Monarques Gold’s Wasamac Feasibility Study Shows Positive Pre-Tax 23.6% IRR and Production Cash Costs of $720 Per Ounce (US$550 Per Ounce)

 

 

 

 

 

MONARQUES GOLD CORPORATION (TSX: MQR) (OTCMKTS: MRQRF) (FRA: MR7) is pleased to report positive results from the feasibility study prepared by BBA Inc. for the Wasamac Gold project, located 15 km west of Rouyn-Noranda, in Abitibi, Quebec. The purpose of this FS was to complete a review and compilation of the resources re-qualified in October 2017 by Roscoe Postle Associates Inc. incorporate advanced mining designs by integrating the Rail-Veyor® technology and a paste backfill system, investigate processing options, tailings and water management facilities and assess the economics of this underground gold project. The technical report summarizing the results of the FS can be found on the Monarques website via the following link: Wasamac 2018 feasibility study.

 

The results of the FS show that Wasamac is an economically viable project that is expected to be a low-cost producing mine. The FS also provides the basis for making a production decision and serves to fully support the permitting and financing processes.

 

“As evidenced by these results, the Wasamac Gold project has the makings of a great gold mine,” said Jean-Marc Lacoste, President and Chief Executive Officer of Monarques. “The feasibility study is based on a top-down mining approach and the use of the Rail-Veyor® system through a twin-ramp access and haulage facility, which eliminates the hefty initial capital expenditures associated with building a shaft, increases flexibility in mine planning, shortens the timeline to production and allows us to significantly decrease the overall cost of the project. We also believe that we will be able to extend the Wasamac mine life, as the deposit remains largely underexplored at depth and along strike.

 

“In the last few weeks, we have created a confidential virtual data room to provide access for those who have expressed an interest in reviewing the data and participating in the project’s development. We have since seen considerable interest from the mining and investment community and are positive about the upside of these new results for Monarques.” 

 

“This feasibility study also leaves the door open to a potential custom milling option. Eliminating the cost of building a mill and a tailings facility would reduce the initial CAPEX by about $230 million, which could potentially increase the project’s internal rate of return and decrease the payback period. Furthermore, the mine infrastructure will be strategically located on our newly acquired land next to the Trans-Canada highway and 200 metres from the railway leading to all the main regional custom milling facilities. We will study all possible options to put the Wasamac Gold project into production in the best interests of our shareholders,” concluded Mr. Lacoste. 

 

FS HIGHLIGHTS

 

 

Description Unit Value
Long term gold price US$/oz 1,300
Exchange rate C$:US$ 1.31
Total tonnes mined M Tonnes 21.5
Average diluted gold grade g/t 2.56
Average gold recovery rate % 88.2
Total gold contained koz 1,767
Total gold production koz 1,558
Average annual gold production  oz per year 142,000
Mine life year 11
Production cash costs $/oz 720
Production cash costs US$/oz 550
All-in sustaining costs (AISC) $/oz 826
All-in sustaining costs (AISC) US$/oz 630
Estimated capital expenditure    
Total preproduction capital cost $M 464
Sustaining capital $M 175
Site restoration cost $M 6
Salvage value $M (16)
Pre-tax summary    
NPV (5%) $M 522
IRR % 23.6
Payback period years 3.6
After-tax summary    
NPV (5%) $M 311
IRR % 18.5
Payback period years 3.9

 

 

SENSITIVITY ANALYSIS

 

The project’s sensitivity to the price of gold shows that an increase of just 20% in the price of gold brings the pre-tax NPV close to $900 million and the IRR above 30%. Concurrently, a drop in the price of gold of 20% would keep the project comfortably above the break-even level of $925 and the IRR would still post a low double-digit return.

 

Pre-tax NPV 5%

 

 

CAD:USD Gold Price (US$/oz)
$1,000 $1,100 $1,200 $1,250 $1,300 $1,400 $1,500 $1,600
1.11 (109.2) 9.2 127.6 186.8 246.0 364.4 482.8 601.2
1.18 (39.6) 85.8 211.2 273.9 336.5 461.9 587.3 712.7
1.25 38.8 172.0 305.2 371.8 438.4 571.6 704.8 838.0
1.31 102.7 242.3 381.9 451.7 521.5 661.1 800.7 940.3
1.43 229.1 381.3 533.6 609.7 685.8 838.0 990.3 1,142.5
1.54 346.2 510.1 674.1 756.1 838.0 1,002.0 1,165.9 1,329.9
1.67 482.8 660.4 838.0 926.8 1,015.6 1,193.2 1,370.8 1,548.5

 

 

Pre-tax IRR

 

 

CAD:USD Gold Price (US$/oz)
$1,000 $1,100 $1,200 $1,250 $1,300 $1,400 $1,500 $1,600
1.11 (0.2%) 5.4% 10.3% 12.5% 14.6% 18.6% 22.4% 25.9%
1.18 3.2% 8.6% 13.4% 15.6% 17.7% 21.7% 25.5% 29.1%
1.25 6.7% 11.9% 16.7% 18.9% 21.0% 25.1% 28.9% 32.5%
1.31 9.3% 14.5% 19.2% 21.4% 23.6% 27.7% 31.5% 35.2%
1.43 14.0% 19.2% 23.9% 26.2% 28.4% 32.5% 36.5% 40.3%
1.54 18.0% 23.2% 28.0% 30.3% 32.5% 36.8% 40.9% 44.8%
1.67 22.4% 27.6% 32.5% 34.9% 37.2% 41.6% 45.8% 49.8%

 

 

MINERAL RESOURCES

 

The mineral resources used as the basis for the FS study are summarized below.

 

Mineral Resource Statement – October 20, 2017

 

 

Resource Category Tonnes (Mt) Grade (g/t Au) Contained Gold (oz)
Measured Resources 3.99 2.52 323,300
Indicated Resources 25.87 2.72 2,264,500
Total Measured + Indicated Resources 29.86 2.70 2,587,900
Inferred Resources 4.16 2.20 293,900
 
Notes:
1. CIM (2014) definitions were followed for Mineral Resources.
2. Mineral Resources are inclusive of Mineral Reserves.
3. Mineral Resources are estimated at a cut-off grade of 1.0 g/t Au.
4. Mineral Resources are estimated using a gold price of US$1,500 per ounce, and exchange rate of US$0.80 = C$1.00.
5. A minimum mining width of four metres was used.
6. A bulk density of 2.8 g/cm3 was used.
7. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.
8. Numbers may not add due to rounding.

 

 

MINERAL RESERVES

 

Mineral reserves were classified complying with the CIM definition standards for mineral resources and mineral reserves. Mineral reserves for the Wasamac deposit incorporate dilution and mining recovery factors based on the selected mining method and design. Mineral reserve is the estimated tonnage and grade of ore that is considered economically viable for extraction.

 

The mineral reserve estimate for the Wasamac deposit is based on the resource block model provided by RPA to Monarques in 2017, along with the information in the Preliminary Economic Assessment study conducted by RPA in 2012 for the previous mine owner, Richmont Mines Inc.

 

The price of gold is determined to be US$1,300/oz. The trailing average exchange rate of 1.31 C$/US$ is used in cut-off grade determination.

 

 

Mineral reserves were estimated from the resource block model provided from RPA, using software-generated optimized stopes based on an estimated 1.0 g/t cut-off grade.

 

Mineral Reserve Statement by Category – December 1, 2018

 

 

  Tonnes
(000 t)
Grade
(g/t Au)
Contained Gold
(000 oz)
Proven 1,028 2.66 88
Probable 20,427 2.56 1,679
Total Proven and Probable 21,455 2.56 1,767

 

 

CAPITAL AND OPERATING COSTS SUMMARY

 

Project capital cost summary

 

 

Cost description Pre-production
capital cost ($M)
Sustaining
capital cost ($M)
Total cost ($M)
General administration (owner’s costs) 9.7 0.0 9.7
Underground mine 137.6 170.5 308.1
Surface infrastructure 50.7 (5.3) 45.4
Filter press plant 39.1 0.0 39.1
Process plant 131.8 0.0 131.8
Tailings and water management 21.2 1.5 22.6
Indirect 42.6 0.0 42.6
Contingency 31.2 7.9 39.1
Total 464.0 174.5 638.5
Site reclamation and closure 0.0 6.1 6.1
Salvage value 0.0 (15.8) (15.8)
Total – forecast to spend 464.0 164.8 628.8

 

 

Project operating cost summary

 

 

Cost description LOM

($M)

Annual average
cost ($M)
Average LOM
($/tonne milled)
Average LOM
($/oz)
OPEX
(%)
Underground mining 573.2 52.1 26.72 368.15 53
Process plant 381.7 34.7 17.79 245.18 35
Tailings and water management 47.2 4.3 2.20 30.33 4
General & administration 75.8 6.9 3.53 48.66 7
Total 1,077.9 98.0 50.24 692.31 100

 

 

OPPORTUNITIES FOR IMPROVEMENT

 

There are significant opportunities that could improve the economics and the timetable of the Wasamac project. The major opportunities identified at this time are summarized in Table 25-4 of the FS. Further information and assessments are needed prior to including these opportunities in the economic evaluation of the project.

 

ESTIMATED SCHEDULE AND WORKFORCE REQUIREMENTS

 

Pending the completion of all studies and receipt of the required permits and financing, the process plant construction is scheduled to begin in Q4 2020 with full capacity production achieved by Q4 2022.

 

The preliminary on-site workforce requirement for construction, including infrastructure, process plant, and development of the underground mine is expected to average 250 construction personnel, peaking at approximately 420 individuals in Q3 2021. It is anticipated that around 300 employees (staff and labour, peaking at 319 in year 2024) will be required for the operations over the life of mine.

 

INDEPENDENT QUALIFIED PERSONS

 

The FS was prepared for Monarques under the direction of BBA, by leading independent industry consultants, all of whom are qualified persons (“QP”) under National Instrument 43-101. The QPs have reviewed and approved the content of this news release. Independent QPs from BBA and RPA who have prepared or supervised the preparation of the technical information relating to the FS include:

 

  • Carl Caumartin, P.Eng., BBA Inc.
  • Alain Dorval, P.Eng., BBA Inc.
  • John Henning, P.Eng., BBA Inc.
  • Richard Jundis, P.Eng., BBA Inc.
  • Luciano Piciacchia, P.Eng., BBA Inc.
  • Tudorel Ciuculescu, M.Sc., P.Geo., Roscoe Postle Associates Inc.

 

The technical and scientific content of this press release has been reviewed and approved by Marc-André Lavergne, P.Eng., the Corporation’s qualified person under National Instrument 43‑101.

 

ABOUT MONARQUES GOLD CORPORATION

 

Monarques Gold Corporation is an emerging gold mining company focused on pursuing growth through its large portfolio of high-quality projects in the Abitibi mining camp in Quebec, Canada. The Corporation currently owns close to 300 km² of gold properties, including the Wasamac deposit (measured and indicated resource of 2.6 million ounces of gold), the Beaufor Mine, the Croinor Gold, McKenzie Break and Swanson advanced projects and the Camflo and Beacon mills, as well as other promising exploration projects. It also offers custom milling services out of its 1,600 tonne-per-day Camflo mill.

 

Posted December 3, 2018

Share this news article

MORE or "UNCATEGORIZED"


PPX Mining Announces Closing Of $1.35 Million Private Placement

PPX Mining Corp. is pleased to announce that it has closed its fu... READ MORE

April 19, 2024

Elevation Gold Reports Financial Results for Year Ended December 31, 2023, including $66.4M in Total Revenue

Elevation Gold Mining Corporation (TSX-V: ELVT) (OTCQB: EVGDF) i... READ MORE

April 18, 2024

Reunion Gold Announces the Signing of a Mineral Agreement With the Government of Guyana for Its Oko West Project

Reunion Gold Corporation (TSX-V: RGD; OTCQX: RGDFF) is pleased to announ... READ MORE

April 18, 2024

Drilling Confirms 4 km of Favourable Corridor at Lynx Gold Trend

Puma Exploration Inc. (TSX-V: PUMA) (OTCQB: PUMXF) is thrilled to... READ MORE

April 18, 2024

Grid Metals Intersects 7 m at 1.28% Li2O at over 125 m Below the Previously Deepest Drill Holes at Donner Lake; Provides Project Update

Grid Metals Corp. (TSX-V:GRDM) (OTCQB:MSMGF) is pleased to announ... READ MORE

April 18, 2024

Copyright 2024 The Prospector News