
K92 Mining Inc. (TSX: KNT) (OTCQX: KNTNF) is pleased to announce financial results for the three and twelve months ended December 31, 2022.
Safety
Production
Fourth Quarter 2022
Full Year 2022
Financials
Fourth Quarter 2022
Full Year 2022
Growth
2023 Operational Outlook
During the first quarter the operation experienced challenges at the process plant and the underground mine. The process plant experienced two notable unplanned maintenance events, with one of the mill trunnion bearings failing and requiring immediate replacement resulting in 2 days downtime, and a limited electrical fire in a cable tray resulting in damage to a number of cables feeding the wet section of the process plant for 6 days downtime. The total combined impact was 8 days of unplanned downtime for the process plant during the first quarter. (See February 27, 2023 press release).
The process plant has performed well after the completion of the unplanned maintenance, achieving multiple new daily throughput records including 1,726 tonnes processed on February 26, 1,773 tonnes processed on February 28, 1,802 tonnes processed on March 3 and 1,815 tonnes processed on March 11. This is significantly higher throughput than the Stage 2A Expansion average daily throughput rate of approximately 1,370 tonnes per day. Additionally, we see further upside to overall process plant performance upon commissioning of the rougher flotation cells to double capacity in 2Q 2023.
During the second half of the first quarter, underground mining encountered an area with more challenging ground conditions than expected, which impacted our production stoping rates and access to higher grade material. Generally, in this situation, mill feed would be supplemented by mining from additional mining fronts as we mine through the impacted area more slowly. However, due to development rates being below budget for several quarters during the COVID-19 pandemic, many of the alternative mining areas were not yet developed, therefore supplementing from our low-grade stockpile was required.
Development is a major focus as we emerge from the pandemic environment, with record development advance achieved in Q4 2022, development advance proceeding well year-to-date and multiple new equipment arrivals this quarter and scheduled for delivery in Q2 to increase our advance rates further. Furthermore, we expect a substantial increase to our underground mining operational flexibility near-term with two new sublevels currently being established, and importantly, an entirely new mining front at depth from the twin incline in the second half of this year.
As a result, we expect the first quarter to be notably below budget, the second quarter to be moderately below budget and annual production to be within the bottom half of the guidance range. As noted in our operational guidance previously, we expect the second half of the year to be our strongest in terms of production.
The Company’s annual consolidated financial statements and associated management’s discussion and analysis for the year ended December 31, 2022 are available for download on the Company’s website and under the Company’s profile on SEDAR (www.sedar.com). All amounts are in U.S. dollars unless otherwise indicated.
See Figure 1: Quarterly Production and AISC Chart
See Figure 2: Quarterly Total Ore Processed, Development Metres Advanced and Total Mined Material Chart
See Figure 3: Ore Processed Daily Records Chart
John Lewins, K92 Chief Executive Officer and Director, stated, “In 2022, Kainantu took another major step forward, achieving significant growth financially, operationally, in our resource base and from exploration in general. Financially, the Company ended the year stronger than ever, with $110 million of cash and no debt. Operationally, in 2022 we achieved record production, ore tonnes processed, ore tonnes mined and underground development. Our resource base expanded considerably, with measured and indicated resources increasing by 92% and inferred by 251%, driven by our updated resource estimate at Kora, maiden resource at Judd and maiden resource at Blue Lake. Exploration outside of our resource base has made significant progress, with record thickness intersections recorded via dilatant zones that were first discovered in early 2022 at Kora South and Judd South, in addition to significant strike extensions from step-out drilling at Kora-Kora South and Judd-Judd South. Drilling has now defined a known drilled strike length at Kora-Kora South of over 2.65 km, and both Kora-Kora South and Judd-Judd South are open in multiple directions.
Importantly, in December 2022, the Government of Papua New Guinea approved the extension of Mining Lease 150 to June 2034 with the Board of Directors of K92 concurrently approving the Stage 3 and 4 Expansions. This is a major milestone for the Company and all of our stakeholders as the Stage 3 and 4 Expansions plan to transform Kainantu into one of the industry’s next world class gold mines, with the Integrated Development Plan Stage 4 PEA case outlining peak annual production of 500 koz gold equivalent. The tender process is making considerable progress, and we will provide an update once this has been completed.
Looking ahead at 2023, there is tremendous excitement within the Company. On vein field exploration, a large majority of our drill rigs are focused on resource growth and have delivered strong results, including an increasing hit-rate of dilatant zone intersections plus many high-grade intersections (see February 21, 2023 press release). Significantly, over the next few months, underground development plans to establish access to multiple highly prospective exploration fronts at depth, particularly at Kora South, Judd South, Kora Deeps and Judd Deeps.
Operationally, we expect the second half of the year to be our strongest in terms of production. This is driven by the arrival of plant and equipment which has been considerably slower than expected due to supply chain constraints, commissioning of the Stage 2A Expansion rougher flotation cells planned for Q2 and increased underground development rates to establish new sublevels, plus an entirely new mining front around the twin incline. This is expected to provide a considerable increase to our operational flexibility.
And lastly, I am very pleased to announce that we have commenced drilling our first hole at the A1 copper-gold porphyry target. The drill program has leveraged data from our extensive soil geochemical program and advanced MobileMT airborne geophysics. The initial program is targeting a depth of approximately 500 metres to defined vectors for deeper targeted drilling. We look forward to providing an update on A1 in due course.”
Mine Operating Activities
Three months ended December 31, 2022 |
Twelve months ended December 31, 2022 |
|||
Operating data | ||||
Head grade (Au g/t) | 8.8 | 8.3 | ||
Gold recovery (%) | 91.2% | 90.4% | ||
Gold ounces produced | 31,204 | 107,546 | ||
Gold ounces equivalent produced (1) (2) | 35,538 | 122,806 | ||
Tonnes of copper produced | 829 | 2,834 | ||
Silver ounces produced | 40,517 | 126,043 | ||
Financial data (in thousands of dollars) | ||||
Gold ounces sold | 35,212 | 110,654 | ||
Revenues from concentrate and doré sales | US$61,980 | US$188,186 | ||
Mine operating expenses | US$10,344 | US$36,908 | ||
Other mine expenses | US$13,120 | US$38,914 | ||
Depreciation and depletion | US$6,320 | US$20,450 | ||
Statistics (in dollars) | ||||
Average realized selling price per ounce, net | US$1,652 | US$1,711 | ||
Cash cost per ounce (2) | US$512 | US$538 | ||
All-in sustaining cost per ounce (2) | US$870 | US$864 |
Notes:
(1) | Gold equivalent in 2022 is calculated based on: gold $1,793 per ounce; silver $22 per ounce; and copper $3.95 per pound. Gold equivalent in Q4 2022 is calculated based on: gold $1,728 per ounce; silver $21 per ounce; and copper $3.63 per pound. | |
(2) | The Company provides some non-international financial reporting standard measures as supplementary information that management believes may be useful to investors to explain the Company’s financial results. Please refer to non-IFRS financial performance measures in the Company’s management’s discussion and analysis dated March 29, 2023, available on SEDAR or the Company’s website, for reconciliation of these measures. |
K92 has not based its production decisions on mineral reserve estimates or feasibility studies, and historically such projects have increased uncertainty and risk of failure. Mineral resources that are not mineral reserves do not have demonstrated economic viability.
Qualified Person
K92 Mine Geology Manager and Mine Exploration Manager, Mr. Andrew Kohler, PGeo, a qualified person under the meaning of Canadian National Instrument 43-101 – Standards of Disclosure for Mineral Projects, has reviewed and is responsible for the technical content of this news release.
About K92
K92 Mining Inc. is engaged in the production of gold, copper and silver at the Kainantu Gold Mine in the Eastern Highlands province of Papua New Guinea, as well as exploration and development of mineral deposits in the immediate vicinity of the mine. The Company declared commercial production from Kainantu in February 2018, is in a strong financial position. A maiden resource estimate on the Blue Lake copper-gold porphyry project was completed in August 2022. K92 is operated by a team of mining company professionals with extensive international mine-building and operational experience.
Figure 1: Quarterly Production and AISC Chart
https://www.globenewswire.com/NewsRoom/AttachmentNg/c0916200-6b30-4af2-aba4-7bf85fc1a3a2
Figure 2: Quarterly Total Ore Processed, Development Metres Advanced and Total Mined Material Chart
https://www.globenewswire.com/NewsRoom/AttachmentNg/59809690-2a30-4476-8a69-9273627550bb
Figure 3: Ore Processed Daily Records Chart
https://www.globenewswire.com/NewsRoom/AttachmentNg/e8ef7e9d-7e54-4fea-ba2d-f6009e088a82
Adds Strategic Interest in Tier-One Juanicipio Silver Mine and Si... READ MORE
Opus One Gold Corp. (TSX-V: OOR) is pleased to announce that the... READ MORE
Silvercorp Metals Inc. (TSX: SVM) (NYSE: SVM) is pleased to repor... READ MORE
Imperial Metals Corporation (TSX:III) reports financial results... READ MORE
Abcourt Mines Inc. (TSX-V : ABI) (OTCQB : ABMBF) is pleased to a... READ MORE