enCore Energy Corp. (NASDAQ: EU) (TSXV: EU) a uranium producer and America’s Clean Energy Company™, provided an update on the production ramp up at its South Texas Alta Mesa In-Situ Recovery Uranium Central Processing Plant and Wellfield. The Company has achieved an important milestone in the expansion of production and is now nearing flow capacity at the first of Alta Mesa CPP’s three ion exchange circuits. The three IX circuits can provide dissolved uranium in groundwater to the Alta Mesa CPP from multiple wellfields simultaneously.
Significant operational highlights include:
Paul Goranson, the Company’s Chief Executive Officer said, “We have been very pleased with the results from the first phase at Alta Mesa and production from the initial startup. As we expand Wellfield 7, we expect continued success which will build up flow rates to support all three of the IX circuits at the Alta Mesa CPP. We continue to work towards reaching full capacity through 2025 with plans to be fully operational at all three of our IX circuits.”
Alta Mesa In-Situ Recovery Uranium Central Processing Plant & Wellfield
The Alta Mesa CPP and Wellfield hosts a fully licensed and constructed ISR uranium plant, located on 200,000+ acres of private land in the state of Texas. Alta Mesa is enCore’s second producing location and operates under a 70/30 joint venture between enCore Energy Corp. and Boss Energy Limited (ASX:BOE) (OTCQX:BQSSF) with enCore Energy as the managing operator.
Total operating capacity at the Alta Mesa CPP is currently 1.5 million lbs. U3O8 per year with an additional drying and packaging capacity of more than 0.5 million lbs. U3O8. The Alta Mesa CPP historically produced nearly 5 million lbs. U3O8 between 2005 and 2013, when full production was curtailed as a result of low uranium prices.
Alta Mesa CPP and Wellfield highlights:
Alta Mesa & Mesteña Grande Mineral Resource Summary (0.30 GT cutoff)1,2 |
Tons | Avg. Grade
(% U3O8) |
Pounds |
Total Measured Mineral Resource1 | 54,000 | 0.152 | 164,000 |
Alta Mesa Indicated Mineral Resource | 1,397,000 | 0.106 | 2,959,000 |
Mesteña Grande Indicated Mineral Resource | 119,000 | 0.120 | 287,000 |
Total Measured & Indicated Resources | 1,570,000 | 0.109 | 3,410,000 |
Alta Mesa Inferred Mineral Resource | 1,263,000 | 0.126 | 3,192,000 |
Mesteña Grande Inferred Mineral Resource | 5,733,000 | 0.119 | 13,601,000 |
Total Inferred Resources | 6,996,000 | 0.120 | 16,793,000 |
1,2 Represents that portion of the in-place mineral resource that are estimated to be recoverable within existing wellfields. Wellfield recovery factors have not been applied to indicated and inferred mineral resources. As reported in the NI-43-101 Technical Report Summary for the Alta Mesa Uranium Project, Brooks and Jim Hogg Counties, Texas, USA completed by Doug Beahm, PE, PG, of BRS Engineering. (Effective January 19, 2023). |
John M. Seeley, Ph.D., P.G., C.P.G., enCore’s Manager of Geology and Exploration, and a Qualified Person under NI 43-101, has reviewed and approved the technical disclosure in this news release on behalf of the Company.
About enCore Energy Corp.
enCore Energy Corp., America’s Clean Energy Company™, is committed to providing clean, reliable, and affordable fuel for nuclear energy as the only United States uranium producer with multiple production facilities in operation. The enCore team is led by industry experts with extensive knowledge and experience in all aspects of In-Situ Recovery (“ISR”) uranium operations and the nuclear fuel cycle. enCore solely utilizes ISR for uranium extraction, a well-known and proven technology co-developed by the leaders at enCore Energy.
Following upon enCore’s demonstrated production success in South Texas, future projects in the production pipeline include the Dewey-Burdock project in South Dakota and the Gas Hills project in Wyoming. The Company holds other assets including significant New Mexico resources, non-core assets and proprietary databases. enCore is committed to working with local communities and indigenous governments to create positive impact from corporate developments.
enCore Energy’s Alta Mesa Plant (CNW Group/enCore Energy Corp.)
enCore Energy CPP Process (IX Circuits operate within Resin Reloading) (CNW Group/enCore Energy Corp.)
First Phosphate Corp. (CSE: PHOS) (OTCQB: FRSPF) (FSE: KD0) is pl... READ MORE
Further to its news release of December 18, 2024, Canadian Gold R... READ MORE
West Red Lake Gold Mines Ltd. (TSX-V: WRLG) (OTCQB: WRLGF) is ple... READ MORE
i-80 GOLD CORP. (TSX: IAU) (NYSE American: IAUX) announces that p... READ MORE
Orion Mine Finance announced today that OMF Fund IV SPV G LLC, a ... READ MORE