Silver Tiger Metals Inc. (TSX:SLVR) (OTCQX:SLVTF) is pleased to provide a construction update for the El Tigre Project located in Sonora, Mexico. Construction is on schedule  for commissioning and first pour in December, 2027.

 

 

  • Build out of Mexican engineering and construction team is nearing completion with a total of 166 persons on site and 100,000-man hours logged since start of construction
  • Detailed engineering by Kappes, Cassiday & Associates and Kappes, Cassiday del Norte S de RL de CV pursuant to the Engineering Procurement and Construction Management Contract for the Project is proceeding on schedule
  • Procurement on long lead items is complete, including crusher plant, conveyer and stacking system, and the Merrill-Crowe plant and refinery

 

  • Land clearing and flora/fauna management for the total construction area is 60% complete

 

  • Installation of construction offices has been completed

 

  • Engineering for improvements to the 46 km road built from Colonia Morelos to El Tigre is complete. The contract to improve this road has been awarded and work has begun, with 25% of road improvements complete

 

  • The major earthworks contract has been awarded for the heap leach, ponds and crusher platforms and these earthworks have commenced

 

  • Comision Federal de Electricidad have granted access to grid electrical power for the El Tigre Project

 

 

 

Glenn Jessome, President and CEO stated, “Our onsite engineering and construction team is nearing 200 persons. Earthworks have begun and land clearing is over 60% complete. Long lead items such as crusher, conveyor, stacking and Merrill-Crowe have been ordered. We are very pleased that mine construction is on schedule for commissioning and first pour in December 2027.”

 

Photo 1: Rehabilitation of Main Access Road for Full Freight Haulage

 

Photo 2: Construction Offices

 

Photo 3: Aerial View of El Tigre

 

Photo 4: Earthworks at the Merrill-Crowe Plant and Pregnant Pond Areas Exploration Drilling

 

The Company has transitioned to exploration drilling targeting the high-potential vein systems north of the main El

Tigre area. This priority zone aligns directly with the El Tigre North Mine Design outlined in Section 24 of the Company’s recently filed Preliminary Economic Assessment (PEA dated January 22, 2026). The PEA also highlighted significant exploration upside beyond the defined underground and Stockwork resources, including the prospective areas 700 meters to the north.

 

 

About Silver Tiger Metals Inc.

 

 

Silver Tiger is constructing the El Tigre Stockwork Zone Project, a silver and gold heap leach project located in Sonora, Mexico.  The project is 100% owned by Silver Tiger and covers over 37,000 hectares.  The Technical Report entitled Stockwork Zone Pre-Feasibility Study and Underground Preliminary Economic Assessment of the El Tigre Silver-Gold Project Sonora, Mexico dated June 20, 2025 is available on SEDAR and under the Corporation’s profile as well as on the Silver Tiger website at www.silvertigermetals.com.

 

 

Silver Tiger has entered into an Engineering Procurement and Construction Management Contract (“EPCM”) with Kappes, Cassidy & Associates (“KCA”) and Kappes, Cassiday del Norte S de RL de CV (“KCN”) to assist in the construction of the mine and process plant at El Tigre. The Company has also now hired its own experienced mine construction executive team to work with KCA and KCN.

 

 

Commissioning and first pour are targeted for December, 2027. The Board of Directors of the Company have approved the construction decision for El Tigre.

 

 

 

VRIFY Slide Deck and 3D Presentation – Silver Tiger’s El Tigre Project

 

 

VRIFY is a platform being used by companies to communicate with investors using 360° virtual tours of remote mining assets, 3D models and interactive presentations. VRIFY can be accessed by website and with the VRIFY iOS and Android apps.  The VRIFY Slide Deck and 3D Presentation for Silver Tiger Metals Inc. can be viewed on the Corporation’s website at:  www.silvertigermetals.com.

 

.

Posted July 8, 2026

Share this news article

MORE or "UNCATEGORIZED"


Canadian Copper Inc. Announces Closing of $44M Project Financing with OR Royalties Inc.

Canadian Copper Inc. (CSE: CCI) announces that it has closed its ... READ MORE

July 16, 2026

New Pacific Metals Reports Results of Updated Carangas Preliminary Economic Assessment: Post-tax $2.65 Billion NPV (5%) and 35.9% IRR; 339.0 Million Oz of Silver Equivalent Produced

New Pacific Metals Corp. (TSX: NUAG) (NYSE-A: NEWP) is pleased to... READ MORE

July 16, 2026

Thunder Gold Reports 1.793 g/t Au over 45.0 metres at UV Target Advancing Tower Mountain Resource Growth Strategy

Thunder Gold Corp. (TSX-V: TGOL) (FSE: Z25) (OTCQB: TGOLF) is ple... READ MORE

July 16, 2026

Vior Gold Corporation Extends High-Grade Mineralization Laterally

5.17 g/t Au Over 2.9 Meters and 7.37 g/t Au Over 2.0 Meters   VI... READ MORE

July 16, 2026

Abcourt Mines Reports Record Development for Q4 2026 at Its Sleeping Giant Mine, Followed by a 160% Increase in Tonnage Processed

Abcourt Mines Inc. is pleased to present a major, unaudited opera... READ MORE

July 16, 2026

Copyright 2026 The Prospector News