
First Quantum Minerals Ltd. (TSX: FM) announces preliminary production for the three months and year ended December 31, 2025, and guidance for production, capital expenditure and costs for the years 2026 to 2028. Additionally, the Company provides an update on the Cobre Panamá mine and Taca Taca project.
“The Zambian operations continued to deliver strong operational performance in 2025. We accomplished another milestone for the Company, achieving commercial production of the Kansanshi S3 Expansion at the end of 2025, which represents the sixth time that First Quantum has delivered a large-scale SAG mill processing train. The project was completed under budget and continues to ramp up in line with expectations, benefiting from the in-house project development expertise that we have built over the past two decades at First Quantum. With S3 complete, First Quantum is positioned to deliver sustainable organic growth over the full three‑year guidance period,” said Tristan Pascall, Chief Executive Officer of First Quantum. “At Cobre Panamá, President José Raúl Mulino has announced that the Government of Panama will approve the removal and processing of stockpiled ore. This marks a positive step forward for ongoing responsible environmental stewardship of the mine in regards to water and tailings management. This will involve the immediate creation of 700 direct jobs and will bring benefits to Panama through royalties on a national resource that belongs to the country. The processing of stockpiles is not a reopening of the mine and we echo the President’s call for transparency and engagement. We remain committed to dialogue to achieve an amicable and durable resolution at Cobre Panamá for the country and the Panamanian people.”
Highlights
2025 Production:
Three-Year Guidance (Future and prior year production guidance figures are presented excluding Cobre Panamá):
Cobre Panamá Update: The President of Panama has indicated that the GOP will authorize the removal and processing of low-grade ore stockpiles at site. The processing of ore stockpiles will mitigate the environmental and operational risks associated with acid rock drainage and ensure the supply of feed material to the tailings management facility. The Company awaits formal approvals to carry out these activities, which will be carried out in coordination with the GOP and in strict compliance with the Preservation and Safe Management plan. The processing of stockpiles does not constitute a mine reopening.
Taca Taca Update: An updated Technical Report for Taca Taca will be released in the first quarter of 2026. The Environmental and Social Impact Assessment and water permit applications are expected to be approved in the first half of 2026. An application to Argentina Incentive Regime for Large Investments is also expected to be filed in the first half of 2026.
2025 Preliminary Production
Comparative figures will be quoted excluding Cobre Panamá unless stated otherwise.
First Quantum achieved annual copper production of 396kt for 2025, 35kt lower than 2024, but within the revised copper guidance range of 390 to 410kt. Copper production in Q4 2025 was 101kt, 4kt below Q3 2025 and 11kt below Q4 2024. Full year copper production was affected by lower grades at Sentinel partially offset by strong performance at Kansanshi, which has benefited from S3 production.
Kansanshi copper production of 181kt for the full year was 10kt higher than 2024 with 25kt of production from the S3 circuit, which produced first concentrate in August 2025. The plant delivered milling rates and operating times above 80% of design capacity, supported by an average recovery of over 80%, marking a significant milestone for the project. As a result of sustained operational stability, the S3 circuit was declared to be in commercial production as of December 1, 2025. Total copper production in Q4 2025 of 48kt was in line with the same quarter of 2024 and marginally higher than Q3 2025 with the inclusion of 19kt from the S3 circuit. Kansanshi copper production for 2025 was its highest annual copper production since 2021 and within the revised guidance range of 175 to 185kt.
Sentinel copper production of 189kt for the full year was 42kt below 2024 due to lower grades and higher maintenance, partially offset by higher throughput. Grades were lower than 2024 due to the mining of lower grades from Stage 3 compared with mining in 2024 from high-grade areas of both Stage 1 and Stage 2. Throughput was higher than 2024 with a higher proportion of weathered, softer ore from Stage 3. This was combined with sustained operational improvements along with enhanced crusher reliability and better ore fragmentation. Q4 2025 copper production of 48kt was 9kt below Q4 2024 and 3kt below Q3 2025, driven by lower grades and throughput. Sentinel production for 2025 of 189kt was 1kt below the bottom end of the revised guidance range of 190 to 200kt.
Other sites achieved consolidated copper production of 26kt for the full year, a 3kt decrease from 2024 but 1kt above the revised guidance of 25kt.
Annual gold production for 2025 of 152koz was 13koz higher than 2024 and above the top end of the revised guidance range of 140 to 150koz. This was driven by higher grades at Kansanshi, due mainly to more selective mining methods employed on higher grade veins during the first quarter and higher ore throughput and recoveries in the second quarter. Kansanshi achieved its highest annual gold production since 2021.
Nickel production for 2025 of 23.2kt was 1kt lower than 2024 which included 5kt of production from Ravensthorpe before it was placed on care and maintenance (“C&M”) in May 2024. Enterprise delivered 4kt more nickel than in 2024, marking its first full year of operations and demonstrating a strong ramp-up and operational performance. Enterprise full year nickel production of 23.2kt exceeded the top end of the revised guidance range of 18 to 23kt.
The production and sales figures provided herein are preliminary and subject to final adjustment. The final production and sales figures will be confirmed in the Company’s financial results for the fourth quarter and year ended December 31, 2025.
| 000’s | Q4 2025 |
Q4 2024 |
Year 2025 |
Year 2024 |
| Copper production (tonnes) | 101 | 112 | 396 | 431 |
| Gold production (ounces) | 37 | 39 | 152 | 139 |
| Nickel production (tonnes) | 9 | 4 | 23 | 24 |
| Copper (000’s tonnes) | Q4 2025 |
Q4 2024 |
Year 2025 |
Year 2024 |
| Kansanshi | 48 | 48 | 181 | 171 |
| Trident – Sentinel | 48 | 57 | 189 | 231 |
| Other | 4 | 7 | 26 | 29 |
| Production | 101 | 112 | 396 | 431 |
| Gold (000’s ounces) | Q4 2025 |
Q4 2024 |
Year 2025 |
Year 2024 |
| Kansanshi | 31 | 30 | 116 | 105 |
| Guelb Moghrein | 6 | 8 | 32 | 31 |
| Other | 1 | 1 | 4 | 3 |
| Production | 37 | 39 | 152 | 139 |
| Nickel production (000’s tonnes) | Q4 2025 |
Q4 2024 |
Year 2025 |
Year 2024 |
| Trident – Enterprise | 9 | 4 | 23 | 19 |
| Ravensthorpe | – | – | – | 5 |
| Production | 9 | 4 | 23 | 24 |
| Copper sales (000’s tonnes) | Q4 2025 |
Q4 2024 |
Year 2025¹ |
Year 2024 |
| Total copper | 108 | 112 | 430 | 420 |
Note: Tables may not cast due to rounding.
¹ Copper sales include 33kt from Cobre Panamá.
2026 – 2028 Guidance
Guidance is based on a number of assumptions and estimates as of December 31, 2025, including, among other things, assumptions about metal prices and anticipated costs and expenditures. Guidance involves estimates of known and unknown risks, uncertainties, and other factors, which may cause the actual results to be materially different.
Guidance for 2026 to 2028 is presented with Cobre Panamá remaining in a phase of P&SM and Ravensthorpe under C&M.
Production guidance
| 000’s | 2026 | 2027 | 2028 |
| Copper (tonnes) | 375 – 435 | 410 – 470 | 430 – 490 |
| Gold (ounces) | 175 – 200 | 185 – 205 | 190 – 210 |
| Nickel (tonnes) | 30 – 40 | 30 – 40 | 20 – 30 |
Production guidance by operation
| Copper | |||
| 000’s tonnes | 2026 | 2027 | 2028 |
| Kansanshi | 175 – 205 | 210 – 240 | 230 – 260 |
| Trident – Sentinel | 190 – 220 | 190 – 220 | 190 – 220 |
| Other sites | 10 | 10 | 10 |
| Gold | |||
| 000’s ounces | 2026 | 2027 | 2028 |
| Kansanshi | 110 – 120 | 125 – 135 | 140 – 150 |
| Guelb Moghrein | 65 – 80 | 60 – 70 | 50 – 60 |
| Nickel | |||
| 000’s tonnes | 2026 | 2027 | 2028 |
| Trident – Enterprise | 30 – 40 | 30 – 40 | 20 – 30 |
Kansanshi copper production in 2026 is marginally below previous guidance due to an increase in ore hardness with a higher proportion of fresh ore compared to feed from stockpiles. The step up in copper production over the three-year guidance period is underpinned by the ramp-up and grade profile of S3 feed. In 2026, S3 feed will be sourced evenly from low-grade stockpiles and higher-grade ore from the South East Dome deposit. From 2027 onward, the feed will primarily consist of fresher ore with higher grades from the pit. Gold production at Kansanshi has decreased from previous guidance due to lower feed grades. The step up in gold production over the guidance period is driven by an improving grade profile. The near-surface gold zone occurrences at South East Dome are not included within the Kansanshi mine plan or guidance.
Sentinel copper production guidance for 2026 and 2027 has been impacted by heavier maintenance routines. The SAG and ball mill availability have been reduced slightly following the identification of the Ball Mill 2 fatigue failures in early 2025, including bolt failures and minor structural shell cracks. Full remedial work will be scheduled for 2027 when parts become available and will involve the replacement of the Ball Mill 2 shell can section and the discharge end head. A separate assessment of the Ball Mill 1 shell can will be conducted during 2026. In addition, maintenance works at Sentinel in 2026 will include the upgrade of thickener feed wells and installation of a new tailings pipeline. These have been included in sustaining capital within capital guidance. Waste stripping volumes remain a key focus to de-risk future ore supply to achieve an optimal and sustainable balance of grades and volumes over the life-of-mine. Mining productivities including Quantum Electra-Haul™ trolley-assist technology, rail-run conveyor (“RRC”) system, and the sequencing of in-pit crusher moves continue to underpin this approach. The RRC completed field trials and entered into operational phase in January 2026 and the planned move of in-pit crusher 4 is expected to be completed in 2026.
Enterprise nickel production guidance is consistent with prior year. Nickel production over the guidance period trends in line with the feed grade profile which aims to distribute waste stripping over the life-of-mine and optimize stripping expenditures.
Guelb Moghrein gold production has been reduced in 2026 with the extension of copper production until Q1 2026 to allow for operational adaptations and adequate build-up of water stock levels. With the cessation of copper production effective as of Q2 2026, Guelb Moghrein will report as a gold-focused operation. The Carbon-in-Leach plant will be treating tailings reclaimed from Tailings Storage Facility 1 and gold-bearing stockpiled oxide material.
Cash cost and all-in sustaining cost
| Total Copper ($/lb) | 2026 | 2027 | 2028 |
| C1 | 1.95 – 2.20 | 1.85 – 2.10 | 1.85 – 2.10 |
| AISC | 3.25 – 3.55 | 3.10 – 3.40 | 3.00 – 3.30 |
| Total Nickel ($/lb) | 2026 | 2027 | 2028 |
| C1 | 3.25 – 4.25 | 3.00 – 4.00 | 3.75 – 4.75 |
| AISC | 4.25 – 5.25 | 4.25 – 5.25 | 5.25 – 6.25 |
2026 and 2027 guidance for total copper C1 and AISC reflects a change in methodology that will exclude by-product credits from Guelb Moghrein effective from the second quarter of 2026 with the expected cessation of copper production. This change in methodology increases C1 cash cost by approximately 10 cents in 2026 and 2027. Total copper C1 and AISC unit cost ranges have also been lifted with revised production guidance, higher employee and maintenance costs, and inflation more than offsetting higher gold prices. Additionally, following the gold stream agreement with Royal Gold announced in 2025, a portion of the gold production at Kansanshi is sold at a fixed gold price.
AISC cash cost guidance compared to previous guidance has increased to reflect the updated production profile combined with an increase in royalties driven by higher copper price assumptions. AISC trends downwards in outer years as production increases and sustaining capital reduces in 2028.
Unit cost guidance assumes a gold price of $4,000 per ounce, average Brent crude oil price of $70 per barrel, Zambian kwacha/United States (“US”) dollar exchange rate of 25 and royalties based on consensus copper prices. An annual compounding US dollar inflation rate of 2.5% has been incorporated into the unit cost guidance for 2027 and 2028.
Total nickel unit cost guidance relates solely to the Enterprise operation while Ravensthorpe remains under a state of C&M. Unit cost guidance has decreased as a result of a stabilized operation and better understanding of the operating cost profile. Unit cost guidance increases in 2028 are driven by a decrease in production.
Capital expenditure
| $ million | 2026 | 2027 | 2028 |
| Project capital | 410 – 460 | 150 – 180 | 100 – 130 |
| Sustaining capital | 360 – 410 | 380 – 420 | 350 – 380 |
| Capitalized stripping | 230 – 280 | 320 – 350 | 300 – 340 |
| Total capital expenditure | 1,000 – 1,150 | 850 – 950 | 750 – 850 |
Actual capital spent in 2025 was approximately $240 million lower than the original guidance for the year. 2026 capital expenditure guidance has increased from previous guidance, reflective of some capital expenditures moving from 2025 into 2026. 2026 also now includes amounts for ball mill management and a third tailings pipeline at Sentinel. In addition, the guidance period reflects higher power costs and labour rates.
Project capital in the three-year guidance period includes approximately:
Within the three-year capital expenditure guidance, approximately $600 million relates to sustainability-related project capital. Each of these projects are expected to drive improved sustainability performance as well as improve cost structure and productivity of the business.
The three-year capital expenditure guidance includes:
We remain committed to reducing the carbon intensity of our mining operations and are investing an additional $210 million in the Kansanshi mining fleet over the next three years. This investment is upgrading the existing ex-pit fleet to be fully compatible with our trolley-assist technology, Quantum Electra-Haul™. The trucks are being designed to be fuel-source agnostic, more energy efficient, and capable of higher payloads. These actions reaffirm our ongoing commitment to invest in innovative technologies that support the decarbonization of our mining operations through pit electrification.
Cobre Panamá Update
On May 30, 2025, the GOP approved and formally instructed the execution of the P&SM plan for Cobre Panamá. Activities related to the P&SM plan that occurred during the fourth quarter of 2025 included:
In the State of the Nation address on January 2, 2026, President José Raúl Mulino announced that the GOP will authorize the removal, processing and export of stockpiled ore at Cobre Panamá that was previously extracted before operations were suspended. Processing of the stockpiles will mitigate environmental and operational risks associated with their prolonged storage, such as acid rock drainage, and provide important feed material to the TMF.
The processing of stockpiles does not constitute a mine reopening and will not require any new extraction, drilling, blasting, or mine operational reactivation.
The total amount of stockpiled ore is approximately 38 million tonnes. On a preliminary basis, it is currently anticipated that processing of the stockpiles could commence in a period of approximately three months from official regulatory notice to proceed and would require approximately one year to process the stockpile. Approximately 70,000 tonnes of copper could be produced from the stockpile. Proceeds from the sale of copper concentrate are anticipated to offset P&SM costs for 2026, depending on the timing of the receipt of regulatory approval.
Processing of the mineralized rock is anticipated to result in an additional 700 new direct jobs beyond the current staffing of 1,600 jobs. It is also expected to generate further contractor hiring and broader indirect employment and economic benefits in equipment supply, transportation, logistics, food services, and other sectors.
The Company awaits formal approvals to carry out processing activities, which will be carried out in coordination with the GOP and in strict compliance with the P&SM plan.
Taca Taca Update
An updated Technical Report for Taca Taca will be released in the first quarter of 2026. The Company continues to work constructively with the Province of Salta regarding the ESIA and water permit applications, and approval is expected in the first half of 2026 after public consultation has been completed. An application to RIGI is also expected to be filed in the first half of 2026.
About First Quantum
First Quantum is engaged in the production of copper, nickel and gold, and related activities including exploration and development. The Company has operating mines located in Zambia, Türkiye and Mauritania. The Company’s Cobre Panamá mine was placed into a phase of Preservation and Safe Management in November 2023. The Company’s Ravensthorpe mine was placed into a care and maintenance process in May 2024. The Company is progressing the Taca Taca copper-gold-molybdenum project in Argentina and is exploring La Granja and the Haquira copper deposits in Peru.
REV Exploration Corp. (TSX-V: REVX) (OTC: REVFF) is pleased to an... READ MORE
Endeavour Silver Corp. (NYSE: EXK) (TSX: EDR) announces its con... READ MORE
Hudbay Minerals Inc. (TSX:HBM) (NYSE: HBM) announced preliminary ... READ MORE
Guanajuato Silver Company Ltd. (TSX-V:GSVR) (OTCQX:GSVRF), a grow... READ MORE
Capital to be Specifically Allocated to Enhancing Processing Capa... READ MORE