P2 Gold BAM Project Update

You have opened a direct link to the current edition PDF

Open PDF Close
Uncategorized

Share this news article

P2 Gold BAM Project Update

 

 

 

 

 

P2 Gold Inc. (TSX-V:PGLD) reports that the 2022 exploration program at its gold-copper BAM Project located in the Golden Triangle in northwest British Columbia is underway.

 

In late May crews mobilized for site preparation at BAM, clearing snow and caching fuel for the upcoming Z‐Tipper Axis Electromagnetic airborne geophysical survey. Camp construction has begun and is expected to be complete in the coming weeks. While camp construction is underway, crews will be based near Highway 37 approximately 45 kilometers to the southeast of BAM.

 

A diamond drill is planned to mobilize to BAM in two weeks to commence the 10,000-meter drill program. Drilling will focus on expanding the near-surface epithermal Monarch Gold Zone, first drilled in July 2021, where Hole BAM-003 intersected 2.63 g/t gold over 45.85 meters including 9.2 meters grading 7.30 g/t gold. Drilling will also test the Monarch Gold Zone at depth by targeting the feeder zone for the surface mineralization. The BAM 2022 drill program is expected to continue through the end of September.

 

The ZTEM airborne geophysical survey is planned to commence mid-June and will target the geological structures underlying the BAM Project, most importantly the potential feeder zone for the near-surface epithermal Monarch Gold Zone.

 

Quality Assurance

 

Ken McNaughton, M.A.Sc., P.Eng., Chief Exploration Officer, P2 Gold, is the Qualified Person, as defined by NI 43-101, responsible for the BAM Project. Mr. McNaughton has reviewed, verified and approved the technical information in this news release.

 

About P2 Gold Inc.

 

P2 is a mineral exploration and development company focused on advancing precious metals and copper discoveries and acquisitions in the western United States and British Columbia.

 

Posted June 9, 2022

Share this news article

MORE or "UNCATEGORIZED"


Santacruz Reports Q1 2026 Production of 1,341,499 Ounces of Silver and 21,640 Tonnes of Zinc, with Continued Recovery of Production at Bolivar Mine

Santacruz Silver Mining Ltd. (NASDAQ:SCZM) (TSX-V:SCZ) announces that total production in the first ... READ MORE

April 17, 2026

Greenland Government Approves Transfer of Final 50.5% of Tanbreez, Taking Critical Metals Corp. to 92.5% Ownership

Critical Metals Corp. (Nasdaq: CRML), a leading critical mineral mining company, today announced tha... READ MORE

April 17, 2026

NMG Announces Closing of US$96.5 Million Equity Public Offering

As part of the financing package for the phased development of the commercial operations of its Mata... READ MORE

April 16, 2026

Group Eleven Drills 23.5m of 12.3% Zn+Pb and 46 g/t Ag, Further Confirms Deeper Cu-Ag Mineralization and Extends Mineralized Strike by 600m to 3.2km

Group Eleven Resources Corp. (TSX-V: ZNG) (OTCQB: GRLVF) (FSE: 3GE) is pleased to announce new assay... READ MORE

April 16, 2026

Argenta Silver Step-Out Drilling Intersects 679 g/t Ag over 13.5m, including 1,163 g/t Ag over 4.0m, Resource Continuity and Expansion Continues

Argenta Silver Corp. (TSX-V: AGAG) (OTCQX: AGAGF) (FSE: T1K) is pleased to report the third set of ... READ MORE

April 16, 2026

Copyright 2026 The Prospector News