Construction Decision Approved: El Tigre First Gold-Silver Pour Targeted for December 2027

You have opened a direct link to the current edition PDF

Open PDF Close
Uncategorized

Share this news article

Construction Decision Approved: El Tigre First Gold-Silver Pour Targeted for December 2027

 

 

 

 

We are pleased to share an exclusive video update featuring Glenn Jessome, President & CEO, discussing our major milestone at the El Tigre Project.In this interview, Glenn outlines the Board’s recent construction decision for the El Tigre surface mine in Sonora, Mexico. Key highlights include:
– Award of the Engineering, Procurement and Construction Management (EPCM) contract to Kappes, Cassidy & Associates (KCA)

– Commissioning and first gold-silver pour targeted for December 2027

– Strong progress on engineering, site clearing, infrastructure, and road improvements

– Over US$86 million in cash to fund immediate development activities
Upcoming exploration drilling at the historic North Tigre Mine area

This marks a significant de-risking step as we transition El Tigre into the construction phase.

 

Courtesy of Silver Tiger Metals via KE Report

 

Posted March 25, 2026

Share this news article

MORE or "UNCATEGORIZED"


Santacruz Reports Q1 2026 Production of 1,341,499 Ounces of Silver and 21,640 Tonnes of Zinc, with Continued Recovery of Production at Bolivar Mine

Santacruz Silver Mining Ltd. (NASDAQ:SCZM) (TSX-V:SCZ) announces that total production in the first ... READ MORE

April 17, 2026

Greenland Government Approves Transfer of Final 50.5% of Tanbreez, Taking Critical Metals Corp. to 92.5% Ownership

Critical Metals Corp. (Nasdaq: CRML), a leading critical mineral mining company, today announced tha... READ MORE

April 17, 2026

NMG Announces Closing of US$96.5 Million Equity Public Offering

As part of the financing package for the phased development of the commercial operations of its Mata... READ MORE

April 16, 2026

Group Eleven Drills 23.5m of 12.3% Zn+Pb and 46 g/t Ag, Further Confirms Deeper Cu-Ag Mineralization and Extends Mineralized Strike by 600m to 3.2km

Group Eleven Resources Corp. (TSX-V: ZNG) (OTCQB: GRLVF) (FSE: 3GE) is pleased to announce new assay... READ MORE

April 16, 2026

Argenta Silver Step-Out Drilling Intersects 679 g/t Ag over 13.5m, including 1,163 g/t Ag over 4.0m, Resource Continuity and Expansion Continues

Argenta Silver Corp. (TSX-V: AGAG) (OTCQX: AGAGF) (FSE: T1K) is pleased to report the third set of ... READ MORE

April 16, 2026

Copyright 2026 The Prospector News