The Prospector News

Sabre Gold Announces Preliminary Economic Assessment Results

You have opened a direct link to the current edition PDF

Open PDF Close
Uncategorized

Share this news article

Sabre Gold Announces Preliminary Economic Assessment Results

 

 

 

 

Sabre Gold Mines Corp. (TSX: SGLD) (OTCQB: SGLDF)  is pleased to announce the results of a Preliminary Economic Assessment for the Company’s 100% owned, road-accessible Brewery Creek Gold Project located in Yukon Territory, Canada.

 

All amounts shown are in United States dollars and metric units of measurement unless otherwise Stated.

 

PEA Highlights:

  • After-tax NPV at 5% of $112 million at an Internal Rate of Return of 27.6% at $1,700 per ounce gold increasing to $157 million at an IRR of 35.7% at $1,900 per ounce gold;
  • After-tax average annual cash flow of $36 million at $1,700 per ounce gold increasing to $44 million at $1,900 per ounce gold
  • Average Annual Production of 60,000 ounces per year for a total 473,000 ounces gold over an initial 8 year mine life;
  • Total cash cost of $850 per ounce and all-in sustaining cost (“AISC”) US$966 per ounce gold;
  • Pre-production capital costs of $105 million with life of mine sustaining costs of $18 million;
  • Payback period of 2.6 years at $1,700 per ounce gold;
  • Excellent expansion potential to extend mine life and annual production with three open prospective resource areas and several targets within a 182 square kilometers project boundary; and,
  • Lower technical and execution risk as a past brownfields producer with existing infrastructure and road access from previous mining operation.

 

Giulio T. Bonifacio, President and Chief Executive Officer of Sabre Gold, stated: “The PEA and initial results confirms our plans to resume production at Brewery Creek with what will be low re-start capital with attractive economics which we believe will be further enhanced in 2022. Sabre Gold intends to continue the expansion of gold resources at Brewery Creek and focus on several key opportunities to enhance value, discussed in detail below. The PEA is advanced in several categories as the predecessor company was initially targeting completion of a feasibility study. Sabre Gold intends to move to a feasibility level study upon completion of the advancement of key opportunities, those of which will not impact our targeted permitting timeline. Our permitting efforts will also now focus on expanding the previously permitted area for purposes of allowing for increases to our annual production profile.” The PEA was prepared in accordance with National Instrument 43-101 (“NI 43-101”) and evaluated the economics of resuming mining at Brewery Creek through open pit mining and heap leaching mined material for gold recovery to doré. The PEA study was prepared by Kappes, Cassiday & Associates of Reno, Nevada in cooperation with Tetra Tech Inc. of Golden, CO, Gustavson and Associates of Lakewood, CO and Wood Environment & Infrastructure Solutions, of Vancouver, British Columbia.

 

PEA Summary – Assumptions and Results
Description Units Pre-Tax Post-Tax
Net Present Value (NPV 5%) US$ M $160 $112
Internal Rate of Return (IRR) %   33.5   27.6
Payback Period (undiscounted) Years     2.6
LOM Average Annual Cash Flow US$ M   44   36
LOM Cumulative Cash Flow (undiscounted) US$ M   237   170
LOM Average Cash Operating costs US$ per ounce $850
LOM Average AISC* US$ per ounce $966
Pre-Production Capital Costs US$ M $105
Sustaining Capital Costs (LOM) US$ M $18
Gold Price US$ per ounce $1,700
Mine Life Years   8
Average Head Grade (diluted) g/t Au   1.05
Average Recovery %   75.4
Average Annual Mining Rate Tonnes per day   9,000
Average Annual Gold Production Ounces per year   60,000
Total LOM Recovered Gold Ounces   473,180

 * AISC – All-In-Sustaining-Cost

 

Mineral Resource Estimate

 

Measured, Indicated and Inferred Mineral Resource estimates have been produced for the eleven named deposits by Gustavson Associates. The results of the estimation result in Brewery Creek Project containing Measured and Indicated Mineral Resources totaling 34.5 million tonnes at 1.03 g/t, containing 1.14 million ounces of gold. Inferred resources total 35.9 million tonnes at 0.88 g/t containing 1.02 million ounces of gold.

 

A Lerchs-Grossmann optimization pit shell constrained the resource using a $2,000/oz gold price and the cutoff grade used is based on a gold price of $1,500/oz and is an internal cutoff grade. The process cost used for the pit shell and cutoff grade includes project general and administrative expenses as well as an average haulage cost to transport process material to the leach pad. Only leachable Measured, Indicated and Inferred Resources are being considered in the PEA.

 

During the work for the PEA, Gustavson reviewed the classification utilized to classify material as Measured, Indicated and Inferred and updated the classification to more appropriately distribute the material into the classification categories, based on an average drill spacing instead of a closest point analysis. This technique utilizes a cell declustering algorithm to quantify drill spacing taking into account geologic anisotropy.

 

 

Total Mineral Resources
Classification Tonnes (‘000) Grade(g/t) Contained (oz Au)
Measured – Leachable
Indicated – Leachable
9,310
13,670
1.18
1.11
353,000
487,000
Total Leachable M & I 22,980 1.14 840,000
Inferred – Leachable 16,200 0.94 489,000
Measured – Sulphide
Indicated – Sulphide
3,950
7,540
0.77
0.85
98,000
206,000
Total Sulphide M&I 11,490 0.82 304,000
Inferred – Sulphide 19,700 0.83 527,000

 

The Mineral Resource Estimate was divided into two categories, leachable and non-leachable resources. Leachable resources are materials that are amenable to cyanide leach processing and can recover gold economically. Leachable material was modeled by using CN soluble gold values to determine potential recoverable gold.

 

The PEA is targeting only leachable resources from the Measured, Indicated and Inferred categories to develop the mine plan and resulting cash flow estimates. Leachable versus non-leachable resources are determined by using the estimated total gold grades and estimated recoveries in the resource model. While the resource tables use cyanide soluble gold for categorization the gold production, gold grades and cutoff grades are shown as in-situ for easy comparison.

 

Leachable Mineral Resources by Pit being evaluated
Classification by Pit Tonnes (‘000) Grade (g/t) Contained (oz Au)
Measured – Leachable
Keg
Lucky
Bohemia-Schooner
East & West Big Rock

3,230
627
2,500
2,950

1.14
1.59
1.35
0.99

119
32
108
94

Indicated – Leachable
Keg
Lucky
Bohemia-Schooner
East & West Big Rock

4,160
1,070
1,310
1,630

1.13
1.76
1.31
0.94

151
61
55
49

Total Leachable M & I 17,477 1.18 669
Inferred – Leachable
Keg
Lucky
Bohemia-Schooner
East & West Big Rock

3,020
767
618
1,030

1.05
1.52
1.45
0.80

102
38
29
26

Total Leachable Inferred 5,435 1.11 195

 

Note: The Keg area includes the previously mined pits of Golden, Kokanee, portions of Canadian and Upper
Fosters and the unmined Lower Fosters deposit. Resources estimates in Table 2 are prior to final pit optimization
and design used to develop diluted potentially minable material.

 

The Mineral Resource Estimate was prepared by Gustavson Associates, LLC (Gustavson). The resource estimate was conducted in accordance with Canadian National Instrument 43-101 Standards of Disclosure for Mineral Projects, June 30,2011, and Canadian Institute of Mining, Metallurgy and Petroleum (CIM) “Best Practices and Reporting Guidelines for Mineral Resources and Mineral Reserves”, May 10, 2014.

 

Mineral Resources are not mineral reserves and do not demonstrate economic viability. The quantity and grade of inferred resources reported herein are uncertain in nature and exploration completed to date is insufficient to define these Mineral Resources as indicated or measured. There is no certainty that all or any part of the Mineral Resource will be converted to mineral reserves. Mineral Resources are not mineral reserves and may be materially affected by environmental, permitting, legal, socio-economic, marketing, political, or other factors. Quantity and grade are estimates and are rounded to reflect the fact that the resource estimate is an approximation. Gustavson knows of no environmental, permitting, legal, title, taxation, socio-economic, marketing, political, or other factors that could materially affect the mineral resource. The effective date of this Mineral Resources Report is May 31, 2020.

 

Mining

 

The Brewery Creek project was evaluated by Tetra Tech for owner operated mining in the PEA as open pit truck and shovel operation. Mining was considered on the leachable (oxide) portions of nine deposits aligned in a more-or-less east-west trend along 8 kilometers in what is known locally as the “reserve trend”. The deposits are West Big Rock, East Big Rock, Upper & Lower Fosters, Kokanee, Golden, Lucky, Bohemian and Schooner. The mine schedule calls for mining and processing over 18.7 million tonnes of heap leach feed and 79.6 million tonnes of waste for a strip ratio of 4.03:1. The current life of mine is 7.9 years.

 

The base case assumes mining and crushing for 275 days per year at an average rate of 9,000 tonnes per day. All heap leach feed material will be crushed to 80% passing 19 mm and conveyor stacked onto existing leach pad which will be off loaded with a 2-meter cushion of old material remaining on the pad to protect the liner. The off-loaded material will be used as back fill to reclaim old pits and or stacked on new storage facilities. The last three original designed cells will be built in year 3.

 

Pit Area Sources of LOM Mill Feed
(kt)
Gold Grade (g/tonne)
Keg 7,173 1.00
Lucky 2,250 1.38
Bohemia-Schooner 4,300 1.23
East & West Big Rocks 4,933 0.80
Total from Pits 18,656 1.05

 

Infrastructure

 

Existing infrastructure includes the existing main access road, two-man camps with a combined capacity for approximately 100 personnel, existing 7 cell leach pad plus foundations for 3 un-built cells, existing haul road network which requires only minor refurbishment, three process solution ponds which require cleaning and new liners, and the former truck shop, a steel structure with the truck bays removed which is currently used as offices and warehousing.

 

Summary of Economic Results

 

Gold Price Sensitivity
Gold
Price
NPV 5% After Tax NPV 5% Pre-Tax Avg. Annual
After tax CF
US$/oz US$M IRR% US$M IRR% US$M
$1450 53.4 16.2 73.0 19.1 27.2
$1500 65.4 18.6 90.4 22.1 29.1
$1600 88.7 23.2 125.2 28.0 32.7
$1700 111.6 27.6 160.0 33.5 36.3
$1800 134.3 31.7 194.7 38.9 39.9
$1900 156.8 35.7 229.5 44.2 43.5
$2000 179.3 39.6 264.2 49.2 47.1

 

 

PEA Capital Cost Summary
Description Pre-Production Sustaining
Capital
Life of
Mine
  US$000s US$000s US$000s
Pre-strip, off load heap $18,105   $18,105
Mine equipment (net of lease)   4,499 $4,601   9,100
Site Infrastructure   29,207   11,182   40,389
Site Infrastructure Haul Roads   1,810     1,810
Process Plant   29,649     29,649
Indirects   2,655     2,655
Owners, EPCM   8,487     8,487
Contingency   10,974   2,236   13,210
Subtotal $105,386 $18,019 $123,405
Working Capital   11,181        (11,181)  
GST (recovery)   5,269   (5,269)  
Reclamation     13,992   13,992
Total Capital $121,836 $15,561 $137,397

 

 

PEA Operating Costs Summary
Mining per tonne moved   1.96
Strip ratio 4:1
Unit Operating Costs (per tonne leached) US$/tonne
     Mining $ 11.31
     Processing   7.62
     General & Administrative   2.52
Total Operating Costs $ 21.45
Total Cash Costs per ounce gold sold $850/oz
All-in-Sustaining Costs per ounce gold sold $966/oz

 

Metallurgy

 

The process plant flow sheet was developed by Kappes, Cassidy Associates of Reno, Nevada and is designed to crush and stack heap leach feed approximately 275 days per year and to recover gold from the heap leach solutions 365 days per year. The flow sheet used a daily feed rate of 9,000 tonnes per day or an annual feed rate of approximately 2.48 million tonnes.

 

Historically, preg-robbing material had hampered gold recoveries on the former heap leach pad. Since 2011, Sabre Gold has routinely assayed for preg-robbing material and the data reveals that the preg-robbing material is confined to sedimentary rocks which were abundant host rocks in the Pacific and Blue pits during the previous mining operation. The pits being targeted for mining in the PEA have gold hosted in intrusive rocks which are largely void of preg-robbing characteristics and contain only minor amounts of sedimentary rocks. There is a strong visual difference between the sedimentary and intrusive rocks at Brewery providing easy visual ore control during mining if sediments are encountered.

 

Material will be delivered to the crushing area and reduced to a nominal 80% passing 19 mm after tertiary crushing with modular crushing units. The crushed material will be stacked on the leach pad by a conveyor stacking system and leached with a low concentration cyanide solution. Gold recovery from the leach solutions is accomplished through an ADR plant.

 

Estimates for gold recovery and consumption rates of reagents is based on metallurgical testing conducted by McClelland Laboratories and SGS. Testing was conducted on fresh drill core samples in 2013, 2016 and 2020. In total 47 column leach tests plus other testing was conducted on the nine deposits included in the PEA and two deposits not included in the PEA. Compacted permeability test work indicate that cement agglomeration is not required for heap heights up to 60 meters.

 

Heap Leach Feed Source Au  NaCN Lime 
Schooner 76 0.40 2.5
Fosters 82 0.21 2.0
Bohemian 82 0.26 3.0
Golden 75 0.21 1.7
Kokanee 65 0.23 1.4
West Big Rock 87 0.30 3.9
East Big Rock 81 0.35 3.4
Lucky 58 0.23 1.4

 

Note: The Keg Pit area consists of Fosters, Golden and Kokanee deposits

 

Key Opportunities to Enhance Value

 

The PEA outlined several opportunities to enhance the economic potential of Brewery Creek including the following:

  • Exploration drilling to expand the leachable mineral resource with several prospective targets identified
  • In-fill drill the areas of inferred resource in the deposits analyzed in this PEA to upgrade them to Measured and Indicated levels of confidence for future conversion to reserves
  • Conduct trade off study for contract mining versus owner mining to potentially reduce up front capital and enhance LOM economics.
  • New leach pad locations should be investigated to accommodate material from additional deposits as they are brought into minable status.
  • Further evaluation of the potential of the sulphide material at depth in all the deposits. Preliminary metallurgical testing has shown good recoveries of gold can be obtained by a flotation process.
  • Continue expanding and upgrading resources at 3 oxide deposits not included in the PEA, Classic, Lonestar and Sleeman.
  • The Classic deposit is located approximately 3 km south of the main Brewery Creek deposit trend. The deposit was originally discovered in 1991 (Hemlo Gold Mines Inc.-Loki Gold Corporation) through a southern grid expansion, the Classic Zone was then being classified as an isolated, arsenic gold anomaly. The deposit is currently defined by 52 reverse-circulation drillholes and 17 core holes, totaling 13,478 meters. The currently identified mineralization lies on the southwest side of the Classic Fault. Predominant rock units hosting mineralization contain variable percentages of syenite (alkali) and biotite monzonite (increasing plagioclase). Mineralization is found to exist within centimeter-scale sheeted quartz veinlets. Structurally, the Classic Zone is open at depth and in both directions along strike. Cutting across the eastern portion is the northwest trending, steeply southwest dipping Classic fault which is mapped to be post intrusion and post mineralization.
  • The Lone Star mineralized area is the fault offset portion of the Classic deposit and lies along the northeast side of the Classic Fault, southeast of and adjacent to the Classic Zone. Surface mineralization was first recognized by soil sampling in the 1990’s but the area remained untested until 2012. Drilling in 2012 consists of 17 core holes and 12 RC holes, totaling 6,147 meters. The same alkalic suite of intrusions that host Classic also host Lone Star. The suite contains syenite, biotite monzonite, monzodiorite, diorite, and gabbro; syenite is the most abundant. The biotite monzonite intrusions commonly form very well developed, course-grained skarn halos where adjacent to limestone and carry copper-gold mineralization. Alteration includes development of a propylitic mineral assemblage of chlorite, calcite and pyrite, and local development of sheeted quartz-carbonate-pyrite-arsenopyrite ±chalcopyrite veins. Three styles of mineralization occur at Lone Star; elevated Au associated with skarns, disseminations in syenite, and auriferous sheeted quartz veins. The geometry of the system is poorly understood; it remains open in both strike directions and at depth.
  • The Sleeman deposit is located to the east of the Brewery Creek Reserve Trend (BCRT). It was discovered by mapping, soil sampling and trenching, and was first drilled in 1992. The zone is currently defined by 7 reverse-circulation drillholes and 58 core drillholes, totaling 11,374 meters. Mineralization at Sleeman is associated with an altered tabular-shaped quartz monzonite intrusion that cuts siltstone of the Steel formation and graphitic argillite of unknown affinity. The intrusion strikes 120° azimuth and dips 65° southwest. It has a known strike length of 500 meters and is open in both strike directions and at depth. All mineralization is associated with altered and veined areas. The style of veining and alteration at Sleeman is similar to the other deposits found within the BCRT with the exception of the presence of elevated base metal concentrations, particularly lead and zinc.

 

First Nations, Community Engagement and Environment

 

Community and First Nation engagement has been a strong component of the Brewery Creek Project dating to the initial mine operator, Viceroy Resources. In 2016 Golden Predator updated and modernized the Socio-Economic Agreement with the Tr’ondek Hwech’in (TH), which addresses environmental responsibilities, permitting, education and employment as well as preferential contracting opportunities and wealth sharing. The Brewery Creek Project lies with the traditional territory of both the Tr’ondek Hwech’in and the First Nation of Na Cho Nyak Dun (NND). Regardless of the pre-existing relationship and agreement with TH and the proximity to Dawson City, Yukon the Company has and will continue to consult with both First Nations on all permitting and regulatory matters.

 

The previous operator and the company have conducted extensive environmental studies and monitoring programs that document the property since the early 1990’s. Studies include water quality, fisheries, wildlife, heritage and vegetation. The company continues to conduct regular environmental sampling and monitoring on the property.

 

Disclosure

 

The PEA results are summarized for purposes of this press release. Further details on the PEA and technical report will be filed on SEDAR and the Company’s website by January 31, 2022.

 

The PEA is preliminary in nature and it includes inferred mineral resources that are considered too speculative to be used in an economic analysis except as allowed for by Canadian Securities Administrator’s NI 43-101 in PEA studies. There is no guarantee that the inferred mineral resources can be converted to Indicated or Measured mineral resources, and as such, there is no guarantee the project economics described in this report will be achieved.

 

Qualified Persons

 

The technical content of this news release has been reviewed and validated by Michael Maslowski CPG, a Qualified Person as defined by National Instrument 43-101 that the information contained in the release is consistent with that provided by the independent Qualified Persons responsible for the PEA. Mr. Maslowski is employed by Sabre Gold Mine Corp as Vice President of Technical Services and Exploration.

 

Non-IFRS Measures

 

The Company has included certain non-IFRS measures in this press release. The Company believes that these measures provide investors an improved ability to evaluate the underlying performance of the project. The non-IFRS measures are intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. These measures do not have any standardized meaning prescribed under IFRS, and therefore may not be comparable to other issuers.

 

About Sabre Gold Mines Corp.

 

Sabre Gold is a diversified, multi-asset near-term gold producer in North America which holds 100-per-cent ownership of both the fully permitted Copperstone gold mine located in Arizona, United States, and the Brewery Creek gold mine located in Yukon, Canada, both of which are former producers. Management intends to restart production at Copperstone followed by Brewery Creek in the near term. Sabre Gold also holds other investments and projects at varying stages of development.

 

Sabre Gold’s two advanced projects have approximately 1.5 million ounces gold in the Measured and Indicated categories, and approximately 1.2 million ounces gold in the Inferred category. Additionally, both Copperstone and Brewery Creek have considerable exploration upside with a combined land package of over 230 square kilometers that will be further drill tested with high-priority targets currently identified. Sabre Gold is led by an experienced team of mining professionals with backgrounds in exploration, mine building and operations.

 

Posted January 18, 2022

Share this news article

MORE or "UNCATEGORIZED"


Red Pine Discovers Significant Gold Mineralization in Faulted Extension of the Jubilee Shear on the Wawa Gold Project

Red Pine Exploration Inc. (TSX-V: RPX) (OTCQB: RDEXF) is pleased ... READ MORE

October 31, 2024

F3 Announces Closing of Private Placement for Aggregate Gross Proceeds of C$8 Million

F3 Uranium Corp. (TSX-V: FUU) (OTC Pink: FUUFF) is pleased to ann... READ MORE

October 31, 2024

Collective Mining Announces Closing of Concurrent Financings for Gross Proceeds of C$46.35 Million

Collective Mining Ltd. (NYSE: CNL) (TSX: CNL) is pleased to ann... READ MORE

October 31, 2024

ARIS MINING ANNOUNCES CLOSING OF US$450 MILLION SENIOR NOTES OFFERING TO FUND REDEMPTION OF OUTSTANDING 6.875% SENIOR NOTES

Aris Mining Corporation  (TSX: ARIS) (NYSE-A: ARMN) announces t... READ MORE

October 31, 2024

Rare Element Resources Receives Final Approval Required to Commence Operations of Rare Earth Demonstration Plant in Wyoming

Staffing in place and operations shakedown underway Rare E... READ MORE

October 31, 2024

Copyright 2024 The Prospector News