Robex Achieves Commercial Production at the Kiniero Gold Project

You have opened a direct link to the current edition PDF

Open PDF Close
Uncategorized

Share this news article

Robex Achieves Commercial Production at the Kiniero Gold Project

 

 

 

 

 

Robex Resources Inc. is pleased to announce that it has achieved commercial production at its Kiniero Gold Project in Guinea, having satisfied the commercial production criteria under both its Senior Secured Facility Agreement with Sprott and the Guinea Mining Code.

 

Commercial production status was achieved following the first shipment of gold on 11 February 2026. The shipment comprised approximately 197 kilograms of gold, equivalent to 6,336 troy ounces.

 

Under the Guinea Mining Code, the date of first commercial production is defined as the earlier of either the completion of a sustained period of production above a prescribed threshold or the date of the first shipment for commercial purposes. The Company confirms that the shipment constitutes the date of first commercial production for Kiniero under the Code.

 

In addition, Robex confirms that all relevant commercial production requirements under its senior secured financing arrangements with Sprott have been satisfied.

 

As at the end of January 2026, and following the successful ramp up of operations, Kiniero had processed approximately 393,000 dry metric tonnes of ore at an average head grade of approximately 1.0 g/t Au. Metallurgical gold recovery averaged approximately 88%, with mill availability of over 92%. Gold recovered totalled approximately 10,900 troy ounces, with approximately 5,550 troy ounces poured, reflecting the normal buildup of gold inventory within the CIL circuit during commissioning and early operations.

 

CEO Comment

 

Matthew Wilcox, Managing Director and Chief Executive Officer of Robex, commented:

“The delivery of our first commercial gold shipment marks a major milestone for Robex and reflects the successful ramp-up of operations at Kiniero. The performance of both the processing plant and the operating team has been strong as we transition into commercial production.

 

With Kiniero now in commercial operation and generating cash flow, the asset is positioned to support the development of Bankan as part of our transformative merger with Predictive Discovery. This milestone reinforces the strategic rationale for the combination and our objective of building a leading multi-asset gold producer.”

 

Plant Operational Performance

 

Since commissioning and through to early February, the Kiniero processing plant has demonstrated stable and improving performance as operations progressed through ramp-up.

 

Key reconciled metrics for the month ended 31 January 2026 are shown below:

 

Kiniero Gold Operation, Guinea Units Jan-26
Operating metrics    
Ore processed dmt 392,678
Average head grade g/t Au 0.98
Metallurgical gold recovery % 87.9
Mill availability % 92.3
Mill operating time % 85.6
Gold recovered oz 10,931
Gold poured oz 5,547
Gold in circuit oz 7,725
     

Operational Performance Charts

 

Throughput increased progressively through January, with higher daily processing rates achieved toward month-end following the ball mill coming online in mid-January and reaching sustained operating capacity by 24 January 2026. CIL Train B was brought online on 23 January with active carbon loaded, and by 25 January all circuits were fully operational.

 

Improved plant stability and increased operating capacity contributed to higher throughput, while short term variability reflects normal commissioning and ramp up conditions.

 

Figure 1: Daily Dry Tonnes Processed and Throughput Rate

 

ABOUT ROBEX RESOURCES INC.

 

Robex Resources is a Canadian gold mining company listed on the TSX-V and ASX, and headquartered in Quebec, Canada. Robex’s material properties consist of the Nampala Project in Mali and the Kiniero Project in Guinea.

 

Posted February 16, 2026

Share this news article

MORE or "UNCATEGORIZED"


First Phosphate Receives Conditional Approval for up to $16.7 Million Non-Repayable Contribution from the Government of Canada

First Phosphate Corp. (CSE: PHOS) (OTCQX: FRSPF) (OTCQX ADR: FPHOY) (FSE: KD0) has been cond... READ MORE

March 3, 2026

Gold X2 Drills 117m of 1.21 g/t Au, Including 10m of 4.37g/t Au; High-Grade Zone Intersected 280m Beneath the Resource Pit Demonstrating Underground Potential at the Moss Gold Deposit

Gold X2 Mining Inc. (TSX-V: AUXX) (OTCQB: GSHRF) (FWB: DF8), is pleased to announce initial drilling... READ MORE

March 3, 2026

Tectonic Raises Over C$92 Million; Completes Upsized Private Placement With Full Over-Allotment Exercised

Tectonic Metals Inc. (TSX-V: TECT) is pleased to announce the successful closing of the Company’s ... READ MORE

March 3, 2026

Cerro de Pasco Resources Enters Project Development Funding Agreement with U.S. International Development Finance Corporation for Quiulacocha

Cerro de Pasco Resources Inc. (TSX-V: CDPR) (OTCQB: GPPRF) (BVL: CDPR) announces that it has ... READ MORE

March 2, 2026

NorthWest Announces Updated Mineral Resource at Kwanika Reflecting Strategic Shift to Higher-Grade Copper-Gold Focus

NorthWest Copper Corp. (TSX-V: NWST) is pleased to announce an updated mineral resource estimate for... READ MORE

March 2, 2026

Copyright 2026 The Prospector News