Silver Tiger Outlines Path to 5+ Moz Annual Silver Production by 2027

You have opened a direct link to the current edition PDF

Open PDF Close
Uncategorized

Share this news article

Silver Tiger Outlines Path to 5+ Moz Annual Silver Production by 2027

 

 

 

 

  • Silver Tiger’s El Tigre PFS demonstrates the project’s robust economics, with an after-tax NPV of $222 million (at a 5% discount rate) and an impressive IRR of 40%. These figures are based on conservative long-term price assumptions of $26/oz silver and $12,150/oz gold.
  • Silver Tiger Metals already holds permits for an 800 tpd underground mine at El Tigre and has submitted amendments to allow for open pit mining and expects to receive the necessary open pit approvals in the first half of 2025, paving the way for a rapid 12-18 month construction period.
  • Initial production from the El Tigre open pit is targeted for mid-2026 at a rate of approximately 5 million ounces of silver per year.
  • While the PFS only considered open pit mining, there is substantial exploration potential in the historic underground mine areas at El Tigre where multiple high-grade silver zones in the hanging wall and footwall of the old workings were identified as well as a previously unknown bulk tonnage silver-gold-base metal sulfide zone.
  • Underground drilling is set to resume imminently with the goal of expanding resources and delivering a Preliminary Economic Assessment (PEA) in the first half of 2025. A longer-term vision of growing production to 8+ Moz silver equivalent per year from the open pit and underground combined.

 

Courtesy of Silver Tiger Metals, and Crux Investor

Posted November 13, 2024

Share this news article

MORE or "UNCATEGORIZED"


Blue Star Announces Closing of Final Tranche of Non-Brokered Private Placement of Flow-Through Common Shares

Blue Star Gold Corp. (TSX-V: BAU) (OTCQB: BAUFF) (FSE: 5WP0) announces that, further to its news rel... READ MORE

June 22, 2026

Radisson Continues to Extend Scope of Gold Mineralization at the O'Brien Gold Project with Latest Drill Results

Radisson Mining Resources Inc. (TSX-V: RDS) (OTCQX: RMRDF) is pleased to announce new assay results ... READ MORE

June 22, 2026

Zacatecas Silver Announces 21% Increase in High-Grade Heap-Leach Updated Gold Mineral Resource at the Esperanza Gold Project to 1.15 Moz AuEq from 45.4 Mt at 0.79 g/t – Grades Above Global Heap-Leach Average & Highest Grades at Surface

Zacatecas Silver Corp. (TSX-V: ZAC) (OTCQB: ZCTSF) (FRA: 7TV) is pleased to announce an increase in ... READ MORE

June 22, 2026

Magna Mining Intersects 29.7% Copper Equivalent over 3.4 metres, consisting of 9.4% Copper, 2.3% Nickel, 19.8 g/t Gold and 8.8 g/t Platinum + Palladium within the R2 Footwall Zone at the Levack Mine in Sudbury, Ontario

Magna Mining Inc. (TSX-V: NICU) (OTCQX: MGMNF) (FSE: 8YD) is pleased to provide the results of ongoi... READ MORE

June 22, 2026

Alamos Gold Extends High-Grade Mineralization Across Multiple Targets within the Island Gold District which Represent Upside as Potential Sources of Additional Higher-Grade Mill Feed

Alamos Gold Inc. (TSX:AGI) (NYSE:AGI) today reported new results from underground and surface explor... READ MORE

June 22, 2026

Copyright 2026 The Prospector News