Monument Delays Start-up of Iron and Copper Project at Mengapur

You have opened a direct link to the current edition PDF

Open PDF Close
Uncategorized

Share this news article

Monument Delays Start-up of Iron and Copper Project at Mengapur

 

 

 

 

 

Monument Mining Limited (TSX-V:MMY) (FSE:D7Q1) announces that it will delay the start-up of producing iron and copper metal at the Mengapur Polymetallic Project in Pahang State, Malaysia until further notice due to depressed and volatile commodity prices. The main plant at the Mengapur site will be put on care and maintenance while some work will continue at a reduced level.

 

 

Project Progress

 

 

The Company has been refurbishing and upgrading its 1,000 tpd pilot plant at Mengapur and has made considerable progress in this regard. The plant including the ball mills have been overhauled and successfully run, all lines have either been cleaned out or replaced and both mills are in satisfactory operational condition to run as a pilot operation which is the first stage of the project. A tailings storage dam for copper and iron process tailings has been emptied, cleaned up, lined, and compacted with impervious clay ready for use. A new pyrrhotite storage dam has been constructed, lined and compacted ready to store this material, a bi-product from producing saleable iron.

 

 

There has been no change in the situation regarding the issue of the Star Destiny mining lease application and no communication from the Pahang State Government as to the official situation surrounding the matter has been received as previously advised to the market. The company is waiting for news from the Pahang State Government to enable it to make decisions on which way to develop the main project. In the meantime no further work can be undertaken on producing a new and compliant 43-101 or a preliminary economic assessment (“PEA”).

 

 

Background

 

 

When the Company acquired the project, saleable grade of Fe 62.5% iron was selling at prices far in excess of the price today. At the time the price was in the range of US$140 per tonne or higher. Due to the recent and sustained fall in iron prices globally last year the Company changed course and commenced re-engineering its 1,000 tonnes per day pilot plant to be able to accommodate production of both iron and copper. The purpose was forward planning based on the main hard rock sulphide ore body containing both iron and copper among other metals. The hard rock ore requires a more complex flow sheet and recovery circuit than the iron contained in free digging soils some of which is overburden waste.

 

 

However, following a number of adverse events including the dramatic drop in the global iron ore price, the falling copper price, the build-up of global inventories in these two metals and general resource market price pressure together with price volatility Monument has been working to try and off-set these events. These events create great uncertainty, especially so when extensive capital investment is required to build a large mining project. The risk profile of the project increases considerably under these conditions. These conditions include the ability to raise project finance funds due to increased risk, volatile and declining metal prices, in an environment of increasing metal inventories. In addition, the Company observes that the major suppliers of iron ore to China, the largest consumer in the world market by far, have been investing large amounts of capital toward increasing production capacity.

 

 

They offset reduced market selling price and return per unit of production with increased production volume to maintain total gross revenue. The large companies produce and ship many millions of tonnes per year.

 

 

Going Forward

 

 

As a result of this interruption in the iron ore market, Monument has been focusing on copper which whilst suffering declines in market price, maintains a reasonable price and margin for many producers, we believe including Monument. Furthermore, demand is predicted to exceed supply by 2018. Therefore the Company will maintain its SGS operated site analytical laboratory that performs 2,000 assays per month. Site security, site maintenance including maintaining all environmental obligations, mining regulatory reporting and compliance, accommodation and messing for key staff to enable them to operate site maintenance functions and allow this important work to continue as well as the laboratory continuing to turn out assays for the Selinsing exploration program, the Selinsing process plant control assays as well as provide assay and R&D support to both the Selinsing and Mengapur Research and Development laboratories.

 

 

In parallel with these developments, the Company will be looking at the best way to introduce programs using Intec technology recently acquired by way of a license for South East Asia to use the technology to produce close to LME grade copper metal and a range of other base metals from Mengapur material. The technology can potentially produce a copper metal product on site without having to export a copper concentrate. This has a considerable cost saving advantage in producing copper metal including storage shipping and handling, insurance and other soft costs (Including application for a tax exemption opportunity).

 

 

As well as looking at the technology and its application relating to copper, Monument will be investigating the local demand for copper metal within Malaysia in applications that manufacture copper pipes, wires and other copper value added products. The Company believes this could potentially improve the economics of the project considerably in the present environment. (See updated PowerPoint presentation on Company website)

 

 

About Monument

 

 

Monument Mining Limited is an established Canadian gold producer that owns and operates the Selinsing Gold Mine in Malaysia. Its experienced management team is committed to growth and is advancing several exploration and development projects including the Mengapur Polymetallic Project, in Pahang State of Malaysia, and the Murchison Gold Projects comprising Burnakura, Gabanintha and Tuckanarra in the Murchison area of Western Australia. The Company employs over 300 people in both regions and is committed to the highest standards of environmental management, social responsibility, and health and safety for its employees and neighboring communities.

 

Posted February 27, 2015

Share this news article

MORE or "UNCATEGORIZED"


First Phosphate Intersects 92.5 m of 11.82% Igneous Phosphate Starting at Surface at Its Begin-Lamarche Project in Saguenay-Lac-St-Jean, Quebec, Canada

First Phosphate Corp. (CSE: PHOS) (OTC: FRSPF) (FSE: KD0) is plea... READ MORE

April 23, 2024

Kuya Silver Provides Update on Mine Start-up and Uncovers New Major Silver-Mineralized Vein Zone South of the Bethania Mine, Peru

Kuya Targeting Commencement of Production at Bethania in H1 2024 ... READ MORE

April 23, 2024

Silvercorp Reports Operational Results and Financial Results Release Date for Fiscal 2024, and Issues Fiscal 2025 Production, Cash Costs, and Capital Expenditure Guidance

Silvercorp Metals Inc. (TSX: SVM) (NYSE American: SVM) reports pr... READ MORE

April 23, 2024

Lithium Ionic Expands Newly Discovered Zone at Salinas; Drills 1.53% Li2O over 15m, incl. 2.31% Li2O over 8m; 1.15% Li2O over 19m, incl. 1.67% Li2O over 10m, and 1.32% Li2O over 14m

Excellent follow-up drill results from high-grade discovery holes... READ MORE

April 23, 2024

Solaris Reports First Drilling Results from 2024 Program and Exploration Update, Including 150m of 0.67% CuEq within 384m of 0.51% CuEq and 284m of 0.53% CuEq from Near Surface

Solaris Resources Inc. (TSX: SLS) (NYSE: SLSR) is pleased to repo... READ MORE

April 23, 2024

Copyright 2024 The Prospector News