
Open pit, run-of-mine (no crushing) heap leach operation with a one-year construction period and initial capital expenditure of $327 million
Average annual production of 183 thousand ounces of gold in years 1 to 5 with Life-of-Mine average annual production of 135 thousand ounces of gold
All-In Sustaining Cost for years 1 to 5 of $1,205 per ounce of gold and LOM AISC of $1,380 per ounce of gold
$552 million After-Tax Net Present Value (5%) with a 32% After-Tax Internal Rate of Return and a 3.3 year payback at a base case gold price of $2,000 per ounce
Liberty Gold Corp. (TSX:LGD) (OTCQX:LGDTF) is pleased to announce the results of a Preliminary Feasibility Study prepared in accordance with National Instrument 43-101 – Standards of Disclosure for Mineral Projects at its flagship Black Pine Oxide Gold Project in southern Idaho, USA. The Study supports a technically straight-forward, low capital intensity, open-pit, run-of-mine (no ore crushing, screening or agglomeration) heap-leach operation processing oxide gold ore, with attractive economic returns.
This news release should be read in combination with the Study presentation slide deck available at this link: https://libertygold.ca/images/news/2024/October/BlackPineProjectPFSDeck.pdf
The Study assumes a base-case gold price of $2,000/ounce and all figures in this news release are stated in United States dollars unless otherwise noted. Table 1 below presents a summary of the key metrics for the Black Pine PFS.
Cal Everett, CEO and Director of Liberty Gold commented: “This PFS highlights the strong economic potential at Black Pine, representing our vision for a low-risk, sustainable and long-lived gold mining operation in Idaho. It demonstrates the Project’s ability to exploit higher grades early in the mine life, allowing for solid cash flows over the first five years, with a production profile that reduces the payback period and maximizes the initial return for our investors. The PFS mine plan produces more than 2 million ounces of gold over a projected mine life of 17 years, creating a solid pathway towards mine permitting, project advancement and a future construction decision.”
“We believe there is significant upside for project optimization and resource growth going into a full feasibility study. Growth will be driven by new resource discovery from multiple target areas, upgrade of inferred mineral resources into the measured and inferred mineral resource categories and assessment of gold production potential from the reclaimed heap leach pad. Work in many of these areas is already beginning to yield encouraging results. We look forward to keeping the market apprised of our progress.”
Table 1: Key Black Pine Project Metrics
Project Economics | Base Case | Spot Price |
Gold Price | $2,000/oz | $2,600/oz |
Pre-tax Net Present Value (“NPV”) (5%) | $658 million | $1,575 million |
Pre-tax Internal Rate of Return (“IRR”) | 35% | 67% |
Operating Pre-Tax Cash Flow | $1,042 million | $2,352 million |
After-Tax NPV (5%) | $552 million | $1,296 million |
After-Tax IRR | 32% | 62% |
After-Tax Cash Flow | $873 million | $1,921 million |
After-Tax Payback Period | 3.3 years | 1.5 years |
Production Profile | ||
Mine Life | 17 years | |
Ore to Leach Pad | 50,000 tonnes per day | |
Total Tonnes of Ore Mined and Processed | 299 million tonnes | |
Head Grade (years 1-5) | 0.45 grams per tonne (“g/t”) | |
Head Grade (Life-of-Mine “LOM”) | 0.32 g/t | |
Strip Ratio (Waste:Ore) | 1.3:1 | |
Average Gold Recovery | 70.4% | |
Total Gold Ounces Recovered | 2,191 koz1 | |
Average Annual Gold Production (Yr 1-5) | 183 koz | |
Peak Annual Gold Production | 231 koz | |
Average Annual Gold Production (LOM) | 135 koz | |
Unit Operating Costs | ||
LOM Operating Cost | $9.10/tonne processed | |
LOM Total Cash Cost2 | $1,249/oz | |
LOM AISC2 | $1,380/oz | |
Total Capital Costs | ||
Initial Capital2 | $327 million | |
LOM Sustaining Capital | $219 million | |
LOM Total Capital | $546 million | |
Closure Costs | $54 million | |
1 “koz” refers to thousand ounces 2Refer to “Non-GAAP Measures and Other Financial Information” below | ||
Project Economics Sensitivity Analysis
A sensitivity analysis was carried out on the after-tax financial metrics from the PFS base case to illustrate the Project’s sensitivity to commodity prices, initial capital and operating costs. Results are illustrated in Tables 2 and 3 (all figures in US dollar millions unless otherwise indicated).
Table 2: After-tax NPV (5%), IRR and Payback Sensitivity to Gold Price
Gold Price ($/oz) | $1,700 | $1,850 | $2,000 | $2,150 | $2,300 | $2,450 | $2,600 |
After-Tax NPV (5%) ($M) | $174 | $362 | $552 | $739 | $924 | $1,110 | $1,296 |
After-Tax IRR (%) | 15% | 24% | 32% | 40% | 47% | 55% | 62% |
Payback (years) | 4.3 | 3.8 | 3.3 | 2.4 | 1.8 | 1.7 | 1.5 |
Table 3: After-Tax NPV (5%) and IRR sensitivity to Changes in Project Parameters & Gold Price
Gold Price/oz | |||||
After-tax NPV (5%) in $M | Change | $1,850 | $2,000 | $2,300 | $2,600 |
Total Capital Costs | 15% | $323 | $512 | $884 | $1,256 |
0% | $362 | $552 | $924 | $1,296 | |
-15% | $403 | $593 | $965 | $1,336 | |
Operating Costs | 15% | $131 | $323 | $701 | $1,072 |
0% | $362 | $552 | $924 | $1,296 | |
-15% | $591 | $776 | $1,148 | $1,516 | |
Gold Price/oz | |||||
After-Tax IRR (%) | Change | $1,850 | $2,000 | $2,300 | $2,600 |
Total Capital Costs | 15% | 20% | 27% | 41% | 54% |
0% | 24% | 32% | 47% | 62% | |
-15% | 29% | 38% | 56% | 73% | |
Operating Costs | 15% | 13% | 22% | 39% | 54% |
0% | 24% | 32% | 47% | 62% | |
-15% | 33% | 41% | 56% | 70% | |
PFS Overview
The PFS incorporates geological, assay, hydrological, metallurgical, geotechnical, environmental and cultural information collected by Liberty Gold and its consultants and contractors, as well as extensive historic information captured from the previous mining operation on site.
Project Description
Black Pine hosts a large, Carlin-style, sedimentary-hosted oxide gold system, located in southeastern Cassia County, southern Idaho, USA, a 2-hour drive north from Salt Lake City, Utah. The currently identified surface footprint of the gold mineralization extends over an approximate 18 square kilometre target area contained within Liberty Gold’s 69.3 km2 project area of which 40.6 km2 are permitted for exploration activities including drilling. (see press releases dated June 11, 2024 and September 25, 2024).
Black Pine is a past-producing open-pit, ROM heap leach mine, active from 1991 to 1997 when Pegasus Gold produced 435,000 oz of gold and 189,000 oz of silver from five open pits. Road access to the site is well established with the I-84 highway running directly adjacent to the project area and existing power at the mine gate. The location is sparsely populated, semi-arid, with no surface water exposed in the project area and no threatened or endangered species.
The production from the Project is subject to a 0.5% net smelter royalty (with a 50% buyback right to the Company, which has been assumed to be exercised in the economic analysis).
For a 3D video of a run through of the site layout, click on this link: https://youtu.be/ScIQ4cF_QwE
Mining
The PFS utilizes open pit mining with mine planning based on economic pit shells generated by mine planning software. Ore feed to the leach pad is planned at 50,000 tonnes per day or 18.3 million tonnes per year for the estimated 17-year life of mine. There will be a 9-month pre-production period to provide access to higher grade ore horizons for early years processing. There are significant opportunities to improve mid-life production through resource growth and conversion ahead of the feasibility study. Lower-grade ores are stockpiled throughout the mine life and re-handled on to the heap to optimize gold production.
Total material movement averages 47 million tonnes per year over life of mine, with a peak at 55 million tonnes per year. Ore is sourced from two large multi-phase open pits, together with six smaller ‘satellite’ open pits. The strip ratio is favourably low at 1.3:1 (waste:ore), resulting from the extensive envelope of lower-grade oxide gold mineralization surrounding the higher-grade horizons and permeating through the mass of carbonate host rock units.
The open pit mining at Black Pine is designed as a conventional, owner-operated surface mining operation, where the owner is responsible for planning and executing direct mining and all mine fleet maintenance, equipment mobilization, supervision, labor, geology and grade control. Blasting would be performed as a contract service. The PFS mine plan proposes a blended mine fleet of 400 tonne-class hydraulic excavators, 100 tonne-class hydraulic excavators, 11.5 cubic metre bucket front end loaders, 136 tonne off-highway haul trucks and 64 tonne off-highway haul trucks.
Metallurgy
Six phases of metallurgical testing have been completed on Black Pine oxide ores, using bulk samples and predominantly, large diameter PQ core. A total of six bulk samples and 174 variability composites have been tested at Kappes, Cassiday & Associates in Reno, Nevada and included extensive geo-metallurgical characterization, comminution testing, bottle roll and column leach testing and environmental characterization of head samples and column residues. The oxide ores respond very well to cyanide leaching with typically >80% of the leachable gold extracted in the first 10 days of laboratory column leaching. Modeling of column test data support ROM leaching as the preferred processing method, with a primary leach cycle of 90 days.
Commercial scale ROM gold and silver grade-recovery models have been developed for the geo-metallurgical oxide ore types, defined by gold cyanide solubility, location and lithology. The limited amount of mineralized carbonaceous material present at Black Pine has been extensively modelled and has been treated as waste rock.
Processing
Gold will be recovered using run-of-mine (no crushing, screening or agglomeration) heap leaching with material placed by mine haul truck stacking onto a single heap leach pad sited at the eastern extent of the Project. The pad is designed in four phases to contain up to 315 million dry tonnes of leachable material, with operational segregation of the oxide ore types in isolated cells on the leach pad to prevent comingling.
ROM-sized ore will be stacked in 10 metre (“m”) vertical lifts to a maximum heap height of 100 m. Lime will be added prior to truck dumping on the pad, ore will be ripped and subsequently leached with dilute cyanide solution using conventional irrigation. Leach solution will flow by gravity through the heap and be conveyed to the process solution tank. No surface ponds other than an emergency event pond are included in the PFS design.
Leached gold will be recovered from solution using a 3-train, activated carbon adsorption circuit. The gold (and any silver) will then be stripped from carbon using a desorption process followed by electrowinning to produce a precipitate sludge, which is refined on site in a furnace to produce final doré bars.
Process water is drawn from five existing, active water wells, located within 5 kilometres from the processing facility. Power is grid supply over an existing 25 kV line to the mine gate.
Cost Estimates
Capital and operating costs were estimated by M3 Engineering for the processing and general and administration components of the PFS costs estimate; all mining costs were estimated by AGP Mining.
The capital costs estimate presented in Table 4, is considered to have overall accuracy of -20% / +25%.
Table 4: Black Pine PFS Capital Cost Breakdown
Capital Costs | Initial | Sustaining | Total |
US$ Million | US$ Million | US$ Million | |
Pre-stripping and Stockpile (1) | $89.3 | $0.0 | $89.3 |
Mine (2) | $31.4 | $55.9 | $87.3 |
Process | $161.4 | $121.3 | $282.6 |
Contingency | $35.3 | $31.4 | $66.7 |
Owners Cost | $9.2 | $10.6 | $19.8 |
Total Capital Costs(3) | $326.6 | $219.2 | $545.8 |
A summary of the operating costs estimate for Black Pine is presented in Table 5. Operating costs are based on ownership and owner’s direction of all mine and processing equipment and facilities. Reclamation and closure costs estimated from first principles at $54 million and validated with a Nevada Standardized Reclamation Cost Estimator model, are additional to sustaining capital costs illustrated in Table 4 and are included in the Project economic evaluation.
The mining costs are based on quotes for mining equipment and estimated owners’ costs. The PFS base case assumes the mine fleet is leased with the mine operating cost carrying the annual lease payment. Processing costs were estimated by M3 Engineering and NewFields, based on first principles, assuming the owner employs and directs all operations and maintenance for all site facilities. Labor costs were estimated using Idaho labor rates and specific staffing requirements. Unit consumption of materials, consumables, power and water were estimated from first principles.
Table 5: Black Pine Operating Cost Estimate
Operating Costs | LOM | Unit Costs |
US$ Million | US$/tonne ore | |
Mining(1) | $1,943 | $6.49 |
Process Plant | $538 | $1.80 |
G&A | $220 | $0.73 |
Refining | $22 | $0.07 |
Total Operating Cost | $2,724 | $9.10 |
Operating costs have an effective date of June 1, 2024, and are presented with no added contingency.
Sustainability
At Liberty Gold, sustainability is integral to our operations and decision-making, ensuring long-term value for stakeholders. Since 2021, we have published annual sustainability reports, reinforcing our commitment to transparency and accountability. At Black Pine, we engage regularly with stakeholders through updates, tours, and local events. We are deeply committed to preserving biodiversity, supporting sage grouse habitat restoration and funding a four-year mule deer migration study with Idaho Fish and Game. Sustainability initiatives included in the Black Pine PFS include renewable energy supply through local utility, no net increase in water draw, habitat mitigation, and waste rock backfill. We propose to explore mine fleet electrification and other key sustainable initiatives during feasibility to minimize our carbon and project footprint.
Further Opportunities
Optimization of the Black Pine Project will be evaluated ahead of and during feasibility. This includes:
Next Steps
Black Pine Mineral Reserve Estimate
Mineral Reserves have been estimated for a conventional, multiple pit, open pit mining operation utilizing surface waste rock storage facilities, pits backfill, extensive ore stockpiling and direct haul to a single ROM heap leach facility. Pit slope angles were defined by geotechnical evaluation supported by hydrological analysis.
Table 6: Black Pine Mineral Reserve Estimate
Reserve Class | Million tonnes | g/t Au | (000) oz Au |
Probable | 299.4 | 0.32 | 3,110 |
Total | 299.4 | 0.32 | 3,110 |
Notes:
Black Pine Mineral Resource Estimate
The Study has updated the Black Pine Mineral Resource estimate. Key changes relative to the previous Mineral Resource estimate (see press release dated February 15, 2024) are:
Table 7: Black Pine Mineral Resource Estimate
Resource Class | Million tonnes | g/t Au | (000) oz Au |
Indicated | 402.6 | 0.32 | 4,163 |
Inferred | 97.7 | 0.23 | 712 |
Notes:
Table 8: Black Pine Mineral Resource Cut-off Grade Sensitivity
Cut-off (g/t Au) | Classification | Million tonnes | g/t Au | (000) oz Au |
0.10 g/t | Indicated | 402.6 | 0.32 | 4,163 |
Inferred | 97.7 | 0.23 | 712 | |
0.17 g/t | Indicated | 250.0 | 0.43 | 3,449 |
Inferred | 40.9 | 0.34 | 445 | |
0.20 g/t | Indicated | 197.8 | 0.49 | 3,119 |
Inferred | 28.0 | 0.39 | 353 | |
0.50 g/t | Indicated | 39.7 | 1.09 | 1,388 |
Inferred | 3.0 | 0.91 | 89 |
*Please refer to notes accompanying Table 7, above. The reporting Mineral Resource estimate is shown in bold font. Tonnes, grade and ounces are expressed within a series of nested pit shells generated at $2,000/ounce gold whereby only the material above each cut-off grade is processed.
Qualified Persons
This announcement has been reviewed and approved for release by Pete Shabestari, Vice President of Exploration at Liberty Gold and the Company’s designated Qualified Person within the meaning of NI 43-101. Mr. Shabestari has verified the data disclosed including sampling, analytical, and test data underlying the drill results, using a variety of techniques including comparison against independently sourced assay certificates, site visit investigations, and digital based verification tests, and he consents to the inclusion in this release of said data in the form and context in which it appears.
The PFS was prepared by a team of independent industry experts. The independent Qualified Persons for the “NI 43-101 Technical Report and Pre-feasibility Study for the Black Pine Project, Idaho, USA”, which will be filed within 45 days of the date of this press release, and which will be available on SEDAR+ (www.sedarplus.ca) and on Liberty Gold’s website, are as follows:
Table 9: Qualified Persons
Category | Name | Company |
Mineral Resource Estimate | Valerie Wilson, P.Geo. | SLR Consulting Ltd. |
Mineral Reserve Estimate | Todd Carstensen, RM-SME | AGP Mining Consultants Inc. |
Metallurgy | Gary Simmons, MMSA | GL Simmons Consulting, LLC. |
Heap Design & Closure | Nicholas T. Rocco, Ph.D., P.E. | NewFields Companies LLC. |
Mineral Processing & Financial Evaluation | Benjamin Bermudez, P.E. | M3 Engineering & Technology Corp. |
Infrastructure & Study Lead Engineer | Matthew Sletten, P.E. | M3 Engineering & Technology Corp. |
Hydrology | John Rupp, P.E. | Piteau Associates Ltd. |
Geotechnical Engineering | Daniel Yang, P.Eng., P.E. | Knight Piésold Ltd. |
Environmental Permitting & Compliance | Richard DeLong, M.Sc. | Westland Engineering & Environmental Services Inc. |
Independent Third-Party Review
The heap design from NewFields was subject to independent third-party review by Tierra Group International Ltd. The financial model from M3 Engineering was subject independent third-party review by Hive Advisory Inc. All material recommendations arising have been incorporated into the Study.
Non-GAAP Measures and Other Financial Measures
Alternative performance measures are furnished to provide additional information. These non-GAAP performance measures are included in this news release because these statistics are key performance measures that management uses to monitor performance, to assess how the Company is performing, to plan and to assess the overall effectiveness and efficiency of mining operations. These performance measures including Initial Capital Costs, Total Cash Costs, and All-In Sustaining Costs, do not have a standard meaning within International Financial Reporting Standards and, therefore, amounts presented may not be comparable to similar data presented by other mining companies. Each of these measures used are intended to provide additional information to the user and should not be considered in isolation or as a substitute for measures prepared in accordance with IFRS.
The non-IFRS financial measures used in this news release and common to the gold mining industry are defined below.
Initial Capital Costs
Initial Capital Cost is defined as capital required to develop, construct and to bring the Project to commercial production.
Total Cash Costs and Total Cash Costs per Gold Ounce
Total Cash Costs are reflective of the cost of production. Total Cash Costs reported in the PFS include mining costs, processing, on-site general & administrative costs, treatment & refining costs, and royalties. Total Cash Costs per Ounce is calculated as Total Cash Costs divided by total LOM payable gold ounces.
All-in Sustaining Costs and AISC per Gold Ounce
AISC is reflective of all of the expenditures that are required to produce an ounce of gold from operations. AISC reported in the PFS includes Total Cash Costs, sustaining capital, closure costs and Idaho Mine License Tax. AISC per ounce is calculated as AISC divided by total LOM payable gold ounces.
ABOUT LIBERTY GOLD
Liberty Gold is focused on exploring for and developing open pit oxide deposits in the Great Basin of the United States, home to large-scale gold projects that are ideal for open-pit mining. This region is one of the most prolific gold-producing regions in the world and stretches across Nevada and into Idaho and Utah. We know the Great Basin and are driven to discover and advance big gold deposits that can be mined profitably in open-pit scenarios.
North Bay Resources, Inc. (OTC: NBRI) is pleased to announce a ... READ MORE
Warrant Highlights: $6,377964 of warrants are still outstanding a... READ MORE
Collective Mining Ltd. (NYSE: CNL) (TSX: CNL) is pleased to anno... READ MORE
Intersected 5.68 g/t Au over 10.72 m, including 19.05 g/t ... READ MORE
LRC rebalances portfolio with partial sale of Tres Quebradas roya... READ MORE