i-80 GOLD CORP. (TSX: IAU) (NYSE: IAUX) reports its operating and financial results for the three and six months ended June 30, 2025, highlighting key developments across its asset portfolio. Unless otherwise stated, all amounts referred to herein are in U.S. dollars.
“The second quarter marked a major turning point at i-80 Gold,” stated Richard Young, President and Chief Executive Officer. “The equity financing completed in May has enabled us to advance key development initiatives across the five gold projects included in our development plan, and advance the Lone Tree autoclave refurbishment study which will be a key component of our hub-and-spoke mining and processing strategy for our high-grade underground projects.”
Mr. Young added, “In support of our three-phase development plan, we anticipate several key catalysts over the next 12 to 18 months. These include initiating underground development at Archimedes, completing infill drill programs and technical work to support upcoming feasibility studies at four of our gold projects, and completing the Lone Tree autoclave feasibility study. In parallel, permitting efforts are well underway across the portfolio as we recently expanded our permitting team and continue working collaboratively with regulators and local stakeholders. We are also actively working to secure the next phase of our recapitalization plan to continue laying the foundation to achieve our expected average annual target of more than 600,000 ounces of gold by the early 2030’s(3).”
OPERATING AND FINANCIAL HIGHLIGHTS
Second Quarter 2025
Three months ended June 30, 2025
Three months ended
June 30, |
Six months ended
June 30, |
||||
2025 | 2024 | 2025 | 2024 | ||
Revenue | $000s | 27,836 | 7,184 | 41,884 | 15,597 |
Net loss | $000s | (30,215) | (41,005) | (71,420) | (60,705) |
Loss per share | $/share | (0.05) | (0.11) | (0.14) | (0.18) |
Cash flow used in operating activities | $000s | (11,335) | (24,559) | (34,036) | (49,782) |
Cash and cash equivalents | $000s | 133,691 | 47,812 | 133,691 | 47,812 |
Drilling | ft | 8,717 | 48,796 | 23,479 | 40,487 |
Gold ounces sold1 | oz | 8,400 | 3,445 | 13,352 | 7,506 |
Average realized gold price2 | $/oz | 3,301 | 2,337 | 3,124 | 2,188 |
Notes to table above:
1.Gold ounces sold include attributable gold from mineralized material sales at a payable factor of 57% in 2025 (2024 – 58%). 2.This is a Non-GAAP Measure; please see “Non-GAAP Measures” section. |
|||||
“Given that i-80’s core assets are brownfield projects with a well understood and sizeable mineral resource base, we continue to advance steadily with relatively low technical and permitting risk due to their historical mining footprints and existing infrastructure,” stated Paul Chawrun, Chief Operating Officer. “The team remains focused on the infill drill programs in support of the upcoming feasibility studies, permitting, and development activities across all core assets as we progress toward achieving our staged production goals and continue to optimize the value and timing of each project within the broader development plan.”
RECAPITALIZATION UPDATE
The Company continues to execute a recapitalization strategy aimed at strengthening its balance sheet and funding its growth plans.
In May 2025, the Company raised gross proceeds of $185.5 million through a bought deal public offering and a concurrent private placement, with combined net proceeds of $175.2 million. If fully exercised, the warrants issued as part of the financing and expiring November 16, 2027, could provide the Company with up to approximately $130 million in additional proceeds. A portion of the proceeds of the offering were used to settle the first phase of the recapitalization plan totaling $42.0 million for gold and silver deliveries under the prepay instruments. Through to mid-2026, approximately $92 million is expected to be allocated to fund construction activities, drilling, permitting and technical studies across five gold projects including the Lone Tree autoclave processing facility, all part of the development plan.
The Company is actively working to secure the balance of required capital to execute the development plan and is in discussions with several parties regarding additional financing options. These potential options include debt facilities, as well as a royalty sale, and the sale of its FAD property, which is a non-core asset. Management aims to complete the balance of its recapitalization plan by mid-2026, aligning with the date of maturity of the Orion Convertible Loan.
UPCOMING CATALYSTS
The Company’s three-phase development plan prioritizes its high-grade underground refractory deposits and the refurbishment and commissioning of its Lone Tree autoclave to serve as a central processing hub, while also progressing permitting and technical work on its two large-scale open pit projects. In alignment with this strategy, the Company expects to achieve the following catalysts:
Archimedes Underground
Feasibility Studies
Recapitalization Plan
OPERATIONAL AND FINANCIAL OVERVIEW
Three months ended June 30, |
Six months ended June 30, |
|||
(in thousands of USD) | 2025 | 2024 | 2025 | 2024 |
Revenue | 27,836 | 7,184 | 41,884 | 15,597 |
Cost of sales | (26,491) | (19,422) | (37,257) | (27,753) |
Depletion, depreciation and amortization | (547) | (74) | (923) | (451) |
Gross profit (loss) | 798 | (12,312) | 3,704 | (12,607) |
Expenses | ||||
Pre-development, evaluation and exploration | 9,045 | 10,436 | 18,590 | 17,710 |
General and administrative | 7,338 | 5,733 | 12,328 | 9,958 |
Property maintenance | 3,166 | 2,781 | 7,313 | 7,103 |
Loss from operations | (18,751) | (31,262) | (34,527) | (47,378) |
Other income and expenses, net | (2,769) | (600) | (19,995) | 4,239 |
Interest expense | (8,695) | (8,757) | (16,898) | (16,793) |
Loss before income taxes | (30,215) | (40,619) | (71,420) | (59,932) |
Deferred tax expense | — | (386) | — | (773) |
Net loss | (30,215) | (41,005) | (71,420) | (60,705) |
Granite Creek
The Granite Creek property includes the Granite Creek underground project, a fully permitted, constructed and operating mine and the Granite Creek open pit oxide deposit adjacent to the underground project, currently in early-stage permitting. The Granite Creek underground is the Company’s first brownfield project to be redeveloped and is currently ramping up towards steady-state gold output.
Granite Creek Property | Three months ended June 30, |
Six months ended June 30, |
|||
Operational Statistics | 2025 | 2024 | 2025 | 2024 | |
Oxide mineralized material mined | tonnes | 24,074 | 16,314 | 39,397 | 25,778 |
Sulfide mineralized material mined | tonnes | 11,201 | 3,196 | 25,844 | 6,434 |
Total oxide and sulfide mineralized material mined | tonnes | 35,275 | 19,510 | 65,241 | 32,212 |
Oxide mineralized material mined grade | g/t | 11.38 | 11.49 | 11.74 | 12.23 |
Sulfide mineralized material mined grade | g/t | 7.43 | 10.08 | 7.93 | 9.23 |
Low-grade mineralized material mined1 | tonnes | 16,173 | 14,033 | 39,019 | 25,748 |
Low-grade mineralized material grade1 | g/t | 3.03 | 3.18 | 2.88 | 3.35 |
Waste mined | tonnes | 31,947 | 42,849 | 59,409 | 75,802 |
Total material mined | tonnes | 83,395 | 76,392 | 163,669 | 133,762 |
Processed mineralized material – sulphide | tonnes | 7,014 | 4,702 | 7,014 | 4,702 |
Processed mineralized material – leach | tonnes | 18,750 | — | 52,587 | — |
Total processed mineralized material | tonnes | 25,764 | 4,702 | 59,601 | 4,702 |
Gold ounces sold2 | oz | 5,981 | 1,809 | 9,086 | 3,384 |
Underground mine development (pre-development) | ft | 692 | 1,515 | 1,196 | 2,264 |
Drilling | ft | 2,978 | 34,414 | 2,978 | 18,479 |
Financial Statistics | 2.025 | 2.024 | 2025 | 2024 | |
Mining cost (total mineralized material and waste) | $/t | 175 | 113 | 173 | 125 |
Processing cost (processed mineralized material) | $/t | 133 | 88 | 74 | 147 |
Site general and administrative (“G&A”) (total mineralized material mined3) | $/t | 34 | 31 | 32 | 38 |
Royalties | $000s | 1,148 | 321 | 1,654 | 1,555 |
Capital expenditure4 | $000s | 1,114 | 278 | 1,491 | 739 |
Pre-development, evaluation and exploration expenses | $000s | 5,949 | 7,634 | 9,719 | 12,115 |
Notes to table above:
1Low-grade mineralized material extracted as part of the mining process that is below cut-off grade but incrementally economic. 2Gold ounces sold include attributable gold from mineralized material sales at a payable factor of 57% in 2025 (2024 – 58%). 3Total mineralized material mined consists of sulfide, oxide, and low-grade mineralized material. 4Capital expenditure based on accrual basis. |
|||||
Granite Creek Underground
Mining activities during the current quarter exceeded levels reported in the comparative prior-year period, primarily driven by additional faces available to mine due to stope development and changes in sequencing of mining. Management expects groundwater inflows to remain at or near the current ingress flow rates for the foreseeable future. Improvements to the existing infrastructure are ongoing, including the installation of at least two additional dewatering wells, an expanded water treatment facility, and an in-line piping and pumping system for the removal of mine contact water from underground workings, which are expected to positively impact development rates.
The Company continues to encounter elevated levels of oxide mineralized material compared to levels anticipated in the March 2025 Preliminary Economic Assessment at Granite Creek. The lower-grade oxide mineralized material continues to be suitable for processing via heap leach at the Company’s Lone Tree heap leach facility. During the quarter, 1,554 ounces of low-grade oxide material from Granite Creek was leached and sold from the Lone Tree heap leach facility.
As at June 30, 2025, the Company has delivered approximately 28,000 tonnes of sulfide mineralized material, waiting to be processed under a new toll milling agreement with a third party. Under the new toll milling agreement, the material is expected to be processed within 120 days of delivery to the process facilities.
For the three months ended June 30, 2025, $4.9 million was spent on pre-development expenses. Pre-development, evaluation, and exploration expenses for the six months ended June 30, 2025 were primarily related to underground development of $7.8 million and infill drilling.
Infill drilling of the South Pacific Zone began in June 2025 with two active drill rigs – one operating from underground and one from surface. Three additional rigs are expected to be mobilized in the third quarter, with one additional rig underground and two at surface. These activities are expected to further support mineral resource definition and expansion. The exploration drift was completed at the end of June to a shorter extent than initially planned. The initial underground drill plan was modified to include additional surface drilling as part of the program. The infill drill program aims to upgrade the mineral resource and form the basis for the upcoming feasibility study, which is targeted for completion in the first quarter of 2026.
Granite Creek Open Pit
Following the release of the Granite Creek open pit PEA, technical work is underway to advance the project toward either a pre-feasibility or a feasibility-level study. Simultaneously, trade off analyses are being conducted to optimize the project economics.
Permitting work is in the initial stages and advancing as expected. Granite Creek open pit has the potential to contribute to company-wide gold output by the end of the decade.
Ruby Hill Property
The Archimedes underground project is expected to be the Company’s second underground mine, while Mineral Point is a large oxide gold and silver deposit with the potential to become the Company’s largest gold producing asset.
Archimedes Underground
Surface infrastructure has been completed, and the initial development of the underground exploration drift is anticipated to commence in the third quarter of 2025.
Permitting for mining above the 5100-foot level at Archimedes underground is nearing completion, with approval for advancement expected shortly. This phase of permitting covers mining activities above the 5100-foot elevation, a threshold consistent with previously approved permits for open pit mining at Ruby Hill. Permitting below the 5100-foot elevation is expected to begin immediately upon receipt of the first phase of permits. This sequential approach to permitting expedites mining while simultaneously pursuing remaining permits for the lower section.
Infill drilling will be initiated in the fourth quarter of 2025 in the Archimedes upper zone and in the first quarter of 2026 for the Archimedes lower zone.
The timeframe for first gold is approximately 14 months in duration from the commencement of portal construction which is expected to commence in the third quarter. In the meantime, the Company continues leaching the historic leach pads. During the three-month period, 665 ounces of gold were sold from Ruby Hill.
Mineral Point
A drill program for the Mineral Point open pit project commenced in June 2025 with two surface core drill rigs, completing approximately 5,800 feet of surface core drilling in the quarter to support geotechnical, metallurgical and hydrogeology studies for baseline data to advance permitting and technical reports. Following the release of a PEA in the first quarter of 2025, strategic evaluations are underway to determine optimal timing of a pre-feasibility or a feasibility-level study.
Cove Project
National Environmental Policy Act permitting activities are underway with the Bureau of Land Management in anticipation of an Environmental Impact Statement. i-80 Gold is actively advancing major permit applications with the goal of aligning regulatory approvals with planned development timelines. Cove is expected to be the Company’s third underground mine and begin contributing to company-wide production in mid-2029.
In addition to the permitting process, an infill drill program was completed during the first quarter of 2025 to increase confidence in the mineral resource and collect data for engineering work to complete a feasibility study expected in the first quarter of 2026 while also incorporating additional metallurgical work. Underground delineation drilling was completed during the first quarter on the Helen and Gap deposits with two core rigs, completing approximately 15,000 feet of core drilled, bringing total drilling over the course of the infill campaign to approximately 145,000 feet. All assay results have been received since the inception of the infill drilling campaign in 2023 and expected to provide an updated mineral resource estimate in the third quarter of 2025. The geological model has been updated with these new drill results, and an updated resource estimate is in progress to be included in the feasibility study.
Lone Tree Processing Facility
The Lone Tree processing facility has one of three autoclave facilities in Nevada and is a strategic asset in unlocking value from i-80 Gold’s three underground deposits by providing an owner-operated processing facility for the Company’s high-grade underground refractory material.
Currently, the Lone Tree autoclave refurbishment feasibility-level Class 3 engineering study is underway in collaboration with Hatch Ltd., an industry leader in autoclave technology, building on an internal feasibility study completed in 2023. The autoclave is envisioned to process refractory mineralized material from the Company’s three underground mines, Granite Creek, Archimedes and Cove, creating a regional hub-and-spoke mining and processing strategy. Concurrently, i-80 Gold is recruiting the owner’s team to oversee the engineering and execution of Lone Tree’s refurbishment, along with risk mitigation planning and opportunities to accelerate the development timeline.
The updated technical study for the facility’s refurbishment will incorporate value engineering initiatives and updated cost estimates to support an improved execution strategy. Completion of the revised feasibility study is targeted for the fourth quarter of 2025.
Lone Tree’s processing facility is currently permitted for the operational components in use; however, new and revised applications will need to be approved for air quality and mercury operating programs, in addition to, Water Pollution Control and Reclamation Permit modifications for the processing and environmental controls included in the refurbishment plan.
1,754 ounces of gold were sold from the Lone Tree leach pads during the three-month period. The leaching of the historic leach pad at Lone Tree continues to produce gold at profitable quantities. The Company plans to continue to recover ounces from the Lone Tree leach pads as long as it is economical to do so.
Capital expenditures of approximately $0.6 million during the three and six months ended June 30, 2025 and in the comparative period were related to the technical work on the refurbishment of the autoclave processing plant.
FINANCIAL STATEMENTS
This press release should be read in conjunction with i-80 Gold’s Quarterly Report on Form 10-Q, including the unaudited condensed consolidated interim financial statements and associated Management’s Discussion and Analysis of Operations and Financial Condition for the three and six months ended June 30, 2025 included therein, which is available on the Company’s website at www.i80gold.com, on EDGAR at www.sec.gov, and on SEDAR+ at www.sedarplus.ca.
QUALIFIED PERSONS
All scientific and technical information contained in this press release has been reviewed, verified and compiled under the supervision of Paul Chawrun, P.Eng., member of the Professional Engineers of Ontario (PEO) and the Company’s Chief Operating Officer, and Tyler Hill, CPG., Vice President Geology for the Company, each of whom is a “Qualified Person” within the meaning of National Instrument 43-101 – Standards of Disclosure for Mineral Projects and S-K 1300 and Subpart 1300 of Regulation S-K under the U.S. Securities Act of 1933, as amended.
ENDNOTES
(1) | Gold ounces sold include attributable gold from mineralized material sales at a payable factor of 57% in 2025 (2024 – 58%). |
(2) | This is a Non-GAAP Measure; please see “Non-GAAP Financial Performance Measures” section. |
(3) | Consolidated production estimates and average annual production targets include the Cove Project, Archimedes Underground Project, Mineral Point Open Pit Project, Granite Creek Underground Project, and Granite Creek Open Pit Project and are based on the most recent life-of-mine production schedules disclosed in the latest technical studies filed for each respective project and related property. These anticipated production figures are preliminary in nature and are based on mineral resources, which do not have demonstrated economic viability, and which are not mineral reserves. In addition, each of the foregoing technical reports are preliminary economic assessments/initial assessment that are preliminary in nature and each include an economic analysis that is based, in part, on inferred mineral resources. Inferred mineral resources are considered too speculative geologically to have for the application of economic considerations applied to them that would enable them to be categorized as mineral reserves. As such, there is no certainty that the production targets will be realized. The production target is also pending the completion of the autoclave refurbishment Class 3 engineering study (where a series of trade-off scenarios will be considered comparing full autoclave refurbishment to alternate toll milling and ore purchase agreement options that could potentially be available), Board approval, and the successful funding, development, and commissioning of the Company’s Lone Tree autoclave processing facility. The production target presented herein is a Company goal and not a projection of results and should not be taken as production guidance. |
ABOUT i-80 GOLD CORP.
i-80 Gold Corp. is a Nevada-focused mining company committed to building a mid-tier gold producer through a new development plan to advance its high-quality asset portfolio. The Company is the fourth largest gold mineral resource holder in the state with a pipeline of high-grade development and production-stage projects strategically located in Nevada’s most prolific gold-producing trends. Leveraging its central processing facility following an anticipated refurbishment, i-80 Gold is executing a hub-and-spoke regional mining and processing strategy to maximize efficiency and growth.
GR Silver Mining Ltd. (TSX-V: GRSL) (FRANKFURT: GPE) is pleased ... READ MORE
Argenta Silver Corp. (TSX-V: AGAG) (OTCQB: AGAGF) (FSE: T1K) is p... READ MORE
NexMetals Mining Corp. (TSX-V: NEXM) (NASDAQ: NEXM) reports assay... READ MORE
Amex Exploration Inc. (TSX-V: AMX) (FSE: MX0) (OTCQX: AMXEF) is... READ MORE