Ero Copper Corp. (TSX: ERO) (NYSE: ERO) is pleased to announce its operating and financial results for the three and six months ended June 30, 2022. Management will host a conference call tomorrow, Wednesday, August 3, 2022, at 11:30 a.m. Eastern time to discuss the results. Dial-in details for the call can be found near the end of this press release.
HIGHLIGHTS
“Our second quarter delivered record operational performance across our assets and saw the successful execution of important milestones critical to our growth strategy,” said David Strang, Chief Executive Officer. “Underpinning our record quarterly production results were new monthly records set for production rates, development rates, asset efficiency and availability, among others. Following a challenging first quarter operating environment, I want to congratulate our on-site teams for setting new high watermarks that showcase the capabilities of our assets and people.
“Across our key growth projects, construction and development activities are progressing on schedule and well within contingency levels at this time. Our team’s adherence to the original capital expenditure estimates for major equipment line items and work packages that have been secured on these projects to date is remarkable given the significant inflationary headwinds that the mining industry has faced since the beginning of 2022.
“Despite our record operating performance and outstanding project execution during the quarter, our financial results were impacted by operational challenges at our primary domestic smelting customer, which resulted in changes to our copper concentrate sales channels that are expected to continue through the balance of the year.”
“Primarily as a result of higher allocation of sales to international customers and elevated input costs in the first half of the year across our business units, we have adjusted our full- year operating cost guidance ranges. Offsetting these increases, proactive capital management reviews with our team during the quarter identified over $20 million of capital deferrals that will not impact our business strategy yet will support continued balance sheet strength during this period of elevated market and copper price volatility.”
*These are non-IFRS measures and do not have a standardized meaning prescribed by IFRS and might not be comparable to similar financial measures disclosed by other issuers. Please refer to the Company’s discussion of Non-IFRS measures in its Management’s Discussion and Analysis for the three and six months ended June 30, 2022 and the Reconciliation of Non- GAAP Measures section at the end of this press release.
SECOND QUARTER REVIEW
OPERATING AND FINANCIAL HIGHLIGHTS
3 months ended | 3 months ended | 3 months ended | 6 months ended | 6 months ended | |||||||||||||
June 30, 2022 | Mar. 31, 2022 | June 30, 2021 | June 30, 2022 | June 30, 2021 | |||||||||||||
Operating Highlights |
|||||||||||||||||
Copper (Caraíba Operations) | |||||||||||||||||
Ore Processed (tonnes) | 801,425 | 596,230 | 553,992 | 1,397,655 | 1,151,586 | ||||||||||||
Grade (% Cu) | 1.74 | 1.78 | 2.13 | 1.76 | 2.22 | ||||||||||||
Cu Production (tonnes) | 12,734 | 9,784 | 10,898 | 22,518 | 23,536 | ||||||||||||
Cu Production (000 lbs) | 28,073 | 21,570 | 24,026 | 49,643 | 51,889 | ||||||||||||
Cu Sold in Concentrate (tonnes) | 12,948 | 10,045 | 10,094 | 22,993 | 22,562 | ||||||||||||
Cu Sold in Concentrate (000 lbs) | 28,546 | 22,145 | 22,253 | 50,691 | 22,253 | ||||||||||||
C1 cash cost of Cu produced (per lb)(1) | $ | 1.24 | $ | 1.31 | $ | 0.72 | $ | 0.63 | $ | 0.49 | |||||||
Gold (Xavantina Operations) |
|||||||||||||||||
Au Production (oz) | 11,122 | 8,796 | 10,377 | 19,918 | 19,828 | ||||||||||||
C1 cash cost of Au Produced (per oz)(1) | $ | 643 | $ | 638 | $ | 499 | $ | 641 | $ | 494 | |||||||
AISC of Au produced (per oz)(1) | $ | 1,169 | $ | 1,092 | $ | 660 | $ | 1,135 | $ | 652 | |||||||
Financial Highlights ($ in millions, except per share amounts) |
|||||||||||||||||
Revenues | $ | 114.9 | $ | 108.9 | $ | 120.7 | $ | 223.8 | $ | 243.2 | |||||||
Gross profit | 50.7 | 61.0 | 83.7 | 111.7 | 166.5 | ||||||||||||
EBITDA(1) | 53.9 | 78.1 | 112.0 | 132.0 | 167.2 | ||||||||||||
Adjusted EBITDA(1) | 55.8 | 62.4 | 85.5 | 118.2 | 172.2 | ||||||||||||
Cash flow from operations | 22.4 | 44.0 | 85.1 | 66.4 | 147.2 | ||||||||||||
Net income | 24.1 | 52.5 | 84.0 | 76.6 | 116.0 | ||||||||||||
Net income attributable to owners of the Company | 23.8 | 52.1 | 83.4 | 75.9 | 115.2 | ||||||||||||
Per share (basic) | 0.26 | 0.58 | 0.95 | 0.84 | 1.31 | ||||||||||||
Per share (diluted) | 0.26 | 0.57 | 0.89 | 0.83 | 1.24 | ||||||||||||
Adjusted net income attributable to owners of the Company(1) |
24.4 |
33.0 |
53.5 |
57.3 |
109.8 |
||||||||||||
Per share (basic) | 0.27 | 0.37 | 0.61 | 0.63 | 1.25 | ||||||||||||
Per share (diluted) | 0.27 | 0.36 | 0.57 | 0.62 | 1.18 | ||||||||||||
Cash, cash equivalents, and short-term investments | 429.9 | 365.5 | 137.7 | 429.9 | 137.7 | ||||||||||||
Working capital(1) | 417.7 | 443.7 | 118.9 | 417.7 | 118.9 | ||||||||||||
Net (cash) debt(1) | (10.2 | ) | (54.4 | ) | 19.2 | (10.2 | ) | 19.2 |
(1) EBITDA, Adjusted EBITDA, Adjusted net income (loss) attributable to owners of the Company, Adjusted net income (loss) per share attributable to owners of the Company, Net (Cash) Debt, Working Capital, C1 cash cost of copper produced (per lb), C1 cash cost of gold produced (per ounce) and AISC of gold produced (per ounce) are non-IFRS measures. These measures do not have a standardized meaning prescribed by IFRS and might not be comparable to similar financial measures disclosed by other issuers. Please refer to the Company’s discussion of Non-IFRS measures in its Management’s Discussion and Analysis for the three and six months ended June 30, 2022 and the Reconciliation of Non-GAAP Measures section at the end of this press release.
2022 GUIDANCE(*)
The Company is reaffirming its full-year production guidance, lowering consolidated 2022 capital expenditure guidance, and raising operating cost guidance for the year.
At its Caraíba Operations, the Company continues to guide to the high-end of its reaffirmed 2022 copper production guidance range of 43,000 to 46,000 tonnes. As previously noted, copper production is expected to be roughly equally weighted between the first and second halves of the year with mining of the initial Project Honeypot stope (RC03) at the Pilar Mine expected to support a continuation of strong mined and processed copper grades into Q3 2022. At the Xavantina Operations, higher gold grades are expected to drive modestly higher gold production during the second half of the year.
The Company is lowering its consolidated 2022 capital expenditure guidance by over $20 million, from $330-$375 million to $308-$354 million, as a result of capital replanning efforts and deferrals at the Caraíba Operations. The deferral of this capital spend is not expected to impact timelines of the Company’s key growth projects.
The Company is raising its full-year operating cost guidance ranges due to the impact of inflation in the cost of key consumables and a stronger BRL versus the US dollar during H1 2022 as well as an expected continuation of elevated copper concentrate sales to international markets in H2 2022. The Company’s revised 2022 copper C1 cash cost guidance range is $1.20 to $1.35 (originally $1.05 to $1.15) per pound of copper produced. The Company is also increasing its 2022 gold C1 cash costs and AISC guidance ranges to
$600 to $700 (previously $500 to $600) and $1,000 to $1,100 (previously $925 to $1,025), respectively, per ounce of gold produced for its Xavantina Operations.
2022 PRODUCTION AND COST GUIDANCE(*)
The Company’s cost guidance for 2022 assumes a USD:BRL foreign exchange rate of 5.30, a gold price of $1,725 per ounce and a silver price of $20.00 per ounce for H2 2022.
Original | Revised | |
Caraíba Operations | ||
Copper Production (tonnes) | 43,000 – 46,000 | Unchanged |
C1 Cash Cost Guidance (US$/lb)(1) | $1.05 – $1.15 | $1.20 – $1.35 |
Xavantina Operations | ||
Gold Production (ounces) | 39,000 – 42,000 | Unchanged |
C1 Cash Cost Guidance (US$/oz)(1) | $500 – $600 | $600 – $700 |
All-in Sustaining Cost (AISC) Guidance (US$/oz)(1) | $925 – $1,025 | $1,000 – $1,100 |
(1) These are non-IFRS measures and do not have a standardized meaning prescribed by IFRS and might not be comparable to similar financial measures disclosed by other issuers.
2022 CAPITAL EXPENDITURE GUIDANCE(*)
The Company’s capital expenditure guidance for 2022 assumes a USD:BRL foreign exchange rate of 5.30 for H2 2022 and has been presented below in USD millions.
Original | Revised | |
Caraíba Operations | ||
Growth | $125 – $140 | $95 – $110 |
Sustaining | $80 – $90 | $85 – $95 |
Exploration | $25 – $30 | Unchanged |
Total, Caraíba Operations | $230 – $260 | $180 – $205 |
Tucumã Project | ||
Growth | $70 – $80 | Unchanged |
Exploration | $5 – $6 | Unchanged |
Total, Tucumã Project | $75 – $86 | Unchanged |
Xavantina Operations | ||
Growth | $0 – $1 | $2 – $4 |
Sustaining | $16 – $18 | Unchanged |
Exploration | $9 – $10 | $10 – $11 |
Total, Xavantina Operations | $25 – $29 | $28 – $33 |
Company Total | ||
Growth | $195 – $221 | $167 – $194 |
Sustaining | $96 – $108 | $101 – $113 |
Exploration | $39 – $46 | $40 – $47 |
Total, Company | $330 – $375 | $308 – $354 |
(*) Guidance is based on certain estimates and assumptions, including but not limited to, mineral reserve estimates, grade and continuity of interpreted geological formations and metallurgical performance. Please refer to the Company’s SEDAR and EDGAR filings, including the Company’s most recent Annual Information Form (“AIF”), for complete risk factors.
Reconciliation of Non-IFRS Measures
The Company utilizes certain alternative performance (non-IFRS) measures to monitor its performance, including C1 cash cost of copper produced (per lb), C1 cash cost of gold produced (per ounce), AISC of gold produced (per ounce), EBITDA, adjusted EBITDA, adjusted net income attributable to owners of the Company, adjusted net income per share, net (cash) debt, working capital and available liquidity. These performance measures have no standardized meaning prescribed within generally accepted accounting principles under IFRS and, therefore, amounts presented may not be comparable to similar measures presented by other mining companies. These non-IFRS measures are intended to provide supplemental information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS.
For additional details please refer to the Company’s discussion of non-GAAP and other performance measures in its Management’s Discussion and Analysis for the three and six months ended June 30, 2022 which is available on SEDAR at www.sedar.com and on EDGAR at www.sec.gov.
C1 cash cost of copper produced (per lb.)
The following table provides a reconciliation of C1 cash cost of copper produced per pound to cost of production, its most directly comparable IFRS measure.
Reconciliation: | 2022 – Q2 | 2022 – Q1 | 2021 – Q2 | 2022 – YTD | 2021 – YTD | ||||||||||||||
Cost of production | $ | 38,015 | $ | 29,163 | $ | 20,464 | $ | 67,178 | $ | 42,266 | |||||||||
Add (less): | |||||||||||||||||||
Transportation costs & other | 2,579 | (904 | ) | (569 | ) | (1,920 | ) | (1,382 | ) | ||||||||||
Treatment, refining, and other | 3,893 | 577 | 701 | (1,330 | ) | (1,967 | ) | ||||||||||||
By-product credits | (6,438 | ) | 1,869 | 1,516 | 4,448 | 2,491 | |||||||||||||
Incentive payments | (1,016 | ) | (4,812 | ) | (5,522 | ) | (11,250 | ) | (11,722 | ) | |||||||||
Net change in inventory | (1,907 | ) | 2,046 | 392 | 5,939 | 1,171 | |||||||||||||
Foreign exchange translation and other | (178 | ) | 386 | 352 | 208 | 199 | |||||||||||||
C1 cash costs | $ | 34,948 | $ | 28,325 | $ | 17,334 | $ | 63,273 | $ | 31,056 | |||||||||
Mining | $ | 23,933 | $ | 20,126 | $ | 13,732 | $ | 44,059 | $ | 11,869 | |||||||||
Processing | 7,988 | 6,447 | 5,132 | 14,435 | 4,010 | ||||||||||||||
Indirect | 5,572 | 4,518 | 3,600 | 10,090 | 3,264 | ||||||||||||||
Production costs | 37,493 | 31,091 | 22,464 | 68,584 | 19,143 | ||||||||||||||
By-product credits | (6,438 | ) | (4,812 | ) | (5,522 | ) | (11,250 | ) | (6,200 | ) | |||||||||
Treatment, refining and other | 3,893 | 2,046 | 392 | 5,939 | 779 | ||||||||||||||
C1 cash costs | $ | 34,948 | $ | 28,325 | $ | 17,334 | $ | 63,273 | $ | 13,722 | |||||||||
Payable copper produced (lb, 000) | 28,073 | 21,570 | 24,026 | 49,643 | 51,889 | ||||||||||||||
Mining | $ | 0.85 | $ | 0.93 | $ | 0.57 | $ | 0.89 | $ | 0.43 | |||||||||
Processing | $ | 0.28 | $ | 0.30 | $ | 0.21 | $ | 0.29 | $ | 0.14 | |||||||||
Indirect | $ | 0.20 | $ | 0.21 | $ | 0.15 | $ | 0.20 | $ | 0.12 | |||||||||
By-product credits | $ | (0.23 | ) | $ | (0.22 | ) | $ | (0.23 | ) | $ | (0.23 | ) | $ | (0.22 | ) | ||||
Treatment, refining and other | $ | 0.14 | $ | 0.09 | $ | 0.02 | $ | 0.12 | $ | 0.03 | |||||||||
C1 cash costs of copper produced (per lb) | $ | 1.24 | $ | 1.31 | $ | 0.72 | $ | 1.27 | $ | 0.49 |
C1 cash cost of gold produced and All-in Sustaining Cost of gold produced (per ounce)
The following table provides a reconciliation of C1 cash cost of gold produced per ounce and AISC of gold produced per ounce to cost of production, its most directly comparable IFRS measure.
Reconciliation: | 2022 – Q2 | 2022 – Q1 | 2021 – Q2 | 2022 – YTD | 2021 – YTD | ||||||||||||||
Cost of production | $ | 7,225 | $ | 5,392 | $ | 5,080 | $ | 12,617 | $ | 10,164 | |||||||||
Add (less): | |||||||||||||||||||
Incentive payments | (188 | ) | (585 | ) | (210 | ) | (773 | ) | (493 | ) | |||||||||
Net change in inventory | (73 | ) | 727 | 292 | 654 | 165 | |||||||||||||
By-product credits | (145 | ) | (124 | ) | (157 | ) | (269 | ) | (305 | ) | |||||||||
Foreign exchange translation and other | 327 | 206 | 176 | 533 | 257 | ||||||||||||||
C1 cash costs | $ | 7,146 | $ | 5,616 | $ | 5,181 | $ | 12,762 | $ | 9,788 | |||||||||
Site general and administrative | 882 | 559 | 369 | 1,441 | 676 | ||||||||||||||
Accretion of mine closure and rehabilitation provision | 112 | 112 | (63 | ) | 224 | (112 | ) | ||||||||||||
Sustaining capital expenditure | 3,690 | 2,296 | 527 | 5,986 | 1,012 | ||||||||||||||
Sustaining leases | 894 | 822 | 565 | 1,716 | 1,027 | ||||||||||||||
Royalties and production taxes | 277 | 204 | 271 | 481 | 540 | ||||||||||||||
AISC | $ | 13,001 | $ | 9,609 | $ | 6,850 | $ | 22,610 | $ | 12,931 | |||||||||
2022 – Q2 | 2022 – Q1 | 2021 – Q2 | 2022 – YTD | 2021 – YTD | |||||||||||||||
Costs | |||||||||||||||||||
Mining | $ | 3,929 | $ | 3,218 | $ | 2,481 | $ | 7,147 | $ | 4,744 | |||||||||
Processing | 2,285 | 1,698 | 1,937 | 3,983 | 3,617 | ||||||||||||||
Indirect | 1,077 | 824 | 920 | 1,901 | 1,732 | ||||||||||||||
Production costs | 7,291 | 5,740 | 5,338 | 13,031 | 10,093 | ||||||||||||||
By-product credits | (145 | ) | (124 | ) | (157 | ) | (269 | ) | (305 | ) | |||||||||
C1 cash costs | $ | 7,146 | $ | 5,616 | $ | 5,181 | $ | 12,762 | $ | 9,788 | |||||||||
Site general and administrative | 882 | 559 | 369 | 1,441 | 676 | ||||||||||||||
Accretion of mine closure and rehabilitation provision | 112 | 112 | (63 | ) | 224 | (112 | ) | ||||||||||||
Sustaining capital expenditure | 3,690 | 2,296 | 527 | 5,986 | 1,012 | ||||||||||||||
Sustaining leases | 894 | 822 | 565 | 1,716 | 1,027 | ||||||||||||||
Royalties and production taxes | 277 | 204 | 271 | 481 | 540 | ||||||||||||||
AISC | $ | 13,001 | $ | 9,609 | $ | 6,850 | $ | 22,610 | $ | 12,931 | |||||||||
Costs per ounce | |||||||||||||||||||
Payable gold produced (ounces) | 11,122 | 8,796 | 10,377 | 19,918 | 19,828 | ||||||||||||||
Mining | $ | 353 | $ | 366 | $ | 239 | $ | 359 | $ | 239 | |||||||||
Processing | $ | 205 | $ | 193 | $ | 187 | $ | 200 | $ | 182 | |||||||||
Indirect | $ | 97 | $ | 94 | $ | 89 | $ | 95 | $ | 87 | |||||||||
By-product credits | $ | (12 | ) | $ | (15 | ) | $ | (15 | ) | $ | (13 | ) | $ | (14 | ) | ||||
C1 cash costs of gold produced (per ounce) | $ | 643 | $ | 638 | $ | 499 | $ | 641 | $ | 494 | |||||||||
AISC of gold produced (per ounce) | $ | 1,169 | $ | 1,092 | $ | 660 | $ | 1,135 | $ | 652 |
Earnings before interest, taxes, depreciation and amortization (EBITDA) and Adjusted EBITDA
The following table provides a reconciliation of EBITDA and Adjusted EBITDA to net income, its most directly comparable IFRS measure.
Reconciliation: | 2022 – Q2 | 2022 – Q1 | 2021 – Q2 | 2022 – YTD | 2021 – YTD | ||||||||||||||
Net Income | $ | 24,110 | $ | 52,486 | $ | 83,979 | $ | 76,596 | $ | 116,036 | |||||||||
Adjustments: | |||||||||||||||||||
Finance expense | 8,154 | 5,496 | 2,306 | 13,650 | 6,076 | ||||||||||||||
Income tax expense | 5,283 | 8,606 | 15,862 | 13,889 | 23,691 | ||||||||||||||
Amortization and depreciation | 16,360 | 11,504 | 9,871 | 27,865 | 21,382 | ||||||||||||||
EBITDA | $ | 53,907 | $ | 78,092 | $ | 112,018 | $ | 132,000 | $ | 167,185 | |||||||||
Foreign exchange loss (gain) | 3,303 | (18,709 | ) | (30,718 | ) | (15,406 | ) | (2,093 | ) | ||||||||||
Share based compensation | (2,333 | ) | 1,990 | 2,480 | (343 | ) | 4,826 | ||||||||||||
Incremental COVID-19 costs | 952 | 1,004 | 1,749 | 1,956 | 2,305 | ||||||||||||||
Adjusted EBITDA | $ | 55,829 | $ | 62,377 | $ | 85,529 | $ | 118,207 | $ | 172,223 |
Adjusted net income attributable to owners of the Company and Adjusted net income per share attributable to owners of the Company
The following table provides a reconciliation of Adjusted net income attributable to owners of the Company and Adjusted EPS to net income attributable to the owners of the Company, its most directly comparable IFRS measure.
Reconciliation: | 2022 – Q2 | 2022 – Q1 | 2021 – Q2 | 2022 – YTD | 2021 – YTD | ||||||||||||||
Net income as reported attributable to the owners of the | |||||||||||||||||||
Company | $ | 23,820 | $ | 52,107 | $ | 83,419 | $ | 75,927 | $ | 115,168 | |||||||||
Adjustments: | |||||||||||||||||||
Share based compensation | (2,333 | ) | 1,990 | 2,480 | (343 | ) | 4,826 | ||||||||||||
Unrealized foreign exchange loss (gain) on USD | |||||||||||||||||||
denominated balances in MCSA | 1,038 | (1,337 | ) | (8,712 | ) | (299 | ) | (912 | ) | ||||||||||
Unrealized foreign exchange loss (gain) on foreign exchange derivative contracts | 1,405 | (24,615 | ) | (29,799 | ) | (23,210 | ) | (12,928 | ) | ||||||||||
Incremental COVID-19 costs | 946 | 998 | 1,735 | 1,944 | 2,291 | ||||||||||||||
Unrealized (gain) loss on interest rate derivative | |||||||||||||||||||
contracts | — | — | 6 | — | (409 | ) | |||||||||||||
Tax effect on the above adjustments | (519 | ) | 3,808 | 4,344 | 3,289 | 1,771 | |||||||||||||
Adjusted net income attributable to owners of the Company | $ | 24,357 | $ | 32,951 | $ | 53,473 | $ | 57,308 | $ | 109,807 | |||||||||
Weighted average number of common shares | |||||||||||||||||||
Basic | 90,539,647 | 90,238,008 | 88,251,995 | 90,389,661 | 88,158,672 | ||||||||||||||
Diluted | 91,850,321 | 92,050,104 | 93,314,274 | 91,887,665 | 93,106,210 | ||||||||||||||
Adjusted EPS | |||||||||||||||||||
Basic | $ | 0.27 | $ | 0.37 | $ | 0.61 | $ | 0.63 | $ | 1.25 | |||||||||
Diluted | $ | 0.27 | $ | 0.36 | $ | 0.57 | $ | 0.62 | $ | 1.18 |
Net (Cash) Debt
The following table provides a calculation of net (cash) debt based on amounts presented in the Company’s condensed consolidated interim financial statements as at the periods presented.
June 30, 2022 | March 31, 2022 | December 31, 2021 | June 30, 2021 | ||||||||||||
Current portion of loans and borrowings | $ | 16,219 | $ | 8,740 | $ | 4,344 | $ | 4,461 | |||||||
Long-term portion of loans and borrowings | 403,492 | 402,345 | 54,906 | 152,404 | |||||||||||
Less: | |||||||||||||||
Cash and cash equivalents | (329,292 | ) | (365,465 | ) | (130,129 | ) | (137,655 | ) | |||||||
Short-term investments | (100,589 | ) | (100,018 | ) | — | (26,408 | ) | ||||||||
Net (cash) debt | $ | (10,170 | ) | $ | (54,398 | ) | $ | (70,879 | ) | $ | (7,198 | ) |
Working capital and Available liquidity
The following table provides a calculation for these based on amounts presented in the Company’s condensed consolidated interim financial statements as at the periods presented.
June 30, 2022 | March 31, 2022 | December 31, 2021 | June 30, 2021 | ||||||||||||
Current assets | $ | 523,201 | $ | 546,439 | $ | 208,686 | $ | 202,342 | |||||||
Less: Current liabilities | (105,527 | ) | (102,743 | ) | (122,660 | ) | (83,453 | ) | |||||||
Working capital | $ | 417,674 | $ | 443,696 | $ | 86,026 | $ | 118,889 | |||||||
Cash and cash equivalents | 329,292 | 365,465 | 130,129 | 137,655 | |||||||||||
Short-term investments | 100,589 | 100,018 | 26,408 | — | |||||||||||
Available undrawn revolving credit | |||||||||||||||
facilities | 75,000 | 75,000 | 100,000 | — | |||||||||||
Available liquidity | $ | 504,881 | $ | 540,483 | $ | 256,537 | $ | 137,655 |
ABOUT ERO COPPER CORP
Ero is a high-margin, high-growth, clean copper producer with operations in Brazil and corporate headquarters in Vancouver, B.C. The Company’s primary asset is a 99.6% interest in the Brazilian copper mining company, Mineração Caraíba S.A. 100% owner of the Company’s Caraíba Operations (formerly known as the MCSA Mining Complex), which are located in the Curaçá Valley, Bahia State, Brazil and include the Pilar and Vermelhos underground mines and the Surubim open pit mine, and the Tucumã Project (formerly known as Boa Esperança), an IOCG-type copper project located in Pará, Brazil. The Company also owns 97.6% of NX Gold S.A. (“NX Gold”) which owns the Xavantina Operations (formerly known as the NX Gold Mine), comprised of an operating gold and silver mine located in Mato Grosso, Brazil. Additional information on the Company and its operations, including technical reports on the Caraíba Operations, Xavantina Operations and Tucumã Project, can be found on the Company’s website (www.erocopper.com), on SEDAR (www.sedar.com), and on EDGAR (www.sec.gov).
Commerce Resources Corp. (TSX-V: CCE) (FSE: D7H0) is pleased to... READ MORE
North Bay Resources, Inc. (OTC: NBRI) is pleased to announce a re... READ MORE
NevGold Corp. (TSX-V:NAU) (OTCQX:NAUFF) (Frankfurt:5E50) is pleas... READ MORE
G2 Goldfields Inc. (TSX: GTWO) (OTCQX: GUYGF) is pleased to annou... READ MORE
Aya Gold & Silver Inc. (TSX: AYA) (OTCQX: AYASF) announced fi... READ MORE