
Integra Resources Corp. (TSX-V: ITR) (NYSE American: ITRG) is pleased to announce the second set of drill results from the 4,597 meter 2023 highwall geotechnical and metallurgical drill program at the DeLamar Project located in southwestern Idaho. The results announced today include 20 drill holes representing 2,290 m from the highwall geotechnical and metallurgical drill program which was completed in November 2023.
The core samples from the drill program will be used for comprehensive mineralogical analysis, Crusher Work Index testing and additional heap leach recovery analysis, including bottle roll, permeability and column leach testwork. The metallurgical drill results from the program will be used to develop an advanced geo-metallurgical model that will support future economic studies at the Project. Geotechnical drilling was also completed in the proposed open pits at the Project to further bolster the 3D geotechnical model and to provide additional data for the Draft Mine Plan of Operations which was submitted to the U.S. Bureau of Land Management in December 2023.
Drilling Highlights:
(1) | Cut-off grade described in NI 43-101 technical report titled: “Technical Report and Preliminary Feasibility Study for the DeLamar and Florida Mountain Gold-Silver project, Owyhee County, Idaho, USA”, dated October 31, 2023 with an effective date of August 25, 2023, available under Integra’s SEDAR+ profile at www.sedarplus.ca |
Integra’s President, CEO & Director, Jason Kosec commented: “The drill results announced today further demonstrate the size, grade, and continuity of the mineral resource at DeLamar. Although the drill program was primarily designed to collect material for heap leach metallurgical testwork and geotechnical studies, we continue to intercept significant mineralized widths at excellent grades throughout the Project, exemplifying the robust nature of DeLamar. The results from this drill program will be used to complete a Feasibility Study at DeLamar in the future and to support on-going permitting work at the Project, following the submission of the MPO to the BLM in December 2023.”
Detailed Drill Results
The following table highlights selected intercepts from the 2023 Florida Mountain Deposit drill program announced today1,2,3,4:
Drill Hole | From (m) |
To (m) |
Interval (m) |
g/t Au | g/t Ag | g/t AuEq |
DH-FLM-23-MET02 | 14.33 | 148.44 | 134.11 | 1.42 | 3.36 | 1.46 |
including | 102.72 | 104.24 | 1.52 | 103.57 | 30.55 | 103.96 |
DH-FLM-23-MET05 | 0.00 | 111.25 | 111.25 | 0.13 | 18.36 | 0.36 |
DH-FLM-23-MET07 | 52.12 | 144.93 | 92.81 | 0.21 | 4.92 | 0.27 |
DH-FLM-23-MET09 | 0.00 | 139.90 | 139.90 | 0.30 | 17.03 | 0.52 |
including | 47.24 | 48.77 | 1.53 | 1.49 | 437.00 | 7.11 |
DH-FLM-23-MET11 | 0.00 | 130.15 | 130.15 | 0.22 | 7.17 | 0.31 |
DH-FLM-23-MET12 | 5.79 | 86.26 | 80.47 | 0.35 | 2.22 | 0.38 |
DH-FLM-23-MET14 | 63.40 | 120.09 | 56.69 | 0.34 | 7.21 | 0.43 |
DH-FLM-23-MET15 | 0.00 | 189.89 | 189.89 | 0.28 | 3.58 | 0.32 |
(1) | Downhole thickness is true thickness. | |||||
(2) | Intervals reported are uncapped. | |||||
(3) | AuEq = g/t Au + (g/t Ag ÷ 77.70). Rounding may cause minor discrepancies in the AuEq column. | |||||
(4) | Certain intervals were not sampled because they were utilized for alternative purposes requiring intact core (i.e. – geotechnical analysis, additional metallurgical tests). These unsampled intervals (~1% of the total program footage) have been replaced by ‘zero grade’ for the purposes of this news release. |
The following table highlights selected intercepts from the 2023 DeLamar Deposit drill program announced today1,2,3,4:
Drill Hole | From (m) |
To (m) |
Interval (m) |
g/t Au | g/t Ag | g/t AuEq |
DH-DLM-23-MET23 | 0.00 | 84.89 | 84.89 | 0.27 | 7.12 | 0.36 |
DH-DLM-23-MET23 | 116.43 | 145.09 | 28.66 | 0.39 | 5.77 | 0.47 |
DH-DLM-23-MET24 | 0.00 | 49.99 | 49.99 | 0.74 | 115.94 | 2.24 |
including | 17.37 | 32.61 | 15.24 | 1.47 | 263.48 | 4.87 |
DH-DLM-23-MET29 | 20.73 | 39.81 | 19.08 | 0.13 | 13.52 | 0.30 |
DH-DLM-23-MET29 | 57.30 | 160.02 | 102.72 | 0.12 | 18.31 | 0.35 |
DH-DLM-23-MET31 | 67.67 | 112.47 | 44.80 | 0.33 | 21.83 | 0.61 |
DH-DLM-23-MET33 | 0.00 | 52.73 | 52.73 | 0.27 | 24.90 | 0.59 |
DH-DLM-23-MET34 | 2.44 | 58.83 | 56.39 | 0.14 | 16.87 | 0.36 |
DH-DLM-23-MET35 | 16.15 | 80.16 | 64.01 | 0.21 | 9.51 | 0.33 |
DH-DLM-23-MET36 | 0.00 | 110.64 | 110.64 | 0.20 | 11.41 | 0.34 |
DH-DLM-23-MET37 | 0.00 | 74.98 | 74.98 | 0.16 | 15.57 | 0.36 |
DH-DLM-23-MET38 | 0.00 | 74.98 | 74.98 | 0.45 | 14.33 | 0.64 |
DH-DLM-23-MET41 | 0.00 | 45.72 | 45.72 | 0.20 | 3.74 | 0.25 |
DM23-MET-P8 | 0.00 | 47.24 | 47.24 | 0.36 | 17.76 | 0.59 |
(1) | Downhole thickness is true thickness. | |||||
(2) | Intervals reported are uncapped. | |||||
(3) | AuEq = g/t Au + (g/t Ag ÷ 77.70). Rounding may cause minor discrepancies in the AuEq column. | |||||
(4) | Certain intervals were not sampled because they were utilized for alternative purposes requiring intact core (i.e. – geotechnical analysis, additional metallurgical tests). These unsampled intervals (~1% of the total program footage) have been replaced by ‘zero grade’ for the purposes of this news release. |
Follow the link below to view drill collar location maps for the Florida Mountain Deposit drill program:
https://integraresources.com/site/assets/files/2572/dc_feb_location_-_fm_nr_-_full_extent_vf.pdf
Follow the link below to view drill collar location maps for the DeLamar Deposit drill program:
https://integraresources.com/site/assets/files/2572/dc_feb_location_-_dm_nr_-_full_extent_vf.pdf
Sampling and QA/QC Procedure
Thorough QA/QC protocols are followed on the Project, including insertion of duplicate, blank and standard samples in the assay stream for all drill holes. The samples are submitted directly to American Assay Labs in Reno, Nevada for preparation and analysis. Analysis of gold is performed using fire assay method with atomic absorption (“AA”) finish on a 1 assay ton aliquot. Gold results over 5 g/t are re-run using a gravimetric finish. Silver analysis is performed using ICP for results up to 100 g/t on a 5-acid digestion, with a fire assay, gravimetric finish for results over 100 g/t silver.
Qualified Person
The scientific and technical information contained in this news release has been reviewed and approved by Raphael Dutaut, Ph.D (P.Geo), Integra’s Vice President, Exploration. Mr. Dutaut is a “Qualified Person” as defined in National Instrument 43- 101 – Standards of Disclosure for Mineral Projects.
DeLamar Project Overview
The past producing DeLamar Project, which includes the adjacent DeLamar and Florida Mountain gold and silver deposits, is located in Owyhee County in southwest Idaho. Since acquiring the Project in 2017, the Company has demonstrated significant resource growth and conversion while demonstrating robust economic studies in its maiden Preliminary Economic Assessment and Preliminary Feasibility Study. An independent technical report for the DeLamar Project has been prepared in accordance with the requirements of NI 43-101 and is available under the Company’s profile at www.sedarplus.ca
About Integra Resources
Integra is one of the largest precious metals exploration and development companies in the Great Basin of the Western USA. Integra is currently focused on advancing its two flagship oxide heap leach projects: the past producing DeLamar Project located in southwestern Idaho and the Nevada North Project, comprised of the Wildcat and Mountain View deposits, located in northwestern Nevada. The Company also holds a portfolio of highly prospective early-stage exploration projects in Idaho, Nevada, and Arizona. Integra’s long-term vision is to become a leading USA focused mid-tier gold and silver producer.
Commerce Resources Corp. (TSX-V: CCE) (FSE: D7H0) is pleased to... READ MORE
North Bay Resources, Inc. (OTC: NBRI) is pleased to announce a re... READ MORE
NevGold Corp. (TSX-V:NAU) (OTCQX:NAUFF) (Frankfurt:5E50) is pleas... READ MORE
G2 Goldfields Inc. (TSX: GTWO) (OTCQX: GUYGF) is pleased to annou... READ MORE
Aya Gold & Silver Inc. (TSX: AYA) (OTCQX: AYASF) announced fi... READ MORE