Juby Gold Drilling intersects 92.6 metres (m) of 0.95 g/t gold

 

 

 

 

 

Intersection includes 23.9m of 1.72 g/t gold, 7.15m of 3.46 g/t gold, and 16m of 0.07 g/t gold*

 

Exploration further expands gold mineralization at Juby Gold Project on Golden Lake Deposit

 

McFarlane Lake Mining Limited (CSE: MLM) (OTC: MLMLF) (FRA: W2Z) is pleased to announce further results from its diamond drilling exploration campaign being conducted on its 100%-owned Juby Gold Project, located west of Gowganda, Ontario, within the southern part of the “Abitibi Greenstone Belt”. Drilling was initiated in December 2025 on the property and commenced at the Company’s 826 Zone and has now moved to the Golden Lake Zone, see Figure 1.

 

Highlights

  • Drill hole GL 76-72 at Golden Lake has intersepted 0.95 g/t gold over 92.6m, this includes 23.9m of 1.72 g/t gold and 7.15m of 3.46 g/t gold. See Figure 2 and Tables 1 and 2.
  • Similar to the previously announced drill hole GL 76-71 (95.4m of 1.36 g/t gold March 2, 2026) this new gold intercept at GL 76-72 further expands the gold mineralization at the Golden Lake deposit bringing in mineralization which was outside the last mineral resource estimate (effective date September 29, 2025, see note below), see Figure 2.
  • Drilling has also intercepted mineralization as logged on holes GL 76-73A and GL 76-74. Both holes are approximately 100m apart from each other and alon g strike from GL 76-71 and GL 76-72. Hole 76-73A has logged over 100m of continuous mineralization. Drill core in both holes (73A & 74) are being prepared for lab sampling.
  • There has been approximately 5,000m drilled thus far on the Juby Gold Project from an original plan of 13,000m.
  • As a result of the significant intercept at GL 76-71 (95.4m of 1.36 g/t announced March 2, 2026), a new hole, GL 76-76, is now being drilled at a 100m step back to GL 76-71. This is to test the extension of the mineralization in a southwest trend in an effort to test the width of the mineralized zone.

“Not only does today’s announcement help support expanded gold mineralization at Juby, what we are seeing in further drilling along strike (Drill hole GL 76-73A and 76-74) is extremely encouraging. Drilling at our Golden Lake deposit i s surpassing expectations. Our team is excited to be developing what is evolving into a world-class deposit”, said Mark Trevisiol, CEO and Chairman of McFarlane.

 

A second diamond drill arrived at site on March 9, 2026 and recently completed hole GL 76-74 and has now moved on to drill GL 76-75. Originally, 14 diamond drill holes were planned; with the feedback received from the drilling to date, McFarlane will increase drilling at Golden Lake by at least 1,000 to 1,500m. One of the two diamond drills will transfer to the Juby deposit within the next 4 to 6 weeks, where approximately 4,000 to 5,000 meters are planned. See Figure 3 for the exploration plan at Juby.

 

Drilling being conducted at site is contracted through two separate firms, each having a business partnership with 2 of the 3 First Nation communities that have territorial rights on the property. There are three First Nation communities recognized as having territorial rights within the Juby Gold project, they include Matachewan First Nation, Temagami First Nation and Atikameksheng Anishnawbek First Nation.

 

Figure 1 – Juby Gold Project – Plan View of Exploration Drilling program showing location of drill holes at Golden Lake, Juby and 826 Zones

 

 

Figure 2 – Golden Lake Deposit Intersection – section looking northwest

 

 

Table 1 – Golden Lake Collar Information

 

Area Hole-ID Azimuth Dip Easting Northing Elevation Length (m)
Golden Lake GL76-71 40 -55 500314 5272450 365 602
  GL76-72 43 -58 500357 5272359 365 692.5

*Table 2 – Golden Lake Zone intercepts

 

Area Hole-ID From
(m)
To
(m)
Au gpt Width
(m)
True width
(m)
Depth
(m)
  GL76-71 111.00 113.00 1.03 2.00 1.5 85.8
Golden
Lake
  185.50 190.00 0.47 4.50 3.5 145.6
    298.10 300.20 0.22 2.10   232.1
  GL76-71 307.85 353.00 0.74 45.15 36.0 -260.1
  Including 315.55 323.00 1.44 7.45    
Golden
Lake
  371.00 466.40 1.36 95.40 75.6 -331.9
Previously Including 383.60 439.00 1.96 55.40    
Reported Including 410.10 420.00 3.22 9.90    
    489.35 516.05 0.68 26.70 21.6 -389.4
  Including 489.35 494.20 2.01 4.95   < td style=”border-right: solid black 1pt ; text-align: center ; vertical-align: middle; vertical-align: bottom ; “>
  GL76-72 83.00 86.00 0.43 3.00 2.2 66.3
    133.00 136.00 0.30 3.00 2.2 108.3
    176.00 182.75 0.35 6.75 4.9 145.8
    197.00 201.50 0.63 4.50 3.3 162.4
    225.70 228.00 0.35 2.30 1.7 185.3
Golden Lake   239.00 244.00 0.39 5.00 3.7 197.5
    264.00 267.00 0.37 3.00 2.2 217.3
    276.00 284.00 0.43 8.00 5.7 229.2
    305.30 312.00 0.69 6.70 4.9 252.5
    326.00 328.00 0.54 2.00 1.5 267.4
    398.00 405.00 0.84 7.00 5.1 327.0
    411.00 414.00 0.38 3.00 2.2 340.6
    464.00 466.00 0.46 2.00 1.5 381.4
    485.30 577.90 0.95 92.60 67.9 432.2
  Including

485.30

537.60 0.88 52.30 38.4 417.0
  Including 525.35 529.00 3.48 3.65 2.7  
  Including 537.60 554.00 0.07 16.40 12.0  
  Including 554.00 577.90 1.72 23.90 17.5 458.1
  Including 559.40 563.00 2.69 3.60 2.6  
  Including 568.85 576.00 3.46 7.15 5.2  
    606.00 608.80 0.28 2.80 2.1 489.2
    662.20 663.25 13.35 1.05 0.8 530.3

 

Figure 3 shows the area of planned drilling on the Golden Lake and Juby deposits in the upcoming weeks.

 

Figure 3 – Planned area of exploration for Golden Lake and Juby Resource areas

 

 

Quality Assurance and Quality Control

 

The drill core samples collected by McFarlane Lake Mining and described in this news release were placed in core boxes by the drill cr ew contracted by the Company. Core was then transported by McFarlane personnel to a secure processing facility. The core is then reviewed with core metreage blocks checked to verify core integrity, geologically logged, and samples marked. Core samples are cut in half, with one half remaining in the box and the other inserted into a clean plastic bag with a sample tag. Certified reference materials are inserted into the sample stream at a rate of no less than 10%. Samples are then transported in secure sealed bags with security tags for preparation and assay by MSA Labs in Timmins, Ontario, a certified lab with AC89, IAS accreditation and compliance with ISO/IEC standard 17025:2017.

 

Samples reported are crushed at the lab in their entirety to 70% passing 2 mm, with one 300 to 500 g subsample split and placed into a jar for analysis by photon assay. Gold concentration results are then recorded with reference to each sample tag number.

 

About McFarlane Lake Mining Limited

 

McFarlane Lake Mining Limited is a Canadian gold exploration company focused on advancing its flagship Juby Gold Project, located near Gowganda, Ontario, within the established Abitibi Greenstone Belt. The Juby Gold Project hosts a current (effective September 29, 2025) NI 43-101 compliant Mineral Resource Estimate of 1.01 million ounces of gold in the Indicated category at an average grade of 0.98 g/t gold (31.74 million tonnes) and an additional 3.17 million ounces of gold in the Inferred category at an average grade of 0.89 g/t gold (109.48 million tonnes). The estimate was calculated using a long-term gold price of US$2,500 per ounce, applying cut-off grades of 0.25 g/t gold for open pit and 1.85 g/t gold for underground resources.

 

A sensitivity analysis completed at a higher gold price of US$3,750 per ounce resulted in an Indicated Mineral Resource of 1.20 million ounces grading 0.94 g/t gold (39.51 million tonnes) and an Inferred Mineral Resource of 4.23 million ounces grading 0.85 g/t gold (154.50 million tonnes) applying cut-off grades of 0.25 g/t gold for open pit and 1.15 g/t gold for underground resources.

 

The independent MRE was prepared by BBA E&C Inc. in accordance with National Instrument 43-101 – Standards of Disclosure for Mineral Projects. The full technical report supporting the resource estimate was filed on SEDAR+ on November 21, 2025, and is also available on the Company’s website www.mcfarlanelakemining.com.

 

McFarlane is actively executing an exploration drilling program as detailed herein, and additional te chnical studies at the Juby Project to further evaluate and advance this large-scale gold system.

 

Posted March 30, 2026

Share this news article

MORE or "UNCATEGORIZED"


Delta-1 Gold Project Awarded $200,000 Funding Under the Ontario Junior Exploration Program

Delta Resources Limited (TSX-V: DLTA) (OTC Pink: DTARF) (FRANKFUR... READ MORE

March 30, 2026

Equinox Gold Updates Canadian Operations Technical Outlook: Average 540,000 Ounces Gold Production per Year for Next 10 Years

Equinox Gold Corp. (TSX: EQX) (NYSE: EQX) is pleased to report r... READ MORE

March 30, 2026

Cascadia Announces Strategic Exploration Alliance, Earn-In Agreement and Equity Investment with Agnico Eagle

Cascadia Minerals Ltd. (TSX-V: CAM) (OTCQB: CAMNF) is pleased to ... READ MORE

March 30, 2026

Montage Gold announces grade control results and resource increase for its Koné and Gbongogo Main deposits at its Koné Project

HIGHLIGHTS:  174,000 meters of exploration and grade control dri... READ MORE

March 30, 2026

Copyright 2026 The Prospector News