 774
Cumulative Cash Flow (undiscounted) $ M 27,011 32,597

Notes:

  1. Production: base case is 3 phases, 1.5Mtpa, 3.0Mtpa and 6.0Mtpa throughput; alternative case is identical with production of LCE-only in Phase 1, but with SOP and Cs2SO4 co-products from Phase 2 expansion onward (Years 6-43).
  2. Includes all operating expenditures with credit for SOP and Cs2SO4 production as offset to Unit LCE Opex, the estimate is expected to fall within an accuracy level of ±30%.
  3. Includes an 11% design development allowance (DDA) on process plant capital costs.
  4. Tax calculation is preliminary with estimates considering current applicable taxes and include: Depreciation; Workers’ Participation Tax; Mining Pension Fund; Modified Mining Royalty Tax; and Federal Income Taxes.

 

Sensitivities (Base Case)

 

The NPV for the project is most sensitive to LCE/metal selling price, but relatively far less sensitive to operating costs, capital costs and main reagent costs. IRR is most sensitive to capital costs and LCE/metal selling price (Figures 1 and 2, below).

 

Figure 1 – Base Case Post-Tax NPV8 Sensitivity Graph

 

Figure 2 – Base Case Post-Tax IRR Sensitivity Graph

 

Mining

 

Based on the analysis completed by DRA Global, the Falchani Project is highly amenable for development by conventional open pit, drill-blast, truck and shovel operation. The Base Case and Alternative Case have identical LOM production plans and schedules.

 

Table 3 – Mining/Processing Rates

 

Parameter Unit Value
Production Life Years 43 (includes 2-year production ramp up)1
Material mined Mt 339.7
ROM head grade to leach (Years 1-32) ppm Li 3,382
ROM head grade to leach (Years 33-43) ppm Li 1,841
Recovered LCE LOM Mt 2.63
Waste LOM Mt 127.0
Total Mineralized Material throughput LOM Mt 212.7
Strip Ratio (LOM) (tw:to) 0.60
  1. 2 years construction, including 1 year Capitalized pre-production mining; 2-year production ramp-up with 75% nameplate in Year 2.

 

Table 4 – Detailed Capital Cost Estimates:

 

Capital Costs Phase 1 Phase 2 Phase 3 LOM
($ millions)        
Mining (pre-strip and capital) 10.3 10.3 20.6 41.2
Processing plant – Direct costs 399.9 359.9 720.5 1480.3
Processing plant/mine – Infrastructure 36.3 32.7 65.5 134.5
Bulk infrastructure1 35.1 17.6 35.2 87.9
Tailings2 29.2 127.4 156.6
Total Direct Costs 510.8 420.5 969.1 1900.4
Total Indirect Costs (Process Plant)2 109.7 98.7 197.4 405.8
Contingency/DDA (Process Plant)11% 60.1 54.1 108.2 222.4
Closure Costs (captured in sustaining) 36.0
TOTAL – Li Only Base Case 680.6 573.3 1274.7 2,564.6
Added Plant Capex for Cs2SO4 + SOP 417 395 812
Added Contingency for Cs2SO4 + SOP 45.9 43.5 89.4
TOTAL – Li + Cs2SO4 + SOP 680.6 1,036.3  1713.2 3,466.0
Sustaining Capital Costs – Li only 235.6
Sustaining Capital Costs – Li + Cs2SO4 + SOP 259.9
  1. Tailings built in phases and included in P1 capital cost estimate and sustaining capital for remaining LOM
  2. Includes EPCM, spares, insurances, owners’ team.

 

The PEA is preliminary in nature and includes inferred resources that are considered too speculative to have the economic considerations applied to them that would enable them to be categorized as mineral reserves and there is no certainty the estimates presented in the PEA will be realized.

 

Qualified Persons

 

David Alan Thompson B-Tech, Pr Cert Eng, SACMA of DRA Projects SA Pty, an Independent Qualified Person as defined by NI 43-101, has prepared or supervised the preparation of, or has reviewed and approved the scientific and technical information pertaining to mining, mine scheduling and optimization contained in this news release.

 

John Joseph Riordan, BSc, CEng, FAuslMM, MIChemE, RPEQ, of DRA Pacific (Pty) Ltd., and Aveshan Naidoo MBA, BSc, PrEng, MSAIMM of DRA Projects SA Pty Ltd., Independent Qualified Persons as defined by NI 43-101, have prepared or supervised the preparation of, or have reviewed and approved the scientific and technical metallurgical information and financial modelling results contained in this news release.

 

Mr. Ted O’Connor, P.Geo., Executive Vice President of American Lithium, and a Qualified Person as defined by National Instrument 43-101 Standards of Disclosure for Mineral Projects, has also reviewed and approved the scientific and technical information contained in this news release.

 

The PEA is preliminary in nature and includes inferred resources that are considered too speculative to have the economic considerations applied to them that would enable them to be categorized as mineral reserves and there is no certainty the estimates presented in the PEA will be realized.

 

In accordance with NI 43-101, the Company intends to file the completed technical report on the PEA under the Company’s profile on SEDAR+ (www.sedarplus.ca) and on the Company’s website within 45 days from the date of this news release.

 

About DRA Global Limited, as lead engineer, is a diversified global engineering, project delivery and operations management group headquartered in Perth, Australia, with an impressive track record completing over 300 unique projects worldwide spanning more than three decades. Known for its collaborative approach and extensive experience in project development and delivery, as well as turnkey operations and maintenance services, DRA Global delivers optimal solutions that are tailored to meet clients’ needs.

 

About American Lithium

 

American Lithium is actively engaged in the development of large-scale lithium projects within mining-friendly jurisdictions throughout the Americas. The Company is currently focused on enabling the shift to the new energy paradigm through the continued development of its strategically located TLC lithium project in the richly mineralized Esmeralda lithium district in Nevada, as well as continuing to advance its Falchani lithium and Macusani uranium development-stage projects in southeastern Peru. All three projects, TLC, Falchani and Macusani have been through robust preliminary economic assessments, exhibit strong significant expansion potential and enjoy strong community support. Pre-feasibility is advancing well TLC and Falchani.

 

Posted January 10, 2024

Share this news article

MORE or "UNCATEGORIZED"


Ascot Announces Closing of C$34 Million Bought Deal Financing

Ascot Resources Ltd. (TSX: AOT) (OTCQX: AOTVF) is pleased to anno... READ MORE

July 25, 2024

RUA GOLD Closes C$8 Million Brokered Offering and Announces Commencement of Trading on the TSX Venture Exchange

Highlights Closing the fully subscribed brokered offering for C$8... READ MORE

July 25, 2024

Mosaic Acquires 100% of the Amanda Project

Mosaic Minerals Corporation (CSE: MOC) announces that it has sign... READ MORE

July 25, 2024

First Phosphate Confirms Significant High-Quality Igneous Phosphate Deposit at Its Bégin-Lamarche Project in the Saguenay-Lac-St-Jean Region, Quebec au Canada

First Phosphate Corp. (CSE: PHOS) (OTC: FRSPF) (FSE: KD0) is ple... READ MORE

July 25, 2024

PROSPECT RIDGE ANNOUNCES FINAL CLOSING OF ITS OVERSUBSCRIBED PRIVATE PLACEMENT

Prospect Ridge Resources Corp.  (CSE: PRR) (OTC: PRRSF) (FRA: OE... READ MORE

July 25, 2024

Copyright 2024 The Prospector News