Southern Silver Exploration Corp. (TSX-V:SSV) (OTCQX:SSVFF) reports results from its Preliminary Economic Assessment on its 100% owned Cerro Las Minitas project.
PEA Highlights(all figures in $US unless otherwise noted) :
The 2024 Preliminary Economic Assessment features:
In comparison to the earlier 2022 economic model, the updated PEA now:
Lawrence Page. K. C. President, said: ” This latest economic update of Cerro Las Minitas represents a new milestone in the ongoing evolution and development of the project which is the culmination of a number of smaller technical improvements, developed over the last 18 months, which together result in a significant increase in the value of the Cerro Las Minitas asset. This includes the addition of new mineral resources from the North Felsite zone as first reported in March 2023; the standardization of the metallurgical recoveries and charges across each of the deposits, including the addition of gold revenues into the project cash-flow; improvements in the mine scheduling and optimization both the Operating and Capital costs of the project.”
“Since acquisition of the property in 2010 and subsequent identification of the mineral resources, a very profitable and valuable mine has been modelled in the results of the PEA disclosed today. Total acquisition, exploration and development costs are approximately US$28 million and significantly, the property is not burdened with royalties, presenting potential financing opportunities for additional drilling and development work on the property. This presentation of the results of the PEA marks a significant milestone in the development of the property and the best is yet to come.”
PEA SUMMARY:
Study support
(see Appendices for Resource details, price and recovery assumptions)
Cautionary Statement
The PEA is preliminary in nature, it may include mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves, and there is no certainty that the PEA will be realized. Mineral resources that are not mineral reserves have not demonstrated economic viability. The mineral resources may be affected by subsequent assessment of mining, environmental, processing, permitting, taxation, socio-economic, and other factors.
Project Economics
The CLM project demonstrates robust LOM revenues over 17 years of production and after-tax NPV5% of $501M. Total Capital Expenditure for the project is $565M which requires $388M of initial capital expenditure and $177M in sustaining and closure capital. The project payback is 48
Table 1: CLM Project Economics
After-Tax, Free Cash Flow
Figure 1 illustrates the estimated annual and cumulative after-tax cash flow over the life-of-mine for both the Base Case (blue) and the Base Case +20% metal values (grey). Mine scheduling targets higher margin mineralization in the first eight years of production resulting in a more aggressive paydown of capital and improved economics with an annual average After-tax Free-cashflow of $107M in the first eight years of production and $78M over the life-of-Mine.
Figure 1: Annual and LOM cashflow
Economic Sensitivities
The Project’s gross revenues, NPV5% and IRR shows greatest sensitivity to metal prices.
Table 2: Gross Revenue, NPV5% and IRR sensitivity at base-case +/- 20% and current pricing
Other factors that may impact the NPV sensitivity include changes in Operating Costs and Initial Capital. These relative impacts together with changes in silver and zinc prices are shown in Table 3 and Figure 2.
Table 3: NPV sensitivity as a function of select metals prices, recoveries, CapEx and OpEx:
Figure 2: After-tax NPV5% sensitivities
Production and Costs:
Annual mine production is estimated to deliver 14.3 Moz AgEq (includes 5.8 Mozs Ag) to the processing facility averaged over a 17-year period. Potential annual product of sales (net deductions, treatment and refining) averaging 11.4 Moz AgEq (includes 4.9 Mozs Ag).
Peak annual Plant Feed is achieved in Year 6 with 22.3 Mozs AgEq (includes 9.4 Moz Ag) being processed with peak annual product of sales of 18.0 Moz AgEq (includes 7.9 Moz Ag). Table 4 summarizes the estimated metal production from the CLM project.
Table 4: CLM LOM Production and Metal Sales
Mine Schedule and All-In-Sustaining-Cost
Mine scheduling targets higher value silver-lead production in the first 8 years of mine life with lower AgEq grading material (zinc-copper dominant) being targeted in the final 9 years. Total plant feed (mine production) is estimated to be 243.2 Mozs AgEq (includes 98.6 Mozs Ag) with 194.3 Moz AgEq (includes 83.9 Moz Ag) sold. Total all-in sustaining costs are estimated to be $US 2.57B averaging $US13.23/oz AgEq sold. LOM production and AISC are illustrated in Figure 3.
Figure 3: LOM AgEq sales and AISC:
OPERATIONS:
Mining:
The mine plan was completed by Entech and incorporates longitudinal and transverse longhole stoping methods. Two separate portals are proposed to access the various deposits, with one portal accessing the Blind-El Sol and Skarn Front deposits, and a second portal accessing the La Bocona, South Skarn, and North Felsite deposits. The process in creating the mine plan is further described below:
The grade and average stoping widths are illustrated in Figure 4 and Figure 5 respectively.
Figure 4: US$NSR/t grade distribution of the Cerro Las Minitas MSO model – looking northeast
Figure 5: Average Stope Width of the Cerro Las Minitas MSO model – looking northeast
Processing:
The process plant for the PEA study is a conventional sulphide flotation system consisting of:
Head grades:
MSO scheduling successfully prioritized higher grade material to the mill earlier in the mine life resulting in higher heads grades (and associated annual revenue) in the first eight years of production as compared to the final 10 years.
Table 5: Head grade over Yr1-8 and LOM
Recoveries and Tailings:
Concentrate Terms:
Metal Payables
The project is expected to produce four saleable concentrates of sufficient quality to be marketable to a variety of global smelters.
Approximately 93% of Ag is recovered with 77 % reporting to the Pb concentrate, 6% to the Cu concentrate, 7% to the Zn concentrate and 3% to the leach circuit.
Table 6: Metal Recoveries established for the PEA
Refining and Treatment:
Treatment and refining charges were based on consultation with industry professionals and generated the terms indicated below:
Table 7: Refining and Treatment
The high Ag grade in the Pb concentrate makes it attractive to smelters and could result in more favourable treatment terms, but these have not been considered at the PEA level. Penalty elements are low, with Cd (in solution with Zn) ($8.9/t conc.) being the major contributor to Zn penalties, and Sb (in solution with Pb) being the major source of Pb penalties ($27/t conc).
Concentrate Transportation:
Transportation costs assume trucking of the concentrate via containers to the international port at Manzanillo, Colima, and then shipping via ocean freight to Asia. Estimated transportation costs (trucking, port handling and ocean freight) are US$96/wmt (wet metric tonnes) for Pb concentrate and US$106/wmt for Zn concentrate. Moisture contents are assumed to be 8.5% based on the grind size of the final concentrates.
CAPITAL EXPENDITURES:
Total initial capital investment in the project is estimated to be $388 million and includes $50 million contingency, which represents the total direct and indirect cost for the development of the project, including associated infrastructure.
Table 8: Capital Expenditure break down.
Mining Development Costs:
Mining development costs were developed by Entech considering a mining contractor model. Total capital costs including sustaining capital allocated to mining are approximately $US291M comprising of the following:
Table 9: Mining Capital Breakdown
Operating Costs
Operating costs are broken down into Mining, Processing, G&A and Treatment and Refining costs, plus additional production charges including government royalty, employee profit sharing and closure expenses. Operating costs were developed by Ausenco and Entech (Mine Operating Cost).
Table 10: Operating cost breakdown on a per tonnage basis
Mining:
The operating costs reflect a contractor mining option which defers capital but utilizes the experience of a contractor for initial construction and development of the mine. Mining considers a modern and large operation using large 21-t loaders and 63-t capable trucks targeting an average daily plant feed of approximately 5,300 tpd and 6,900 tpd when including waste development (peak of 7,800 tpd in production Year 4) as both portals are in production. Mining costs are developed by Entech and are from Entech’s cost database which includes pricing from mining contractors.
Table 11: Production and Development Breakdown
Operating costs are summarized as follows and are appropriate for a Preliminary Economic Assessment:
Processing and General & Administration costs:
The process plant is a conventional sulphide flotation system consisting of both primary and secondary crushing, a closed-circuit ball mill grinding and sequential Cu-Pb-Zn flotation circuit producing three filtered concentrates for sale. A fourth pyrite concentrate is produced for leaching.
Operating costs are as follows:
Table 12: Breakdown of Process Plant Operating cost
G&A costs reflect a well-located project in an area of excellent infrastructure and immediately adjacent to the town of Guadalupe Victoria (population: ~35,000).
Opportunities:
Mine life extension: Mineralization on the eastern and northern sides of the Cerro remains relatively under-drilled and several gaps occur in the current resource model both at relatively shallow depths and down dip of several of the main higher-grade zones. Identification of further mineralization at relatively shallow depths would potentially add more value in the earliest parts of the mine schedule.
Infill Drilling:Infill drilling, specifically on the portions of the deposit that fall within the Inferred category of classification will increase confidence in the Mineral Resource estimate, will further de-risk the project and potentially increase the value of the project.
Metallurgical Upside: XRT-based preconcentration testwork showed excellent discrimination between sulphide and oxide material enabling a 3-4x upgrade of run-of-mine rock crushed to 80% passing 75mm with the sub-15 mm fines removed. Pay metal retention in the sulphidic fraction exceeded 98%. This option provides an excellent opportunity for further reductions in project Capex and Opex should the need arise.
Technical Disclosure
Appendices
Appendices with the following supporting information is found at the back of this release.
Appendix A: Sulphide Mineral Resource Estimate
Appendix B: Project location and Infrastructure
Appendix C: Simplified Process Flow Sheet
About Southern Silver Exploration Corp.
Southern Silver Exploration Corp. is an exploration and development company with a focus on the discovery of world-class mineral deposits either directly or through joint-venture relationships in mineral properties in major jurisdictions. Our specific emphasis is the 100% owned Cerro Las Minitas silver-lead-zinc project located in the heart of Mexico’s Faja de Plata, which hosts multiple world-class mineral deposits such as Penasquito, Los Gatos, San Martin, Naica and Pitarrilla. We have assembled a team of highly experienced technical, operational and transactional professionals to support our exploration efforts in developing the Cerro Las Minitas project into a premier, high-grade, silver-lead-zinc mine. Our property portfolio also includes the Oro porphyry copper-gold project and the Hermanas gold-silver vein project where permitting applications for the conduct of a drill program is underway, both located in southern New Mexico, USA
Appendix A: Sulphide Mineral Resource Estimate as of March 20, 2024
1) The current Resource Estimate was prepared by Garth Kirkham, P.Geo., of Kirkham Geosystems Ltd.
2) All mineral resources have been estimated in accordance with Canadian Institute of Mining and Metallurgy and Petroleum (“CIM”) definitions, as required under National Instrument 43-101 (“NI43-101”).
3) Mineral resources were constrained using continuous mining units demonstrating reasonable prospects of eventual economic extraction.
4) Silver Equivalents were calculated from the interpolated block values using relative recoveries and prices between the component metals and silver to determine a final AgEq value. Metal recoveries: 95%. silver, 75% gold, 70% copper, 87% lead and 93.2% zinc.
5) Silver Equivalents and NSR$/t values were calculated using average long-term prices of $22.5/oz. silver, $1,850/oz. gold, $3.78/lb. copper, $0.94/lb. lead and $1.25/lb. zinc . All prices are stated in US$.
6) The formula used for NSR$/t calculations was as follows – $NSR = (Ag g/t x 0.55) + (Au g/t x 34.45) + (Cu% x 48.68) + (Pb% x 13.41) + (Zn% x 15.59)
7) Mineral resources are not mineral reserves until they have demonstrated economic viability. Mineral resource estimates do not account for a resource’s mineability, selectivity, mining loss, or dilution.
8) An Inferred Mineral Resource has a lower level of confidence than that applying to an Indicated Mineral Resource and must not be converted to a Mineral Reserve. It is reasonably expected that the majority of Inferred Mineral Resources could be upgraded to Indicated Mineral Resources with continued exploration.
9) All figures are rounded to reflect the relative accuracy of the estimate and therefore numbers may not appear to add precisely.
Model Parameters for the Blind, El Sol, Skarn, South Skarn, Bocona, and North Felsite Zones
Appendix B: Project Location and Site Infrastructure
Appendix C: Simplified Process Flow Sheet
The process plant for the PEA study is a conventional sulphide flotation system consisting of both Primary and secondary crushing, a closed-circuit ball mill grinding and sequential Cu-Pb-Zn flotation circuit producing three filtered concentrates for sale. A fourth pyrite concentrate will be produced and leached.
Search Minerals Inc. (TSX-V: SMY) is pleased to announce that i... READ MORE
New Found Gold Corp. (TSX-V: NFG) (NYSE-A: NFGC) is pleased to re... READ MORE
GoldHaven Resources Corp. (CSE: GOH) (OTCQB: GHVNF) (FSE: 4QS0) ... READ MORE
Eldorado Gold Corporation (TSX: ELD) (NYSE: EGO) reports the Comp... READ MORE
Centerra Gold Inc. (TSX: CG) (NYSE: CGAU) reported its third quar... READ MORE