The Prospector News

Fiore Gold Meets Full Year 2019 Production Guidance

You have opened a direct link to the current edition PDF

Open PDF Close
Uncategorized

Share this news article

Fiore Gold Meets Full Year 2019 Production Guidance

 

 

 

 

 

FIORE GOLD LTD. (TSX-V: F) (OTCQB: FIOGF) is pleased to announce preliminary production results for the Company’s fourth fiscal quarter and the full fiscal year 2019 which ended September 30th, 2019 for its Pan open pit mine in White Pine County, Nevada.

 

Highlights:

 

  • Full-year gold production of 41,491 ounces, a 21% increase over the preceding year and within full-year guidance of 40,000-43,000 ounces. Q4 gold production was 9,282 ounces.
  • Sales of 40,886 gold ounces for the year with Q4 sales of 8,902 gold ounces.
  • Full-year mined ore production of 13,923 tons per day at a stripping ratio of 1.8. Q4 mined ore production of 13,156 tons per day at a stripping ratio of 2.3.
  • Our operations team at Pan received the Small Mine Safety Award from the Nevada Mining Association for the fourth consecutive year.
  • 91,672 man-hours worked in fiscal year 2019, achieving our goal of zero reportable incidents, zero reportable accidents, and zero lost-time injuries. Currently the operation is at 1,230 consecutive days of attaining this Triple-Zero achievement.
  • Transition from Run of Mine (“ROM”) to 100% crushed ore placement nearing completion with the commissioning of the Pan Mine primary crushing circuit.
  • A 10,000 m program of resource expansion drilling underway at the Pan Mine in support of a resource and reserve update and a new life of mine plan in mid-2020.
  • Approximately 10,000 m of drilling largely completed and metallurgical work underway at the federally permitted Gold Rock project in support of a Preliminary Economic Assessment by the end of calendar 2019.

 

Tim Warman, Fiore’s CEO commented, “Our team at the Pan Mine had another excellent year, with gold production within our guidance range and 21% higher than 2018 while continuing to maintain our high standards for safety and environmental protection. Gold production in Q4 decreased relative to Q3 in part due to placing lower grade ore as well a slower ramp-up of the crusher than we anticipated. However, tons crushed per day consistently increased through the quarter and as ore placement on the leach pad returns to planned levels, gold production is expected to likewise return to planned levels over the first quarter of FY/2020. The change from ROM to crushed ore marks the last major operational change at Pan, and the focus is now on our adjacent Gold Rock project which we intend to advance rapidly towards development and production. A PEA will be completed by year-end, and our plan is to transition directly from a positive PEA to a full Feasibility Study with the goal of arriving at a construction decision by mid-2021.”

 

FY/2019 Production

 

Quarterly and full-year production numbers for the Pan Mine are shown in the table below:

 

 

  Q1 Q2 Q3 Q4 FY/2019
Gold Production (oz) 9,765 10,759 11,685 9,282 41,491
Ore Tons Mined (tpd) 15,196 13,211 14,114 13,156 13,923
Gold Grade (oz per ton) 0.016 0.015 0.014 0.013 0.015
Total Tons Mined (tpd) 37,792 34,782 38,275 43,005 38,484

 

Gold production of 41,491 ounces fell comfortably within our full year production guidance of 40,000 to 43,000 ounces. Pan mined 13,923 ore tons per day, also in line with our 14,000 ore tons per day guided target. Total tons mined of 38,484 tons per day reflects a strip ratio of 1.8 which as expected was higher than the 1.6 life of mine average strip. Importantly, the total tons mined per day trended upward through 2019 with Q4 of 43,005 total tons mined per day. This is a positive reflection of improved productivity from a mining perspective.

 

Q4 gold production was impacted by lower gold grades in the second half of the year in line with the mine plan. Additionally, Q4 ore mining rates and placement of crushed ore on the leach pad were lower than planned as we worked to achieve consistent crusher availability and throughput. Tons crushed per day consistently increased through the quarter. As ore placement on the leach pad returns to planned levels, gold production is expected to likewise return to planned levels over the first quarter of FY/2020. With 2019 production finishing 21% over 2018, we will look to build on the positive momentum heading into 2020 when we expect to see increased gold recoveries and production with a full year of placing predominantly crushed ore on the leach pad.

 

A new drilling program aimed at increasing the resource and reserve base and extending the mine life at Pan commenced in September 2019. The program will consist of approximately 10,000 m of reverse circulation drilling and may also include some diamond core holes. Once the drilling is complete, a new resource estimate will be carried out by our independent geological consultants and a new life of mine plan will be prepared by mid-2020.

 

At Gold Rock, work on the PEA continues to progress well with approximately 10,000 m of RC drilling now complete and a further 1,800 m of core drilling expected to wrap up by the end of October. Results for 17 of the 32 RC holes have been released to date, with the remaining holes in process at the assay lab. Drilling has encountered thick intervals of oxide gold mineralization both within and outside of the current resource pit shells and has shown that mineralization continues through a lightly drilled gap in the current resource.

 

The drilling program, resource update and ongoing metallurgical testing is part of a detailed development plan for Gold Rock that lays out the activities and schedule required to advance the project towards production. The plan aims to arrive at a construction decision by mid-2021, assuming successful completion of these activities and a positive feasibility study. Based on its experience operating the nearby Pan Mine, the Company intends to proceed directly from the PEA to a Feasibility Study in order to shorten the development timeframe.

 

The Gold Rock development plan will look to leverage the infrastructure and workforce at the adjacent Pan Mine to the greatest extent possible, in particular the existing Pan power line and the access road from Highway 50. We are also evaluating opportunities to reduce capital, operating expenses and environmental impacts by using the Pan ADR plant and assay lab.

 

Technical Disclosure

 

The scientific and technical information relating to Fiore Gold’s properties contained in this news release was approved by J. Ross MacLean (MMSA), Fiore Gold’s Chief Operating Officer and a “Qualified Person” under National Instrument 43-101.

 

Corporate Strategy

 

Our corporate strategy is to grow Fiore Gold into a 150,000 ounce per year gold producer. To achieve this, we intend to:

 

  • continue to grow gold production at the Pan Mine, while increasing the resource and reserve base
  • advance the development of the nearby Gold Rock project
  • acquire additional production or near-production assets to complement our existing operations

 

Posted October 17, 2019

Share this news article

MORE or "UNCATEGORIZED"


PPX Mining Announces Closing Of $1.35 Million Private Placement

PPX Mining Corp. is pleased to announce that it has closed its fu... READ MORE

April 19, 2024

Elevation Gold Reports Financial Results for Year Ended December 31, 2023, including $66.4M in Total Revenue

Elevation Gold Mining Corporation (TSX-V: ELVT) (OTCQB: EVGDF) i... READ MORE

April 18, 2024

Reunion Gold Announces the Signing of a Mineral Agreement With the Government of Guyana for Its Oko West Project

Reunion Gold Corporation (TSX-V: RGD; OTCQX: RGDFF) is pleased to announ... READ MORE

April 18, 2024

Drilling Confirms 4 km of Favourable Corridor at Lynx Gold Trend

Puma Exploration Inc. (TSX-V: PUMA) (OTCQB: PUMXF) is thrilled to... READ MORE

April 18, 2024

Grid Metals Intersects 7 m at 1.28% Li2O at over 125 m Below the Previously Deepest Drill Holes at Donner Lake; Provides Project Update

Grid Metals Corp. (TSX-V:GRDM) (OTCQB:MSMGF) is pleased to announ... READ MORE

April 18, 2024

Copyright 2024 The Prospector News