NorthWest Copper Corp. (TSX-V: NWST) (OTCQX: NWCCF) is pleased to announce the results of the preliminary economic assessment, conducted by Ausenco Engineering Canada Inc. (“Ausenco”) and Mining Plus Canada Consulting Ltd on its 100% owned Kwanika-Stardust Project comprising the Kwanika and Stardust deposits. This represents the first technical and economic evaluation of the combined deposits outlining a robust project with manageable initial capital cost and multiple opportunities for project growth. NorthWest plans to continue to evaluate the possibility of further synergies with nearby deposits and the proposed Project infrastructure, with a particular focus on the nearby 100% owned Lorraine Project1.
The 2023 PEA outlines a project that proposes mining approximately 96 million tonnes of material in a combination of open pit and underground operations from the Company’s 100% owned Kwanika and Stardust deposits. The 2023 PEA contemplates a 22,000 tonnes per day process plant, producing high-quality copper concentrate with significant gold and silver by-product credits.
Highlights
Table 1: Summary Project Metrics
Production Per Year | AISC | Economics | |||||||||
Cu (Mlbs) |
Au (koz) |
Ag (koz) |
CuEq10 (Mlbs) |
Cu (US$/lb) |
CuEq (US$/lb) |
Initial Capital (C$M) |
Total Operational11 ATCF (C$M) |
After- Tax NPV-7 (C$M) |
After- Tax IRR % |
||
LOM Average |
58.31 | 67.43 | 269.12 | 90.56 | $1.12 | $2.01 | $567.90 | $1,324.98 | $215.04 | 12.7% | |
“This study is a major step in demonstrating the value created by combining Kwanika and Stardust, the cornerstone deposits of the NorthWest portfolio,” stated President and CEO Peter Bell. “We have been describing a project with manageable initial capital and significant copper production to the market since creating the Company in 2021. This PEA supports that vision. We are also now working towards advancing the Project including exploring whether the nearby 100% owned Lorraine Project, located approximately 40 km away, can be developed with the infrastructure contemplated in the Kwanika-Stardust PEA. Conducting the necessary studies to ascertain whether Lorraine can be incorporated into the Kwanika-Stardust project will be the main objective of the Company in 2023, as we believe that this will add further value to the strong project we have outlined with this PEA.”
“The focus in Canada is turning to critical minerals, including copper,” continued Mr. Bell. “Our project is extremely well located, has both meaningful scale and manageable capex, benefits from existing infrastructure, has access to renewable power and is in a Tier 1 jurisdiction making it rare and highly valuable. We look forward to working collaboratively with First Nations to advance the project as part of BC and Canada’s push for critical Canadian copper production.”
Mineral Resources
Mineral Resources for Kwanika have been updated with parameters from the 2023 PEA. Stardust is also updated to reflect refined operating and capital costs. Mineral Resources at Kwanika Central are 95% in the Measured and Indicated categories, reflecting the amount of drilling and geological data that have been completed in this area. Kwanika South and Stardust represent areas for both further growth of Mineral Resources as well as conversion of Inferred Resources to Measured and Indicated Resources. The quantity of mineralized material was estimated and included in the mine plan using a Net Smelter Return (“NSR”) threshold approach, alternately called economic cut off, rather than a copper cut-off grade.
Table 2: Combined summary resource estimate12
Kwanika Central | |||||||||
Open Pit | Economic Cut-Off US$/t |
Classification | Tonnes (Mt) | Cu (%) | Au (g/t) |
Ag (g/t) |
Cu (Mlbs) |
Au (koz) |
Ag (koz) |
8.21 | Measured | 30.7 | 0.31 | 0.31 | 1.05 | 210.8 | 310.5 | 1,041.7 | |
Indicated | 35.9 | 0.22 | 0.19 | 0.80 | 174.9 | 222.0 | 923.9 | ||
M&I | 66.6 | 0.26 | 0.25 | 0.92 | 385.7 | 532.5 | 1,965.6 | ||
Inferred | 4.1 | 0.15 | 0.15 | 0.58 | 13.8 | 20.1 | 77.3 | ||
Underground | Economic Cut-Off US$/t |
Classification | Tonnes (Mt) | Cu (%) | Au (g/t) |
Ag (g/t) |
Cu (Mlbs) |
Au (koz) |
Ag (koz) |
16.41 | Measured | 25.6 | 0.50 | 0.61 | 1.62 | 284.4 | 501.3 | 1,332.6 | |
Indicated | 11.3 | 0.51 | 0.65 | 1.56 | 126.2 | 236.7 | 565.1 | ||
M&I | 36.8 | 0.51 | 0.62 | 1.60 | 410.6 | 738.0 | 1,897.8 | ||
Inferred | – | – | – | – | – | – | – | ||
Kwanika South | |||||||||
Open Pit | Economic Cut-Off US$/t |
Classification | Tonnes (Mt) | Cu (%) | Au (g/t) |
Ag (g/t) |
Cu (Mlbs) |
Au (koz) |
Ag (koz) |
8.21 | Inferred | 25.4 | 0.28 | 0.06 | 1.68 | 155.0 | 52.4 | 1,373.9 | |
Stardust | |||||||||
Underground | Economic Cut-Off US$/t |
Class | Tonnes (Mt) | %Cu | g/t Au | g/t Ag | Cu (Mlbs) |
Au (koz) |
Ag (koz) |
88.00 | Indicated | 1.6 | 1.49 | 1.63 | 30.1 | 52.2 | 83.1 | 1,536.4 | |
Inferred | 4.1 | 1.00 | 1.38 | 22.8 | 90.0 | 181.1 | 3,004.3 |
2023 PEA Summary
The 2023 PEA includes capital and operating costs for a potential Kwanika-Stardust mine; as well as recovery assumptions, metal prices and a mine plan for the combined Project. The 2023 PEA was developed in accordance with National Instrument 43-101 – Standards of Disclosure for Mineral Projects (“NI 43-101”) by Ausenco and Mining Plus, using historical and the latest 2022 metallurgical testing data performed by SGS Minerals, ALS Metallurgy, Bureau Veritas Commodities, and Base Metallurgical Laboratories Ltd (“Base Met”), with further details on the historic data used shown in the Database section below. The Company plans to file the complete 2023 PEA NI 43-101 technical report under the Company’s SEDAR profile at www.sedar.com within 45 days of this news release.
The 2023 PEA will supersede the previous PEA on the Kwanika deposit13 and updates the previous Mineral Resource estimate on the Kwanika deposit14. The 2023 PEA also updates the previous Mineral Resource estimate on the Stardust deposit15. The table below summarizes the key findings of the 2023 PEA.
Table 3: 2022 PEA Economic Highlights
Base Case Economics | Units | Pre-Tax | After-tax |
NPV (7%) | C$M | $440.10 | $215.04 |
NPV (7%) | US$M | $339.83 | $166.05 |
IRR | % | 17.1% | 12.7% |
Initial Capital | C$M | $567.90 | |
Sustaining Capital | C$M | $282.43 | |
Growth Capital16 | C$M | $493.27 | |
Economic Assumptions | Units | Base Case | |
Copper | US$/lb | $3.63 | |
Gold | US$/oz | $1,650.00 | |
Silver | US$/oz | $21.50 | |
Financial Metrics | Units | LOM | |
Average Annual Revenue | C$M | $425.70 | |
Average Annual Operating Costs | C$M | $185.03 | |
Avg. Ann. Free Cash Flow (after tax) | C$M | $111.29 |
The 2023 PEA is preliminary in nature and includes Inferred Mineral Resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as Mineral Reserves. There is no certainty that the Project described in the 2023 PEA will be realized. Table 4 provides a summary of key operating metrics from the 2023 PEA:
Table 4: 2023 PEA Operating Highlights
Operating Statistics | Units | Avg. LOM |
Mine Life | Years | 11.9 |
Tonnes Processed | ktpa | 7,967.3 |
Strip Ratio17 | W:O | 1.79 |
Production (per year) | ||
Copper | Mlbs | 58.31 |
Gold | koz | 67.43 |
Silver | koz | 269.12 |
CuEq | Mlbs | 90.56 |
Recoveries – Open Pit | ||
Copper | % | 84.3 |
Gold | % | 60.0 |
Silver | % | 57.8 |
Recoveries – Underground | ||
Copper | % | 89.7 |
Gold | % | 71.4 |
Silver | % | 70.3 |
Operating Costs | ||
Cash Cost – Cu with by-products | US$/lb | $0.44 |
Cash Cost – CuEq | US$/lb | $1.58 |
AISC – Cu with by-products | US$/lb | $1.12 |
AISC – CuEq | US$/lb | $2.01 |
Economic Sensitivity
Tables 5 and 5a below summarizes the pre-tax and after-tax sensitivities of NPV and IRR to metal prices:
Table 5 – Economic Sensitivity to Metal Prices (C$M, pre-tax)18
Metal Prices | NPV (5%) | NPV (7%) | NPV (10%) | IRR (%) |
Spot | $860.83 | $665.55 | $439.95 | 21.7% |
52 Week high | $1,490.45 | $1,207.90 | $878.64 | 31.9% |
Base Case + 20% | $1,281.04 | $1,027.91 | $733.40 | 28.6% |
Base Case + 10% | $940.35 | $734.01 | $495.28 | 23.0% |
Base Case | $599.67 | $440.10 | $257.16 | 17.1% |
Base Case – 10% | $258.99 | $146.19 | $19.04 | 10.6% |
Base Case – 20% | -$81.70 | -$147.72 | -$219.08 | 3.1% |
Table 5a – Economic Sensitivity to Metal Prices (C$M, after tax)
Metal Prices | NPV (5%) | NPV (7%) | NPV (10%) | IRR (%) |
Spot | $499.11 | $363.32 | $207.06 | 16.4% |
52 Week high | $904.75 | $715.05 | $494.60 | 24.7% |
Base Case + 20% | $769.84 | $598.31 | $399.37 | 22.0% |
Base Case + 10% | $550.47 | $407.87 | $243.51 | 17.5% |
Base Case | $329.13 | $215.04 | $84.88 | 12.7% |
Base Case – 10% | $104.23 | $18.12 | -$78.27 | 7.5% |
Base Case – 20% | -$129.04 | -$187.15 | -$249.39 | 1.9% |
Sustainability
Advancement of the Kwanika-Stardust Project is aligned with supplying critical mineral production, especially copper, in Canada. Collaboration with First Nations is a key part of our effort. The Project would be designed to have meaningful metal production while minimizing the Project’s environmental footprint.
The Project is in an area of British Columbia with existing infrastructure, hydroelectric power and a local workforce supporting our programs. Environmental, social and governance (ESG) performance is core to NorthWest’s longer-term goal to contribute to sustainable economies and encourage and promote cultural and environmental stewardship. The Company has taken a step towards our goals by completing a comprehensive 2021 ESG report19 in 2022, which gives NorthWest a strong baseline to track and demonstrate ESG progress.
Development of the Project may create many opportunities to bring needed resources to meet the demands of society and the changing economy. However, development of the Project will also impact the environment, First Nations and local communities. There are opportunities to build on traditional and local knowledge to manage these potential impacts and to put systems in place that support a better understanding of the land, and to encourage and support stewardship. In addition, by working collaboratively with First Nation communities and leadership we see opportunities to build and support the development of stronger local economies.
NorthWest envisions a future of shared values, where partnerships with local communities drive a new kind of mining where the rights of First Nations are recognized and stewardship of the environment and cultural heritage form the foundation of future development. As a Company we will strive to pursue best practices as we advance the Project beyond the 2023 PEA.
Next Steps
With completion of the 2023 PEA, NorthWest intends to continue to advance its portfolio of projects. Key next steps are expected to include:
Opportunities
In addition, to the next steps noted above, the Company is actively exploring several additional opportunities which the Company hopes will enhance Project value. These include:
Mining
Preliminary mine designs have been developed for the Project based upon the Mineral Resource estimates for Kwanika-Stardust. Resource models were imported to Minesight® mine planning software where a Lerch Grossman algorithm was applied to a NSR model to determine possible open pit limits.
The mine plan was developed to mine 95.6 Mt of mineralized material and 86.9 Mt of waste over the LOM (shown in Figure 1). Mineralized material will be mined from four areas: Kwanika Central open pit (years 1-4), Stardust underground (years 4-9), Kwanika Central underground block cave (years 4-12) and Kwanika South open pit (years 9-12). Further detail on the Kwanika Central open pit and underground is shown in Figures 2 and 3, the underground development plan at Stardust is shown in Figure 4, and detail on the Kwanika South open pit is shown in Figure 5.
Table 6: Key mining statistics
Metric | Units | Quantity |
Mine Life | Years | 11.9 |
Milling Rate | tpd | 22,000 |
Strip Ratio21 | W:O | 1.79 |
Total Tonnage Mined | kt | 182,533 |
Total Mineralized Material Mined | kt | 95,607 |
LOM Average Grades | ||
Copper | % | 0.39 |
Gold | g/t | 0.39 |
Silver | g/t | 2.21 |
CuEq22 | % | 0.62% |
Table 6a: Mining Detail
Description | Mineralized Material (Mt) |
Waste (Mt) |
Kwanika Central Open Pit | 29.41 | 55.21 |
Kwanika South | 19.05 | 31.71 |
Kwanika Block Cave | 44.04 | – |
Stardust | 3.11 | – |
Total | 95.61 | 86.93 |
The total resources processed in the conceptual mine plan are shown in the following tables. The quantity of mineralized material was estimated and included in the mine plan using an NSR threshold approach, rather than a copper cut-off grade. Mine operating costs are summarized in Table 7.
Table 7: Mining Costs
Area | Kwanika Central Open Pit (C$/t mined) |
Kwanika Underground (C$/t mined) |
Stardust Underground (C$/t mined) |
Kwanika South Open Pit (C$/t mined) |
Total Mining Cost | 2.88 | 10.62 | 111.32 | 2.95 |
Processing
The 2023 PEA contemplates a concentrator and related facilities processing mineralized material at a nominal rate of 22,000 tpd through a grinding circuit comprising one SAG mill and one ball mill, flotation facilities, regrind facilities, and thickening and filtration to produce copper concentrates for export (Figure 6). Gold and silver will report to the copper concentrate. Processing costs are summarized in Table 8 below.
Table 8: Mineral Processing
Area | Units | Unit Cost |
Reagents & Consumables | C$/t processed | 4.19 |
Maintenance | C$/t processed | 0.32 |
Power | C$/t processed | 1.87 |
Labor | C$/t processed | 1.75 |
Total processing Cost | C$/t processed | 8.13 |
Tailing Storage Facility
The TSF has been designed to accommodate over 96.3 Mt of tailings produced over the life of mine. The proposed TSF will be located in a valley east of the Stardust Deposit and upstream of the process plant site. The site drains to the northwest and southeast requiring two embankments to contain slurry tailings. Runoff above the facility will diverted around the facility in channels and perimeter access roads, which allows for simple access by the tailings deposition lines and water reclaim system. The TSF will be constructed using a shell of non-acid generating waste rock with an upstream impermeable layer. The construction of the TSF will utilize downstream construction methodology along with being built in multiple phases to ensure safety and long-term containment of the tailings. The facility is designed in accordance with Canadian Dam Association guidelines (2019) and Part 10 of the Health, Safety and Reclamation Code for Mines in British Columbia (2016).
Metallurgy
Metallurgical test work was undertaken in 2022 by BaseMet to test the viability of blending material from Kwanika and Stardust. Historical metallurgical testing data performed by SGS Minerals, ALS Metallurgy, and Bureau Veritas Commodities, was also included. Ausenco reviewed and interpreted the test work and incorporated the results into the process plant design criteria, flowsheet development, and process equipment selection. The design basis for the processing plant is 22,000 tpd at 92% availability. Design mineral grades to the process plant are estimated at 0.80% copper and 0.80 g/t gold to account for feed grade variability, and the estimated recoveries for open pit are 84.3% for copper, 60.0% for gold, and 57.8% for silver, and for underground are 89.7% for copper, 71.4% for gold, and 70.3% for silver.
Operating Cost Summary
The operating cost estimate for the 22,000 tpd operation was estimated at $23.04/t. A breakdown of total site operating costs is summarized in Table 9:
Table 9: Total Site Operating Costs
Area | Units | Cost |
Mining Cost | C$/t processed | 12.63 |
Processing | C$/t processed | 8.13 |
G&A | C$/t processed | 2.28 |
Total Site Operating Cost | C$/t processed | 23.04 |
Capital Cost and Infrastructure Summary
The capital cost estimate was developed by Ausenco using an EPCM project development approach. Ausenco estimated the initial and sustaining capital cost based on the mining costs provided by Mining Plus, major process equipment quotes from vendors, and other costs from an Ausenco database of historical projects. The mine plan and associated mine initial, growth and sustaining capital were prepared by Mining Plus using current equipment prices and leasing terms and conditions provided by a mine equipment procurement consultant retained by NorthWest. Growth Capital is capital associated with brining new areas of mineralized material into production – namely the Kwanika underground block cave and Stardust underground. The process facilities and other related facilities were designed and estimated by Ausenco. The capital cost of these facilities was developed using budgetary quotes obtained for major process and infrastructure facility equipment requirements, and construction labour rates obtained from Ausenco’s database of projects in British Columbia. The 2023 PEA capital cost estimate is summarized in Table 10 below.
Table 10: Capital Cost Summary (in millions)
Area | Initial Capital | Sustaining Capital |
Growth Capital |
C$ | C$ | C$ | |
Mining | 65.76 | 151.40 | 393.31 |
Process Plant | 198.02 | 0.00 | 0.00 |
Additional Process Facilities | 6.41 | 5.60 | 0.00 |
On-Site Infrastructure | 21.61 | 4.90 | 0.00 |
Off-Site Infrastructure | 82.53 | 78.50 | 0.00 |
Project Preliminaries | 28.42 | 2.10 | 0.00 |
Project Delivery | 50.36 | 2.10 | 0.00 |
Owner’s Costs | 33.68 | 27.34 | 99.96 |
Provisions | 81.09 | 10.50 | 0.00 |
Total | 567.90 | 282.43 | 493.27 |
Economic Analysis
Economic evaluations were generated incorporating forecasts for economic inputs using the Base Case and Spot Price. The Spot Price case is based on prices as of January 3, 2023. See Table 11 for the results of the economic analysis.
The 2023 PEA is preliminary in nature. It includes inferred Mineral Resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as Mineral Reserves and there is no certainty that the 2023 PEA will be realized.
Table 11: Project Economics
Parameter | Unit | Base Case | Spot Price | 52 Week High |
Copper Price | US$/lb | $3.63 | $3.83 | $4.94 |
Gold Price | US$/oz | $1,650.00 | $1,840.00 | $1,790.00 |
Silver Price | US$/oz | $21.50 | $23.97 | $23.30 |
CAD:USD Exchange Rate | US$/CAD$ | 0.77 | ||
Average Annual Revenue | C$ million | $425.7 | $458.3 | $537.4 |
Economic Result (pre-tax) | ||||
Avg. Free Cash Flow (“FCF”) | C$ million | $148.1 | $180.6 | $259.8 |
NPV (5%) | C$ million | $599.7 | $860.8 | $1,490.4 |
NPV (7%) | C$ million | $440.1 | $665.6 | $1,207.9 |
NPV (10%) | C$ million | $257.2 | $439.9 | $878.6 |
IRR | % | 17.1% | 21.7% | 31.9% |
Payback | Years | 5.99 | 5.55 | 4.67 |
Economic Result (after-tax) | ||||
Avg. FCF | C$ million | $111.3 | $132.0 | $182.2 |
NPV (5%) | C$ million | $329.1 | $499.1 | $904.8 |
NPV (7%) | C$ million | $215.0 | $363.3 | $715.0 |
NPV (10%) | C$ million | $84.9 | $207.1 | $494.6 |
IRR | % | 12.7% | 16.4% | 24.7% |
Payback | Years | 6.37 | 5.86 | 5.11 |
Database
The database used for the Kwanika Central Mineral Resource estimate comprises collar, survey, assay, lithology, alteration, density, and structural information for exploration drilling conducted between 2006 and 2021. Drilling on the Central Zone totaled 76,156m in 166 holes.
The database used for the Kwanika South Mineral Resource estimate comprises collar, survey, assay, lithology, alteration, density, and structural information for exploration drilling conducted between 2006 and 2021. Drilling on the South Zone totaled 19,099 m in 62 holes.
The database used for the Stardust Mineral Resource estimate contains 206 drill holes representing 74,253 m of drilling up to and including holes drilled in 2020. It comprises collar, survey, assay, lithology, alteration, density, and structural information. Fifty-eight of these holes (38,329 m) were completed between 2018 and 2020 by Sun Metals.
Quality Assurance and Quality Control
Kwanika
An independent assay Quality Assurance/Quality Control program has been in place throughout the drilling campaigns carried out by Serengeti and Northwest Copper since 2006. Control samples have included Certified Reference Materials pulp blanks, and quarter-core twin samples (field duplicates).
CRMs were prepared by CDN Resource Labs Ltd. (CDN) of Langley, BC or by Ore Research & Exploration P/L in Australia. Most of the standards used are certified for both copper and gold values. Two standards are not certified for gold and are deemed “Provisional”. Blank material comprised packets of pulverized barren material. The 2020-2021 drilling campaign used a certified blank, also prepared by CDN. Pulp blanks are used to assess contamination during assaying. During 2021, a small number of coarse blanks (unmineralized garden stone) were used to assess contamination during preparation.
Twin samples were produced by cutting the initial core sample interval in half and leaving one half in the core box. The half to be sent to the laboratory for analyses was then quartered by cutting each piece in half again and putting one quarter of the core in one sample bag and the other quarter of the core in a separate sample bag. Twin samples are generally used to assess sampling precision and mineralization homogeneity.
A full report on QA/QC will be available in the 2023 PEA technical report.
Stardust
Diamond drill core samples had standard and blank reference material inserted into the sampling series at regular intervals. Field duplicates were also taken at regular intervals. In sections of high-grade mineralization, the frequency of insertion of reference material and field duplicates was increased. Additional reference material samples and field duplicates were also added at the discretion of the logging geologist on site. The results indicated no significant problems with the laboratory analysis.
Correlation between field duplicate core samples is generally strong. Increased variability is noted in returned gold and silver analytic results <1 ppm. Minor variability is noted in copper results throughout the range of returned results. These inconsistencies are interpreted to be due to the irregular nature of mineralization in skarn and CRD systems and local relative coarseness of commodity bearing minerals in these systems.
A full report on QA/QC will be available in the 2023 PEA technical report.
Technical Report and Qualified Persons
A technical report prepared in accordance with NI 43-101 with respect to the 2023 PEA will be filed under the Company’s SEDAR profile at www.sedar.com within 45 days of this news release.
Technical aspects of this news release have been reviewed, verified, and approved by Tyler Caswell P.Geo., Vice President Exploration of NorthWest, who is a qualified person as defined by NI 43-101. Mr. Caswell confirms that there were no limitations from the Company in verifying the drilling and sample data underlying the Mineral Resource estimates which were verified through site visit observations and data review.
The following qualified persons contributed to the 2023 PEA:
Figure 1: Mining Production Profile
https://www.globenewswire.com/NewsRoom/AttachmentNg/477a394b-d06d-4e61-8922-7f79f373d31e
Figure 2: Kwanika Central Open Pit
https://www.globenewswire.com/NewsRoom/AttachmentNg/290fa02e-b821-4eb1-8a7e-9cd1200e40a8
Figure 3: Kwanika Central Underground
https://www.globenewswire.com/NewsRoom/AttachmentNg/e7b2935e-951b-45cc-833e-c960e6966757
Figure 4: Stardust Underground
https://www.globenewswire.com/NewsRoom/AttachmentNg/a24fdc06-3720-4ef3-82f6-f5662dbfae62
Figure 5: Kwanika South Open Pit
https://www.globenewswire.com/NewsRoom/AttachmentNg/2c29b2c6-be59-4d18-864e-13caaf2b0336
Figure 6: Process Flow Diagram:
https://www.globenewswire.com/NewsRoom/AttachmentNg/1540199d-0e7e-49af-9729-23c46f9ff469
About NorthWest Copper:
NorthWest Copper is a new copper-gold explorer and developer with an exciting pipeline of projects in British Columbia. With a robust portfolio in a tier one jurisdiction, NorthWest Copper is well positioned to participate fully in a strengthening global copper market. We are committed to responsible mineral exploration which involves working collaboratively with First Nations to ensure future development incorporates stewardship best practices and traditional land use.
Flying Nickel Mining Corp. (TSX-V: FLYN) (OTCQB: FLYNF) is please... READ MORE
Big Ridge Gold Corp. (TSX-V: BRAU) (OTCQB: ALVLF) is pleased to a... READ MORE
First Phosphate Corp (CSE: PHOS) (OTC: FRSPF) (FSE: KD0) is pleas... READ MORE
LaFleur Minerals Inc. (CSE: LFLR) (OTC Pink: WPNNF) is pleased to... READ MORE
Foran Mining Corporation (TSX: FOM) (OTCQX: FMCXF) is pleased to ... READ MORE