Spanish Mountain Gold Ltd. (TSX-V: SPA) is pleased to announce the assay results from its strategic 2018 drilling program for the Spanish Mountain Gold Project located in British Columbia, Canada.

 

The highly selective program targeted areas within the high-grade, near-surface First Zone of the Project’s multi-million ounce gold resource as described in the news release dated April 10, 2017. The objective of the program is to increase the total number of gold ounces captured in a possible future mine plan by reclassifying certain Inferred Resources to the Measured & Indicated categories. By design, the 2017 Preliminary Economic Assessment only incorporated M&I resources in the mine plan and thereby treated the extracted Inferred Resources as “waste”, which had the effect of artificially inflating the Project’s strip ratio and operating cost. If the current drilling program is successful in upgrading the targeted ounces in a future resource estimate, it is expected to further improve the Project’s robust economics as it effectively converts mined “waste” into mill feed and production ounces.

 

Highlights of the First Set of Drilling Results include:

 

  • 27.43 metres (m) grading 1.76 grams per tonne (g/t), including 12.19m grading 3.62 g/t gold in hole 18SMRC-1221
  • 67.06m grading 0.82 g/t, including 13.72m grading 1.22 g/t and 12.19m grading 1.86 g/t gold in hole 18SMRC-1224
  • 16.76m grading 1.03 g/t, including 4.57m grading 2.28 g/t gold in hole 18SMRC-1225
  • 41.15m grading 0.63 g/t, including 10.67m grading 1.32 g/t gold in hole 18SMRC-1226

 

Significant assay results are summarized in Table 1 appended to this news release.

 

The results of all six holes included in this first set of assays clearly indicate additional higher grade gold mineralization at shallow depths, most of which is at less than 100 metres from the surface. The holes are all located in areas that are proposed to be mined during the early years (Phase I) under the mine plan developed in the 2017 PEA.

 

As announced in the news release dated September 13, 2018, the Company has executed a number of work programs during the year in order to actively advance the Project in multiple technical areas. These programs were designed to fulfil the objectives of achieving higher feed grades, lower capital cost and a more robust resource than those assumed in the 2017 PEA. The initial results appear to support the distinct and welcome possibility for further scaling down from the 2017 mill throughput, which is expected to potentially reduce the initial capital cost significantly while maintaining the robust economics. In contrast with the previously assumed (2012 PEA) throughput of 40,000 tonnes per day for the Project, the 2017 PEA presented a 20,000 tpd scenario focused exclusively on mining the high-grade/ near-surface First Zone resulting in a reduction of initial capital by $257 million. The lower throughput case has materially improved all the economic metrics for the Project in spite of a significantly lower gold price assumption (US $1,250 vs. US $1,462). Please refer to the Company’s website for a detailed comparison of these two scenarios at: www.spanishmountaingold.com/project/2017-pea-vs-2012-pea/

 

Management expects to report the remaining assay results as well as the results of the other programs over the next few months.

 

Larry Yau, Chief Executive Officer, commented: “We are delighted with this first set of assay results, which clearly sit well with our objective of converting ‘waste’ into mill feed in the next mine plan. Of note, this is the third consecutive drilling program over a number of years in which we have consistently encountered results with grades higher than 1 g/t over long intercepts at shallow depths, far exceeding the average grade for the entire resource. I believe that these results call for a comprehensive reassessment of the quality of our large resource as well as the economic model for its development. I look forward to reporting our progress on multiple fronts in due course.”

 

Judy Stoeterau, P.Geo., the Company’s Vice-President of Geology and the qualified person as defined under National Instrument 43-101, has reviewed the contents of this news release. All samples were assayed at ALS Global Ltd. in Vancouver, BC. The Company has retained Discovery Consultants of Vernon, BC, to independently monitor the quality control and quality assurance (QC/QA) data on the Spanish Mountain Gold Project. Analytical precision and accuracy are being measured and monitored by the use of duplicates, prep and pulp samples and by standards (reference material). Possible contamination during the sampling and processing procedures is being monitored by the insertion of blank samples.

 

 

Table 1: Summary of Significant Assay Results

 

 

Hole From To Length Au g/t
18-SMRC-1221 0.00 10.67 10.67 0.50
including 3.05 6.10 3.05 1.17
and 3.05 4.57 1.52 1.92
18-SMRC-1221 13.72 16.76 3.05 0.46
18-SMRC-1221 19.81 21.34 1.52 0.24
18-SMRC-1221 24.38 51.82 27.43 1.76
including 28.96 41.15 12.19 3.62
and 38.10 41.15 3.05 13.26
and 38.10 39.62 1.52 25.70
18-SMRC-1221 82.30 83.82 1.52 0.47
18-SMRC-1221 89.92 96.01 6.10 0.56
18-SMRC-1221 99.06 102.11 3.05 0.35
18-SMRC-1222 27.43 28.96 1.52 0.24
18-SMRC-1222 32.00 41.15 9.14 0.30
18-SMRC-1222 45.72 47.24 1.52 0.58
18-SMRC-1222 64.01 74.68 10.67 0.38
including 64.01 65.53 1.52 1.31
18-SMRC-1222 77.73 79.25 1.52 0.83
18-SMRC-1222 91.44 92.97 1.52 0.92
18-SMRC-1222 102.11 103.63 1.52 0.20
18-SMRC-1222 106.68 111.25 4.57 0.25
18-SMRC-1222 114.30 115.83 1.52 0.22
18-SMRC-1223 0.00 24.38 24.38 0.39
including 9.14 10.67 1.52 1.56
including 21.34 24.38 3.05 0.97
and 22.86 24.38 1.52 1.26
18-SMRC-1223 30.48 32.00 1.52 0.21
18-SMRC-1223 36.58 44.20 7.62 0.23
18-SMRC-1224 4.57 71.63 67.06 0.82
including 4.57 18.29 13.72 1.22
and 6.10 7.62 1.52 1.37
and 12.19 18.29 6.10 1.82
and 12.19 15.24 3.05 2.78
and 12.19 13.72 1.52 4.24
including 22.86 25.91 3.05 1.73
and 22.86 24.38 1.52 3.06
including 35.05 47.24 12.19 1.86
and 44.20 45.72 1.52 4.18
18-SMRC-1225 0.00 16.76 16.76 1.03
including 7.62 12.19 4.57 2.28
18-SMRC-1225 22.86 27.43 4.57 1.23
including 22.86 24.38 1.52 3.31
18-SMRC-1225 45.72 79.25 33.53 0.42
including 68.58 79.25 10.67 0.76
and 68.58 74.68 6.10 1.06
and 68.58 70.10 1.52 2.65
18-SMRC-1225 120.40 121.92 1.52 0.41
18-SMRC-1225 126.49 128.02 1.52 0.44
18-SMRC-1226 6.10 28.96 22.86 0.72
including 12.19 13.72 1.52 2.01
and 16.76 18.29 1.52 1.10
and 27.43 28.96 1.52 1.42
18-SMRC-1226 48.77 89.92 41.15 0.63
including 60.96 67.06 6.10 1.01
and 62.48 67.06 4.57 1.27
including 70.10 80.77 10.67 1.32
including 71.63 74.68 3.05 2.32
18-SMRC-1226 99.06 100.58 1.52 0.31
18-SMRC-1226 112.78 115.82 3.05 0.48

 

 

Posted December 4, 2018

Share this news article

MORE or "UNCATEGORIZED"


Elevation Gold Reports Financial Results for Year Ended December 31, 2023, including $66.4M in Total Revenue

Elevation Gold Mining Corporation (TSX-V: ELVT) (OTCQB: EVGDF) i... READ MORE

April 18, 2024

Reunion Gold Announces the Signing of a Mineral Agreement With the Government of Guyana for Its Oko West Project

Reunion Gold Corporation (TSX-V: RGD; OTCQX: RGDFF) is pleased to announ... READ MORE

April 18, 2024

Drilling Confirms 4 km of Favourable Corridor at Lynx Gold Trend

Puma Exploration Inc. (TSX-V: PUMA) (OTCQB: PUMXF) is thrilled to... READ MORE

April 18, 2024

Grid Metals Intersects 7 m at 1.28% Li2O at over 125 m Below the Previously Deepest Drill Holes at Donner Lake; Provides Project Update

Grid Metals Corp. (TSX-V:GRDM) (OTCQB:MSMGF) is pleased to announ... READ MORE

April 18, 2024

Azimut and SOQUEM Cut Thick Spodumene Pegmatites at Galinée, James Bay Region, Quebec

Azimut Exploration Inc. (TSX-V: AZM) (OTCQX: AZMTF) is pleased ... READ MORE

April 18, 2024

Copyright 2024 The Prospector News