Taseko Mines Limited (TSX: TKO) (NYSE MKT: TGB) (LSE: TKO) announces second quarter production results of 20 million pounds of copper and 185,000 pounds of molybdenum.

 

the relocation of the in-pit crusher and concurrent maintenance activities in concentrator #1, as well as a strike by the mine’s unionized workforce in June. The in-pit crusher move was completed in late May but the final installation work and the other mill maintenance was interrupted by the 18-day strike in June. This work resumed following the strike, when contractors were able to return to site, and is now completed. Concentrator #1 has restarted and is in the process of ramping up to full capacity.

 

Concentrator #2 has been running consistently and at improved throughput rates since the repair work in January. An insurance claim has now been finalized for this previous issue, and insurance proceeds of US$22 million are expected to be received in the third quarter.

 

Stuart McDonald, President & CEO of Taseko, commented, “Production in the second half of 2024 is expected to be stronger with the major project and maintenance work in both concentrators completed.  An updated mine plan and mill throughput opportunities are being evaluated to recover some of the production that was lost during the strike.  Copper production for the year is expected to be in the range of 110 to 115 million pounds, compared to original guidance of 115 million pounds.”

 

Posted July 15, 2024

Share this news article

MORE or "UNCATEGORIZED"


Hudbay Provides Annual Reserve and Resource Update with Mine Life Extensions and Improved Three-Year Production Outlook

Hudbay Minerals Inc. (TSX:HBM) (NYSE: HBM) today released its ann... READ MORE

March 27, 2026

OREZONE GOLD COMPLETES STRATEGIC ACQUISITION OF CASA BERARDI GOLD MINE AND QUEBEC EXPLORATION PORTFOLIO AND REPORTS FOURTH QUARTER 2025 RESULTS

Strategic acquisition of an established operating gold mine, loca... READ MORE

March 27, 2026

Cerro de Pasco Resources Secures Access Agreement Over Entire Quiulacocha Tailings Area, Enabling Next Phase of Project Development

Cerro de Pasco Resources Inc. (TSX-V: CDPR) (OTCQB: GPPRF) (FRA: ... READ MORE

March 26, 2026

SAGA Metals Acquires Strategic Titanium Assets from Rio Tinto in Quebec

The Garneau Titanium Project Features Ilmenite-Rich Boulder with ... READ MORE

March 26, 2026

ValOre Reports Positive Leaching Results from Ongoing Metallurgical Program for Pedra Branca PGM Project, Brazil; 73% Platinum and 74% Palladium Achieved Extraction from Weathered Material and 66% Platinum and 79% Palladium from Chromitite;

ValOre Metals Corp. (TSX‐V: VO) (OTCQB: KVLQF) (Frankfurt: KEQ0... READ MORE

March 26, 2026

Copyright 2026 The Prospector News