The Prospector News

Rubicon Achieves Construction and Financing Milestones Towards the Completion of the Phoenix Gold Project

You have opened a direct link to the current edition PDF

Open PDF Close
Uncategorized

Share this news article

Rubicon Achieves Construction and Financing Milestones Towards the Completion of the Phoenix Gold Project

 

 

 

 

 

 

Rubicon Minerals Corporation (TSX:RMX) (NYSE MKT:RBY) provides an update on the development of the Phoenix Gold Project. Rubicon has recently completed sinking the shaft, initial development of the tailings facility, construction of the mill building, earthworks, and 200-person camp. Underground development is underway. The Company has also entered into a US$75 million gold stream agreement to assist in financing the Project construction.

 

The Phoenix Gold Project Development and Construction Update

 

Shaft Sinking Completed

 

Rubicon completed shaft sinking in mid-December 2013. The total shaft depth is 730 metres from the surface. The installation of a loading pocket on the 337-metre level from surface is completed and the surface skip dump is nearing completion. This allows the Company to expedite underground lateral development on the 122-metre, 244-metre, and 305-metre levels. Two 10-tonne skips and two cages for personnel transport have been installed. The Company will be installing a 10-tonne loading pocket at the 685-metre depth and is planning lateral development at the 610-metre level.

 

Underground Project Development

 

Lateral development has been initiated on the 244-metre level for diamond drilling. Vertical development on the 122-metre and 305-metre levels has commenced and this will provide access for the ventilation system expansion.

 

Tailings Management Facility and Remaining Earthworks

 

The Company has completed the majority of the TMF development necessary for the first 2 years of operation.

 

Mill Construction

 

The main components of the semi-autogenous and ball mill were delivered and received on site in 2013. The Company has poured most of the required outdoor concrete slabs. The mill building is completed and the internal cranes are fully operational. The mill thickener tank foundations are completed. Management has deferred some activities in the mill construction to preserve the Company’s strong balance sheet.

 

Surface Infrastructure Completed

 

The Company has commissioned a 2,500 horsepower hoist and extended headframe. In addition, Rubicon has completed the construction of the required roads, a 200-person camp, a new power line and substation, the mill building, and the SAG and ball mill foundations.

 

Timeline to Projected Production

 

Rubicon believes that the main elements required to complete the Phoenix Gold Project are the completion of the mill construction, as well as the underground lateral and vertical development. The completion of the mill construction is the critical path. Management has deferred mill construction to preserve the Company’s balance sheet until it has secured the remaining financing to complete the Project. Rubicon has entered into a US$75 million gold stream agreement with Royal Gold and the Company estimates it will need to raise an additional US$100 million to complete the Project to potential production. Rubicon is currently evaluating financing alternatives with a strong focus on minimizing the Company’s cost of capital. We estimate projected gold production in approximately 12-14 months following the completion of additional financing.
 

“We are extremely pleased with the key construction milestones that we have achieved to-date,” stated Michael A. Lalonde, President and Chief Executive Officer of Rubicon. “The Company has completed a substantial amount of the required construction, further de-risking the Project.”

About Rubicon Minerals Corporation

 

Rubicon Minerals Corporation is an advanced stage gold development company. The Company is focused on responsible and environmentally sustainable development of its Phoenix Gold Project in Red Lake, Ontario. Gold production is projected to commence 12-14 months following the completion of the remaining financing. The Phoenix Gold Project is fully permitted for initial production at 1,250 tonnes per day. In addition, Rubicon controls over 100 square miles of prime exploration ground in the prolific Red Lake gold district which hosts Goldcorp’s high-grade, world class Red Lake Mine.

Posted February 11, 2014

Share this news article

MORE or "UNCATEGORIZED"


Azimut Drills 24.0 g/t Au over 18 m, including 38.7 g/t Au over 9 m, in the expanding Patwon Gold Zone, Elmer Property, Quebec

Azimut Exploration Inc. (TSX-V: AZM) is pleased to report that i... READ MORE

June 22, 2021

Opus One Obtains 6.02 g/t Gold Over 2.5 m and Brings to Light Its Gold Discovery Near Matagami

Opus One Gold Corp. Inc. (TSX-V:OOR) a mining exploration compan... READ MORE

June 22, 2021

Western Sierra Resource Corporation Enters Talks to Acquire Majority Stake in a Gold Mining Operation With Enhanced Recovery Net Income Projected at $3.2 Billion

WESTERN SIERRA RESOURCE CORPORATION (OTC: WSRC) is pleased to a... READ MORE

June 22, 2021

Maritime Resources Traces Orion North Zone Over 550 Metres - Intersects 12.43 gpt Gold and 2.15 gpt Silver Over 1.20 Metres, Including 50.60 gpt Gold and 7.90 gpt Silver Over 0.20 Metres

Maritime Resources Corp. (TSX-V: MAE) is pleased to announce dril... READ MORE

June 22, 2021

Labrador Gold Intercepts 50.38 g/t Over 1.85 Metres Including 160.42 g/t Over 0.55 Metres at Big Vein, Kingsway Project, Newfoundland

Labrador Gold Corp. (TSX-V:LAB) (OTCQX:NKOSF) (FNR: 2N6) is pleas... READ MORE

June 22, 2021

Copyright 2021 The Prospector News