Silver Tiger Outlines Path to 5+ Moz Annual Silver Production by 2027

You have opened a direct link to the current edition PDF

Open PDF Close
Uncategorized

Share this news article

Silver Tiger Outlines Path to 5+ Moz Annual Silver Production by 2027

 

 

 

 

  • Silver Tiger’s El Tigre PFS demonstrates the project’s robust economics, with an after-tax NPV of $222 million (at a 5% discount rate) and an impressive IRR of 40%. These figures are based on conservative long-term price assumptions of $26/oz silver and $12,150/oz gold.
  • Silver Tiger Metals already holds permits for an 800 tpd underground mine at El Tigre and has submitted amendments to allow for open pit mining and expects to receive the necessary open pit approvals in the first half of 2025, paving the way for a rapid 12-18 month construction period.
  • Initial production from the El Tigre open pit is targeted for mid-2026 at a rate of approximately 5 million ounces of silver per year.
  • While the PFS only considered open pit mining, there is substantial exploration potential in the historic underground mine areas at El Tigre where multiple high-grade silver zones in the hanging wall and footwall of the old workings were identified as well as a previously unknown bulk tonnage silver-gold-base metal sulfide zone.
  • Underground drilling is set to resume imminently with the goal of expanding resources and delivering a Preliminary Economic Assessment (PEA) in the first half of 2025. A longer-term vision of growing production to 8+ Moz silver equivalent per year from the open pit and underground combined.

 

Courtesy of Silver Tiger Metals, and Crux Investor

Posted November 13, 2024

Share this news article

MORE or "UNCATEGORIZED"


Appia Intersects REE-Bearing Monazite in Three of Six Drill Holes and Completes 2026 Alces Lake Summer Drill Program

Appia Rare Earths & Uranium Corp. (CSE: API) (OTCQB: APAAF) ... READ MORE

August 6, 2026

Sorrento Resources Ltd. Intersects 31m of 0.42g/t Au, Rodgers Cove, Newfoundland

Sorrento Resources Ltd. (CSE: SRS) (OTCQB: SRSLF), a Canadian exp... READ MORE

August 6, 2026

EraNova Announces Positive Preliminary Economic Assessment for the Adanac Molybdenum Project: After-Tax NPV of $714.4 Million and 23.5% IRR

Study confirms Adanac as a large-scale, long-life primary molybde... READ MORE

August 6, 2026

Oroco Drills 26.48m of 1.18% CuEq in South Zone

Oroco Resource Corp. (TSX-V: OCO) (OTCQB: ORRCF) is pleased to re... READ MORE

August 6, 2026

Winshear Reports Drill Results from the Rodburn Target, Portsoy Project, NE Scotland

High-Grade Mineralization Extended Downdip at the South Zone and ... READ MORE

August 6, 2026

Copyright 2026 The Prospector News