The Prospector News

Sparton Resources Announces Vanadium Flow Battery Entering Final Commissioning Phase

You have opened a direct link to the current edition PDF

Open PDF Close
Uncategorized

Share this news article

Sparton Resources Announces Vanadium Flow Battery Entering Final Commissioning Phase

 

 

 

 

 

Sparton Resources Inc. (TSX-V:SRI) is pleased to announce that the final phase of commissioning for the Zhangbei Project’s 8 megawatt hour vanadium flow battery is expected to begin on or about January 8, 2016.

 

 Commissioning Work

 

 

The State Grid North China Company Limited’s “863” comprehensive testing program was completed satisfactorily on January 5, 2016. This test involved integrated full power charging and discharging of all of the energy storage units currently installed at Zhangbei including the 8 megawatt hour vanadium flow battery. These performance tests were monitored by engineers and technicians from State Grid to ensure that the battery meets design protocols. Following successful completion of the 863 testing procedures, State Grid has given permission to begin the continuous 240-hour operations test that will be the final phase of the 8 megawatt hour vanadium flow battery commissioning program.

 

 

Both State Grid and VanSpar’s technicians will monitor the battery operation during this test period and will prepare comprehensive reports on the test procedures and results. These will be submitted to State Grid for acceptance.

 

 

Funding Through Subsidiaries

 

 

Funding for this commissioning project has been carried out by VanSpar Mining Inc. a 90.4% owned Sparton subsidiary. In the past two months, VanSpar has raised Cdn$183,000 in convertible debt which could, if the conversion feature is exercised by all of the current debt holders, reduce Sparton’s ownership in VanSpar to approximately 85% fully diluted. Funds raised by VanSpar have been advanced to Jiujiang Sparton Vanadium Trade and Tech Co. Ltd. a Sino Foreign Chinese joint venture company 90% owned by VanSpar. JJSP has the commissioning contract with the builder of the battery. Additional financing efforts by VanSpar are continuing concurrently with the commissioning process.

 

 

Once the test period is successfully completed, and the performance and acceptance reports are submitted to State Grid’s satisfaction, a payment, which is expected to be up to RMB 16.44 million (approximately US$2.64 million), will become payable by State Grid to JJSP’s client, the battery builder, under a court-supervised payment process. After certain deductions are approved by the court for payment, which are expected to be in the range of RMB10.56 million (approximately US$1.70 million), the balance will be available for payment to JJSP by its client and JJSP will then repay VanSpar. The amounts payable at each step of this process are undetermined at this time, as the timing for each step is not fixed. The commissioning contract further provides for JJSP to continue the service obligations of its client for this battery by providing 3 years of maintenance on the installation. For this ongoing program, JJSP is to receive from its client annual payments of RMB5.5 million (approximately US $880,000) that are required to be paid by State Grid to JJSP’s client.

 

 

About the Zhangbei Project

 

 

The Zhangbei Project, jointly launched in May 2010 by the Ministry of Finance, the Ministry of Science and Technology, and the National Energy Bureau is operated by State Grid. Located approximately 180 km north of downtown Beijing near Zhangjiakou, in Hebei Province, it integrates wind power, solar power, energy storage, and smart grid transmission technologies. Clean power generated by this project supplies a portion of north China’s energy needs. The energy storage equipment currently installed and being tested on site includes the 8 megawatt hour vanadium flow battery being commissioned by VanSpar as well as smaller capacity lithium and lead-acid storage batteries and capacitors.

 

 

Zhangbei is China’s largest wind and solar energy electricity generation and storage installation. It supports the storage and release of clean electricity into the power grid in an efficient and controlled manner.

 

 

The project is a key component of China’s Golden Sun Photovoltaic Solar Pilot Project.

 

 

It currently includes 500 megawatts of wind power and 100 megawatts of solar power, with 110 megawatts of energy storage capacity, and covers a total land area of 200 square kilometres. Expansion plans for both electricity generation from wind and solar sources, and additional energy storage capacity have been recently announced.

 

 

With a total investment of 12 billion RMB (approximately US$1.8 billion), upon completion, it will be China’s largest grid integration photovoltaic solar power generation station and its largest land-based wind farm in unit capacity, as well as the world’s largest chemical energy storage station.

 

 

The project represents state of art installations for all its various components and will integrate a large number of different operational technologies in a single new energy project.

 

Posted January 7, 2016

Share this news article

MORE or "UNCATEGORIZED"


Uranium Royalty Corp. Closes $30 million Initial Public Offering and Announces Listing on the TSX Venture Exchange

Uranium Royalty Corp. (TSX-V: URC) is pleased to announce that it... READ MORE

December 6, 2019

Denison Completes CAD$4.7 Million Bought Deal Private Placement of Flow-Through Shares

Denison Mines Corp. (DML: TSX) (DNN: NYSE American) is plea... READ MORE

December 6, 2019

Scorpio Gold Reports Results of Drilling at the Keystone-Jumbo Area, Goldwedge Property, Nevada

Scorpio Gold Corporation (TSX-V:SGN) announces results of its fir... READ MORE

December 6, 2019

Nevada Exploration Closes Oversubscribed Financing

Nevada Exploration Inc. (TSX-V: NGE) (OTCQB: NVDEF) is pleased to... READ MORE

December 6, 2019

Ascot Exploration Drilling Intersects 17.29 g/t Gold Over 3.58 Metres in New Area West of Premier Portal

Ascot Resources Ltd (TSX: AOT) (OTCQX: AOTVF) is pleased to annou... READ MORE

December 6, 2019

Copyright 2019 The Prospector News - Site design by Spyderbaby Productions