
Fortuna Mining Corp. (NYSE: FSM) (TSX: FVI) reports production results for the fourth quarter and full year 2025 from its three operating mines in Latin America and West Africa. In 2025, Fortuna achieved its annual production guidance, delivering 317,001 gold equivalent ounces1. Unless otherwise noted, all dollar amounts in this news release are expressed in U.S. dollars.
Fourth Quarter 2025 Highlights
Full Year 2025 Highlights
2026 Outlook Highlights
Notes:
2025 Consolidated GEO Production
| Q4 20252 | Q3 20252 | FY 2025 | 2025 Guidance (000)1 | |||||
| Ongoing Operations | ||||||||
| Séguéla, Côte d’Ivoire | 36,942 | 38,799 | 152,426 | 134 – 147 | ||||
| Lindero, Argentina | 19,201 | 24,417 | 87,489 | 93 – 105 | ||||
| Caylloma, Peru | 8,987 | 9,246 | 39,292 | 44 – 49 | ||||
| Total from ongoing operations | 65,130 | 72,462 | 279,207 | 271 – 301 | ||||
| Divested Operation | ||||||||
| Yaramoko, Burkina Faso | – | – | 37,794 | 38 | ||||
| Total from ongoing and divested operations | 65,130 | 72,462 | 317,001 | 309 – 339 | ||||
Note:
West Africa Region
Séguéla Mine, Côte d’Ivoire
Delivered record gold production above the upper end of annual guidance.
| Q4 2025 | Q3 2025 | FY 2025 | 2025 Guidance (000) | |||||
| Tonnes milled | 410,014 | 435,770 | 1,718,973 | – | ||||
| Average tpd milled | 4,506 | 4,737 | 4,709 | – | ||||
| Gold grade (g/t) | 3.16 | 3.01 | 2.98 | – | ||||
| Gold recovery (%) | 92.1 | 91.4 | 92.3 | – | ||||
| Gold production (oz)1 | 36,942 | 38,799 | 152,426 | 134 – 147 | ||||
Note:
Mining
Mine production for the fourth quarter of 2025 totaled 340,464 tonnes of ore, averaging 3.71 g/t Au, and containing an estimated 40,614 ounces of gold from the Antenna, Ancien, and Koula pits. Ore tonnes mined were lower than tonnes milled during the quarter, in line with the mine plan and the strategy to reduce surface stockpiles. A total of 3,920,293 tonnes of waste was moved during the period, resulting in a strip ratio of 11.5:1.
Processing
Séguéla produced 36,942 ounces of gold during the quarter at an average head grade of 3.16 g/t Au. The 5% decrease in ounces produced is a result of a 6% decrease in tonnes milled, partially offset by 5% higher grade compared to the third quarter of 2025. Lower tonnes milled during the quarter were primarily due to downtime caused by a failure of the SAG mill motor cooling system in October and other planned maintenance activities. Gold recoveries increased modestly during the quarter following planned maintenance on the carbon-in-leach tanks completed in the third quarter. Several initiatives are currently underway to further improve gold recovery in 2026.
Project Updates
Full Year 2025 Production
Séguéla produced a record total of 152,426 ounces of gold in 2025, 4% above the upper end of annual guidance.
Latin America Region
Lindero Mine, Argentina
Mechanical downtime at primary crusher and HPGR resolved in December; quarter production impacted
| Q4 2025 | Q3 2025 | FY 2025 | 2025 Guidance (000) | |||||
| Ore placed on pad (t) | 1,191,030 | 1,699,007 | 6,471,573 | – | ||||
| Gold grade (g/t) | 0.63 | 0.60 | 0.58 | – | ||||
| Gold production (oz)1 | 19,201 | 24,417 | 87,489 | 93 – 105 | ||||
Note:
Mining
During the fourth quarter, Lindero mined 1.41 million tonnes of ore, maintaining a low strip ratio of 1.5:1. A total of 1.2 million tonnes of ore were placed on the leach pad at an average head grade of 0.63 g/t Au, containing an estimated 24,040 ounces of gold. Quarter over quarter, the reduced tonnage of ore placed on the leach pad reflects lower mechanical availability of the crushing system.
Processing
Lindero produced a total of 19,201 ounces of gold during the quarter, representing a 21% decrease in production quarter over quarter. As previously disclosed (see Fortuna news release dated November 5, 2025), Lindero experienced unplanned downtime of the primary crusher in late September. The primary crusher was returned to full service on December 19, 2025. During the downtime period, Management implemented several mitigation measures, including the use of a portable jaw crusher and direct run-of-mine ore screening, which offset the impact of the primary crusher interruption.
On December 8, 2025, the HPGR tertiary crusher experienced abnormal vibration originating from one of its two cardan shafts, resulting in a twelve-day full stoppage. A spare cardan shaft was installed, and the HPGR circuit was restarted on December 20, 2025. The production loss associated with the HPGR repair could not be mitigated. Consequently, gold production for December, and cumulative production for the fourth quarter, were below Management’s plan, resulting in Lindero not achieving its annual production guidance.
Following an engineering assessment of the primary crusher and its supporting foundations, Management has approved a planned 30-day replacement of the steel foundations starting in
March 2026, at an estimated capital cost of $2.2 million. Mining operations will continue ahead of the scheduled work, with ore being stockpiled to support uninterrupted stacking on the leach pad during the foundation replacement period.
Full Year 2025 Production
Lindero produced a total of 87,489 ounces of gold in 2025, 6% below the lower end of annual guidance.
Caylloma Mine, Peru
Strong operational performance; base metal production exceeded the upper end of annual production guidance.
| Q4 2025 | Q3 2025 | FY 2025 | 2025 Guidance | |||||
| Tonnes milled | 139,997 | 140,523 | 555,649 | – | ||||
| Average tpd milled | 1,556 | 1,561 | 1,556 | – | ||||
| Silver grade (g/t) | 65 | 63 | 65 | – | ||||
| Silver recovery (%) | 84.64 | 82.03 | 83.42 | – | ||||
| Silver production (oz)1 | 248,882 | 233,612 | 966,108 | 900,000 – 1,000,000 | ||||
| Lead grade (%) | 2.95 | 3.01 | 3.1 | – | ||||
| Lead recovery (%) | 92.60 | 91.10 | 91.33 | – | ||||
| Lead production (lbs) | 8,443,705 | 8,492,206 | 34,696,351 | 29,000,000 – 32,000,000 | ||||
| Zinc grade (%) | 4.32 | 4.27 | 4.55 | – | ||||
| Zinc recovery (%) | 91.11 | 90.59 | 90.99 | – | ||||
| Zinc production (lbs) | 12,149,675 | 11,988,738 | 50,761,436 | 45,000,000 – 49,000,000 | ||||
| GEO production (oz) | 8,987 | 9,246 | 39,292 | 44,000 – 49,000 |
Note:
The lower GEO production when compared to guidance reflects the significant rise in gold prices through 2025 resulting in changes to the gold-to-base-metal ratios used in the GEO calculation.
Mining
Mine production for the fourth quarter totaled 134,697 tonnes of ore, with 77% mined from the Animas vein using the overhand cut and fill method, 20% mined primarily by sublevel stoping from the Cimoide ASNE vein, and the remaining 3% from the Ramal Carolina vein.
Processing
Caylloma produced 248,882 ounces of silver in the quarter at an average head grade of 65 g/t Ag, maintaining production levels consistent with the previous quarter.
Zinc and lead production totaled 12.1 million and 8.4 million pounds, respectively, at average head grades of 4.32 % Zn and 2.95 % Pb. Base metal production remained consistent with the previous quarter, as mining continued from the same levels and stopes.
Project Update
The power grid enhancement project was successfully completed and commissioned in early December. As a result, the Caylloma mine is now able to meet 100% of its current and future energy requirements through the national power grid, which is supplied entirely from renewable sources. This transition eliminates the need for supplemental diesel-based power generation.
Full Year 2025 Production
Caylloma produced a total of 966,108 ounces of silver, 50.8 million pounds of zinc, and 34.7 million pounds of lead or 39,292 GEO in 2025.
2026 Outlook
2026 is a key year in the growth of Fortuna, with a budget focused on materializing its Brownfields projects, with the aim of subsequently achieving the corporate target of producing 500,000 ounces annually.
Fortuna is allocating approximately $100 million to the advancement of the Diamba Sud Gold Project, including exploration, with a focus on early works to de-risk the project timeline as the Company moves toward a construction decision by mid-year. At the Séguéla Mine, a growth budget of approximately $14 million has been assigned to the development of Sunbird underground infrastructure and mill expansion studies. In addition, the Company is allocating $55 million towards exploration across its portfolio.
Fortuna’s growing financial strength underpins planned investments in project development and expansion. As of December 31, 2025, it is estimated that the Company had liquidity of $704 million, and a net cash position of $382 million. The foregoing is preliminary unaudited financial information and has been prepared by Management and remains subject to final review of the Company’s audit committee and approval of the Company’s board of directors. Refer to the “Cautionary Statement” section at the end of this news release.
GEO production for 2026 is guided to be between 281,000 and 305,000 ounces, driven by increased production at the Séguéla Mine, offset by lower GEO production at the Caylloma Mine due to the effect of a higher gold price on the gold-to-base-metal conversion used in the GEO calculation.
Consolidated AISC is expected to be between $1,830 and $1,975 per ounce, representing a slight increase compared to 2025. This increase is primarily attributable to higher royalties of approximately $30 per ounce, assuming a gold price of $3,750 for 2026, and the impact of relative metal prices at Caylloma, estimated at $60 per ounce on a gold equivalent basis. In addition, AISC reflects a higher cost base at Séguéla, as the prior year benefited from the processing of ore inventory with lower unit mining costs. These factors are partially offset by lower cash costs at Lindero and higher gold production at Séguéla.
2026 GEO consolidated production and cost guidance table
| Mine | Production (000) | Cash Cost1,2, 3,5 | AISC1,2,3,5 | |||
| Silver | Ag Eq | ($/oz Ag Eq) | ($/oz Ag Eq) | |||
| Caylloma, Peru3 | 2,400 – 2,700 | 17.3 – 19.1 | 31.3 – 35.6 | |||
| Gold | Au | ($/oz Au) | ($/oz Au) | |||
| Lindero, Argentina4 | 92 – 102 | 975 – 1,140 | 1,520 – 1,655 | |||
| Séguéla, Côte d´Ivoire | 160 – 170 | 735 – 815 | 1,630 – 1,730 | |||
| GEO Consolidated Total | 281 – 3053 | $895 – 1,0006 | $1,830 – 1,9756 | |||
Notes:
| Mine | Cash Costa,b,c | AISCa,b,c | |||
| Silver | ($/oz Ag Eq) | ($/oz Ag Eq) | |||
| Caylloma, Peru | 14.12 | 21.72 | |||
| Gold | ($/oz Au) | ($/oz Au) | |||
| Lindero, Argentina | 1,051 | 1,793 | |||
| Séguéla, Côte d’Ivoire | 584 | 1,153 |
(a) Cash cost and AISC are non-IFRS financial measures; refer to section titled “Non-IFRS Financial Measures” below.
(b) Silver equivalent was calculated using metal prices of $2,233/oz Au, $27.88/oz Ag, $2,072/t Pb and $2,786/t Zn for the year ended December 31, 2024.
(c) Further details on cash cost and AISC for the year ended December 31, 2024 are disclosed on pages 32 and 36 (with respect to cash cost) and pages 34 and 38 (with respect to AISC) of the Company’s management discussion and analysis (“MD&A”) for the year ended December 31, 2024 dated as of March 5, 2025 (“2024 MD&A”) which is available under Fortuna’s SEDAR+ profile at www.sedarplus.ca and is incorporated by reference into this news release, and the note under “Non-IFRS Financial Measures” below.
2026 Asset Outlook
Diamba Sud Gold Project, Senegal
Advancing early works toward a mid-2026 construction decision
Supported by robust PEA economics (refer to Fortuna news release dated October 15, 2025), Fortuna is advancing the Diamba Sud Gold Project toward a mid-2026 final investment decision (“FID”). Current progress includes the commencement of construction of the new accommodation camp and critical ancillary infrastructure, along with ongoing engineering and procurement activities.
Key milestones include:
To support continued project advancement, Fortuna has allocated $69 million in pre-FID capital, comprising $2.5 million for the completion of the feasibility study and $67 million for early works. This investment targets de-risking critical-path activities, including:
In addition to project-level investment, Fortuna expects to incur approximately $28 million to advance ongoing exploration activities and enhance operational readiness, including:
Séguéla Mine, Côte d’Ivoire
Exploration success leads to production expansion opportunities
Séguéla’s mine plan for 2026 considers mining from the Antenna, Ancien, Koula, and Sunbird pits, with planned processing of 1.75 million tonnes of ore at an average grade of 3.2 g/t Au. Capital investments are estimated at $90.2 million, including $61.7 million for sustaining capital expenditures, $14.5 million for growth CapEx, and $14.0 million for Brownfields exploration programs.
Major sustaining capital investments include:
| Capitalized stripping | $51.0 million | ||
| Miscellaneous Infrastructure | $8.6 million |
Major growth capital investments include:
| Sunbird Underground mine portal | $7.5 million | ||
| Sunbird Underground Infrastructure and permitting – Power extension, transformer, civil works, and primary fans | $3.4 million |
Cash cost and AISC:
Cash cost is expected to be between $735 and $815 per ounce of gold, representing an increase compared to 2025. The increase is primarily driven by inventory accounting, as the prior year benefited from processing low-cost stockpiles, and by a higher proportion of stripping costs remaining in OpEx rather than being capitalized. This is partially offset by higher grades.
AISC is expected to be between $1,630 and $1,730 per ounce of gold, reflecting the higher cash cost relative to 2025 and the impact of higher royalties of approximately $30 per ounce, assuming a gold price of $3,750 for 2026.
2026 guidance compared to 2026 outlook provided in 2025:
Gold production for 2026 is in line with the 2026 outlook provided in 2025 (refer to Fortuna news release dated May 13, 2025). The guidance range has been refined to between 160,000 and 170,000 ounces, reflecting a narrower range with no change to the lower end of the outlook.
Cash cost for 2026 is expected to be higher than the 2026 outlook provided in 2025, primarily due to the impact of 5% higher mining costs and 15% higher processing costs.
AISC guidance for 2026 is expected to be approximately $350 per ounce higher than the outlook provided in 2025, driven mainly by increased royalties, reflecting an estimated $150 per ounce impact associated with the gold price assumption, higher operating costs, including waste striping of approximately $130 per ounce, and higher capital expenditures and genset leases of approximately $55 per ounce.
Lindero Mine, Argentina
Sustained cost discipline supports lower costs
The Lindero Mine is expected to place approximately 7.1 million tonnes of ore on the leach pad in 2026, averaging 0.59 g/t Au and containing an estimated 135,000 ounces of gold. Capital investments are estimated at $41.0 million, including $22.4 million in capitalized stripping, $14.0 million in sustaining capital, and $4.6 million allocated to Brownfields exploration. The waste stripping ratio is planned to reduce from 2.2:1 in 2025 to an average of 1.5:1, in line with the life of mine design.
Major sustaining capital investments include:
| Capitalized stripping | $22.4 million | ||
| Plant (maintenance and acquisitions) | $5.7 million | ||
| Mine fleet (maintenance and acquisitions) | $5.4 million | ||
| Primary crusher foundation replacement | $2.2 million |
Cash cost and AISC:
Cash cost is expected to decrease in 2026 to a range of $975 to $1,140 per ounce of gold, reflecting operating efficiency initiatives currently in place, lower consumable prices, a reduced stripping ratio, and the favorable impact of Argentine peso foreign exchange movements against the U.S. dollar.
AISC is expected to improve in 2026 to a range of $1,520 to $1,655 per ounce of gold, supported by lower sustaining capital expenditures, reduced operating costs, and higher ounces sold as production increases compared to 2025. While AISC is expected to be elevated in the first quarter of 2026 due to the planned primary crusher foundation replacement, the Company anticipates a strong sequential cost reduction through the year, reaching the low $1,300s by the fourth quarter, reflecting the completion of planned capital spending and the full benefit of operational efficiencies.
Caylloma Mine, Peru
Continued solid production
The Caylloma Mine is scheduled to process 550,000 tonnes of ore in 2026, averaging 61 g/t Ag, 2.5 % Pb, and 3.8 % Zn. Capital investments are estimated at $29.9 million, including $22.2 million for sustaining capital, $1.6 million for non-sustaining capital, and $6.0 million for Brownfields exploration programs.
Major sustaining capital investments include:
| Mine development and infill drilling | $8.1 million | ||
| TSF-3 expansion capacity | $6.6 million | ||
| TSF-2 closure (Phase 1) | $2.1 million |
Cash cost and AISC:
Cash cost is expected to be between $17.3 and $19.1 per ounce of silver equivalent, while AISC is expected to be between $31.3 and $35.6 per ounce of silver equivalent. This represents an increase compared to 2025, primarily due to the impact of relative metal prices on silver equivalent production. The metal prices assumed for 2026 guidance, compared to those used for the 2025 guidance, are estimated to increase AISC by approximately $9 per ounce.
2026 Exploration Outlook
Supporting growth through focused Brownfields and Greenfields exploration
The Company has a total mineral exploration budget of $55.0 million for 2026, compared to an estimated $49.9 million invested in 2025. Brownfields exploration represents 52%, while Greenfields initiatives, including $8.8 million allocated to the Diamba Sud Gold Project, representing 48%.
Brownfields Exploration
Fortuna’s consolidated Brownfields exploration budget for 2026 totals $26.8 million and includes approximately 127,000 meters of reverse circulation and diamond core drilling.
Séguéla Mine, Côte d’Ivoire
The Brownfields exploration budget at Séguéla is $12.2 million, including approximately 69,000 meters of exploration drilling. Programs are focused on resource upgrade drilling primarily at the Sunbird Underground project, infill and expansion drilling at the Kingfisher deposit, and continued target generation.
Diamba Sud Gold Project, Senegal
The Brownfields exploration budget at Diamba Sud is $8.8 million, including approximately 35,000 meters of exploration drilling to support resource upgrade drilling and continued target generation.
Lindero Mine, Argentina
The Brownfields exploration budget for Lindero is $3.7 million, including approximately 11,000 meters of exploration drilling at Arizaro, focused on further testing and extending the 2.5-kilometer strike potential to the southwest and at depth.
Infill drilling totaling approximately 6,000 meters is planned at Lindero to target Inferred Mineral Resources located below the reserve ultimate pit shell. The program is designed to increase confidence in the geologic continuity of mineralization, with the objective of converting additional resources to reserves and extending the mine life.
Caylloma Mine, Peru
The Brownfields exploration program budget at Caylloma is $3.8 million, including approximately 12,000 meters of diamond core drilling targeting extensions to ore shoots 3 and 4 at the Animas zone, along with continued exploration of several other near mine anomalies.
Greenfields Exploration
Generative Greenfields exploration programs in Argentina, Côte d’Ivoire, Mexico, and Senegal are supported by a budget of $24.7 million.
Mexico
Exploration activities in Mexico will focus on project generation and target testing across several emerging projects. A total of $3.1 million has been budgeted, including approximately 6,000 meters of planned diamond core drilling.
Côte d’Ivoire
The exploration budget for Côte d’Ivoire is $3.7 million, with the majority allocated to advancing exploration activities at Guiglo and Tongon North. Planned programs include approximately 19,000 meters of auger drilling and 17,000 meters of reverse circulation drilling for target generation and testing.
Senegal
The exploration budget for Senegal is $3.7 million, supporting approximately 12,000 meters of auger drilling and approximately 10,000 meters of RC drilling for continued target generation.
Argentina
The $5.0 million exploration budget for Argentina is planned to support work at Cerro Lindo and other regional exploration projects. Programs include approximately 7,000 meters of diamond core drilling at Cerro Lindo as part of an extensive reconnaissance program targeting this significant anomaly, as well as an additional 3,000 meters of diamond core drilling across other regional generative targets.
Qualified Person
Eric Chapman, Senior Vice President of Technical Services for Fortuna Mining Corp., is a Professional Geoscientist registered with Engineers and Geoscientists British Columbia (Registration Number 36328) and a Qualified Person as defined by National Instrument 43-101 Standards of Disclosure for Mineral Projects. Mr. Chapman has reviewed and approved the scientific and technical information contained in this news release and has verified the underlying data.
Paul Weedon, Senior Vice President of Exploration for Fortuna Mining Corp., is a Qualified Person as defined by National Instrument 43-101 being a member of the Australian Institute of Geoscientists (Membership Number 6001). Mr. Weedon has reviewed and approved the scientific and technical information relating to exploration contained in this news release.
About Fortuna Mining Corp.
Fortuna Mining Corp. is a Canadian precious metals mining company with three operating mines and a portfolio of exploration projects in Argentina, Côte d’Ivoire, Mexico, and Peru, as well as the Diamba Sud Gold Project in Senegal. Sustainability is at the core of our operations and stakeholder relationships. We produce gold and silver while creating long-term shared value through efficient production, environmental stewardship, and social responsibility.
Fireweed Metals Corp. (TSX-V: FWZ) (OTCQX: FWEDF) is pleased to r... READ MORE
Borealis Mining Company Limited (TSX-V:BOGO) (OTC Pink: BORMF) (F... READ MORE
Alpha Bowl Drilling Now Connects to Chicken Mountain, Establishin... READ MORE
HIGHLIGHTS Fourth quarter 2025 gold production from the Pan Opera... READ MORE
Record Production and Strong Financial Performance Continue into ... READ MORE