Sierra Metals Announces Positive Preliminary Economic Assessment Results for a 67% Output Expansion at its Bolivar Mine in Mexico to 5,000 Tonnes Per Day Yielding a Return on Investment of 550%

 

 

 

 

 

Sierra Metals Inc. (TSX: SMT) (BVL: SMT) (NYSE AMERICAN: SMTS) is pleased to report the results of a Preliminary Economic Assessment regarding the Company’s Bolivar Mine, located in Chihuahua State, Mexico. The PEA is based on technical inputs from various independent consulting groups, including; SRK, Redco, Anddes and Transmin.

 

 

Based on the technical work from the various independent consultants, the PEA was compiled under National Instrument 43-101 standards by Mining Plus Peru SAC. The full technical report will be filed on SEDAR within 45 days of this news release.

 

 

Highlights of the PEA include:

 

  • After-tax Net Present Value (NPV): US$214 Million at an 8% discount rate
  • Return on Investment (ROI): 550%
  • After-tax Payback Period: 3.4 years
  • Life of Mine Capital Cost: US$96 Million
  • Net After-tax Cash Flow: US$303 Million
  • Total Operating Unit Cost: US$21.18/tonne
  • Plant Processing Rate: 5,000 tonnes per day (TPD)
  • Average Copper Recovery Rate 85%
  • Mine Life: 11 years based on existing Mineral Resource Estimate
  • Life of Mine Copper Payable Production: 252,507,942 pounds

 

 

Igor Gonzales, President and CEO of Sierra Metals commented: “The Company is very encouraged by the results of this PEA as they support the plan to profitably develop and grow the Bolivar Mine in sustainable and staged steps from 3,000 TPD currently, to 3,600 TPD in Q1-2019, and to 5,000 TPD in mid-2020, based on consensus metal pricing.

 

 

The Company is incorporating an aggressive Capex program into the PEA of US$96.0 million over the life of the mine, which includes exploration drilling to increase the mineral resources and convert the existing resources to reserves. Additionally, the PEA reflects an aggressive development program designed to open a mineable reserve at depth and on strike. The Opex reflects yearly production development, definition drilling programs, and other operational costs.

 

 

The current study focuses on the current Mineral Resource reported in the 43-101 Technical Report filed on July 5, 2018 and does not include any drilling completed after October 31, 2017. The Company is continuing with its successful brownfield exploration programs and expects to continue to grow the mineral resources at the Bolivar Mine this year. We believe that this expansion not only provides additional value to the company, as the PEA quantifies, but could also leverage the value of future resource additions. Potential new copper pounds discovered could be incorporated into production plans earlier than if the Company maintained current capacity levels.”

 

 

He concluded, “We are continuing with our strategy to increase shareholder value and grow the reserve and resource base at the Company. We successfully completed brownfield exploration programs at all three mines and increased the mineral reserves and resources during the past two years. Additionally, we implemented a successful operational improvement program in Peru and have completed an effective turn-around program in Mexico, and we have already seen returns on this well-spent capital. Building upon these successes, we have completed a PEA at Cusi and Bolivar, and scoping studies at the Yauricocha Mine expected shortly, which will maximize value and profitability through the implementation of automation and possible throughput increases which will further drive growth and benefit all shareholders in the future.”

 

 

Mineral Reserve and Resource Estimate

 

 

The property is located in the Piedras Verdes District of Chihuahua State, Mexico, approximately 250 kilometers southwest of the city of Chihuahua and consists of 14 mineral concessions (6,800 hectares). The Bolivar deposit is a Cu-Zn skarn and is one of many precious and base metal deposits of the Sierra Madre belt, which trends north-northwest across the states of Chihuahua, Durango and Sonora in northwestern Mexico (Meinert, 2007). Mineralization exhibits strong stratigraphic control and two stratigraphic horizons host the bulk of the mineralization: an upper calcic horizon, which predominantly hosts Zn-rich mineralization, and a lower dolomitic horizon, which predominantly hosts Cu-rich mineralization. In both cases, the highest grades are developed where structures and associated breccia zones cross these favorable horizons near skarn-marble contacts.

 

 

This PEA considers depleted measured, indicated and inferred resources reported on 2017 by SRK and effective date as of October 31, 2017. The results of this PEA are indicative of conceptual potential and are not definitive.

 

 

Table 1-1: Summary of resource reported by SRK, 2017 (Effective October 31, 2017)

 

 

 

Class Tonnes
(000’s)
Ag

(g/t)

Au

(g/t)

Cu

(%)

Ag

(koz)

Au

(koz)

Cu

(t)

Indicated 13,267 22.5 0.29 1.04 9,616 124 137,537
Inferred 8,012 22.4 0.42 0.96 5,779 109 76,774
(1) Mineral resources are not mineral reserves and do not have demonstrated economic viability. All figures rounded to reflect the relative accuracy of the estimates. Copper, gold and silver assays were capped where appropriate.
(2) Mineral resources are reported at cut-off values based on metal price assumptions*, metallurgical recovery assumptions**, mining/transport costs (US$17.59/t), processing costs (US$8.33/t), and general and administrative costs (US$2.41/t).   
(3) The metal value cut-off grade for the Bolivar Mine is US$29/t. No mineral resources are reported for the remaining pillars.
* Metal price assumptions considered for the calculation of metal value are: Copper (Cu): US$/lb 3.00, Silver (Ag):  US$/oz 18.25, and Gold (Au): US$/oz 1,291.00.
** Metallurgical recovery assumptions are 83% Cu, 78% Ag, and 64% Au.
The resources were estimated by David Keller of SRK consulting (Canada) using Ordinary Kriging (OK), and reviewed and validated by Giovanny Ortiz, B.Sc., PGeo, FAusIMM #304612 of SRK, a Qualified Person.
Note: Mining has continued since the publication of this resource and resources have not been subsequently depleted.

 

 

 

Sierra Metals commissioned various specialist groups (Table 1-2) to evaluate how, on a conceptual level, mining, mineral processing, and tailings management could be adapted at the property to achieve a sustainable and staged increase in mine production and mill throughput from 3,000 TPD, to 3,600 TPD in Q1-2019, to 5,000 TPD by mid-2020. 

 

 

Table 1-2: Groups involved in development for conceptual plan considered in the PEA

 

 

 

Group Concept Report
SRK Consulting (U.S), Inc. Resource Estimation SRK, 2018
Redco Mining Consultants Increase mine output to 5,000 TPD Redco, 2018
Sierra Metals (SM) Increase Piedras Verdes Pant Capacity to 5,000 TPD Sierra, 2018
Transmin Metallurgical Consultants (TM) Engineering associated with increased Plantas Verdes plant capacity Transmin, 2018
Anddes Asociados Executive Summary – Tailings Expansion Design Andess, 2018

 

 

 

Mining Methodology

 

 

To determine how mine output could be increased, Sierra Metals commissioned Redco Mining Consultants (“Redco’) to undertake a scoping study, considering; existing development and infrastructure, geotechnical characteristics, geological controls and mineralization style. The study (Redco, 2018) determined that Longhole Stoping could be used to achieve sustainable production of 5,000 TPD.

 

 

As part of their scoping study, Redco considered plans for ventilation on a general scale. Sierra Metals recognizes that further and more detailed ventilation plans are required to support a deeper conceptual mine design.

 

 

Mineral Processing

 

 

The Piedras Verdes Plant, located 5.1 kilometers from the Bolivar Mine, uses a conventional crushing-milling-flotation circuit to recover mineral and to produce commercial quality copper concentrates with silver and gold by-product credits. Mineral is delivered from the mine to the plant in 18-tonne trucks.

 

 

Mineral processing and the recovery of the mineral is demonstrated, and copper, silver and gold recoveries are established at 85.0%, 78.2% and 63.7% respectively.

 

 

The Piedras Verdes Plant current throughput is 3,000 TPD. In line with proposed increases in mine output, the processing capacity at Piedras Verdes will increase to 3,600 TPD in Q1-2019, and to 5,000 TPD by mid-2020.

 

 

The current tailings storage facility has an in-situ capacity to store tailings until year end 2019.
A plan is currently underway to construct a much larger capacity facility which will include the installation of a starter dam followed by deposition of filtered – dewatered tailings in a facility which will accommodate 14 million tonnes of filtered tailings providing capacity for future plant expansion. Engineering for this program is provided by ANDDES Engineers from Peru.

 

 

Economic Analysis

 

 

The PEA calculates a Base Case after-tax NPV of US$214 million, with an after – tax Return on Investment of 550% using a discount rate of 8%. The total life of mine capital cost of the project is estimated to total US$96.0 million. The payback period for the Life of Mine (LoM) capital is estimated at 3.4 years. Operating costs of the life of mine total US$359 million, equating to an operating cost of US$21.18 per tonne milled.

 

 

 

PEA Highlights

 

Base case of $1,291/oz Gold, $18.25/oz Silver, $3.00/lb. Copper

Unit Value
Net Present Value (After Tax 8% Discount Rate) US$ M 214
Return on Investment ROI (%) 550
Mill Feed Tonnes (Mt) 16.9
Peak Mining Production Rate t/year 1,800,000
LOM Project Operating Period Years 11
Total Life of Mine (LoM) Capital Costs US$ M 96
Net After – Tax Cashflow US$ M 303
Total Operating Unit Costs US$/t 21.18
LOM Gold Production (Payable) oz 86,472
LOM Silver Production (Payable) oz 7,013,157
LOM Copper Production (Payable) t 114,537

 

 

 

Quality Control

 

 

All technical data contained in this news release has been reviewed and approved by:

 

 

Gordon Babcock, P.Eng., Chief Operating Officer and a Qualified Person under National Instrument 43-101 – Standards of Disclosure for Mineral Projects.

 

 

Americo Zuzunaga, MAusIMM CP (Mining Engineer) and Vice President of Corporate Planning is a Qualified Person and chartered professional qualifying as a Competent Person under the Joint Ore Reserves Committee (JORC) Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves.

 

 

Augusto Chung, FAusIMM CP (Metallurgist) and Consultant to Sierra Metals is a Qualified Person and chartered professional qualifying as a Competent Person on metallurgical processes.

 

 

About Sierra Metals

 

 

Sierra Metals Inc. is Canadian based growing polymetallic mining company with production from its Yauricocha Mine in Peru, and its Bolivar and Cusi Mines in Mexico. The Company is focused on increasing production volume and growing mineral resources. Sierra Metals has recently had several new key discoveries and still has many more exciting brownfield exploration opportunities at all three Mines in Peru and Mexico that are within close proximity to the existing mines. Additionally, the Company also has large land packages at all three mines with several prospective regional targets providing longer-term exploration upside and mineral resource growth potential.

 

Posted July 9, 2018

Share this news article

MORE or "UNCATEGORIZED"


Silver Mountain Announces Closing of Prospectus Offering

Silver Mountain Resources Inc. (TSX-V: AGMR) (OTCQB: AGMRF) is ... READ MORE

April 24, 2024

Mandalay Extends the Storheden Gold Deposit Adjacent to the Operating Björkdal Mine

Mandalay Resources Corporation (TSX: MND) (OTCQB: MNDJF) announce... READ MORE

April 24, 2024

Collective Mining Intercepts 632.25 Metres at 1.10 g/t Gold Equivalent in a 200 Metre Step-Out Hole to the South at Trap

Collective Mining Ltd. (TSX: CNL) (OTCQX: CNLMF) (FSE: GG1) is pl... READ MORE

April 24, 2024

Koryx Copper Intersects 207 Meters at 0.49% and 116 Meters at 0.54% Copper Equivalent

Significant copper and molybdenum intersections include: HM19: 11... READ MORE

April 24, 2024

Red Pine Intercepts Significant Mineralization at the Wawa Gold Project, including 5.34 g/t over 13.39 metres including 16.50 g/t gold over 0.97 metre and 13.62 g/t gold over 2.13 metres

Red Pine Exploration Inc. (TSX-V: RPX) (OTCQB: RDEXF) is pleased ... READ MORE

April 24, 2024

Copyright 2024 The Prospector News